ML15349A834

From kanterella
Jump to navigation Jump to search
EN-15-032, Enforcement Notification Regarding Issuance of a Confirmatory Order for Northern States Power Company, Minnesota, Monticello Nuclear Generating Plant, Docket Number 50-263 (EA-14-193)
ML15349A834
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 12/15/2015
From: Wray J
NRC/OE
To:
Northern States Power Co
References
EA-14-193, EN-15-032
Download: ML15349A834 (2)


Text

December 15, 2015 EN 15-032 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: Northern States Power Company, Minnesota EA-14-193 Monticello Nuclear Generating Plant Docket No. 05000263

Subject:

ISSUANCE OF CONFIRMATORY ORDER This is to inform the Commission that a publicly available Confirmatory Order will be issued on or about December 21, 2015, to Northern States Power Company, Minnesota (licensee) confirming commitments reached as part of an alternative dispute resolution (ADR) settlement agreement addressing violations identified through an investigation at Monticello Nuclear Generating Plant (Monticello).

The violations involved two contractor technicians at Monticello who deliberately failed to perform nondestructive examinations (NDEs) on the Dry Shielded Canisters (DSCs) in accordance with procedural requirements, and the falsification of records when recording the NDE results, contrary to the requirements in Title 10 of the Code of Federal Regulations (10 CFR) 72.158, Control of special processes, 10 CFR 72.11, Completeness and accuracy of information, and 10 CFR 72.154(c), Control of purchased material, equipment, and services.

In a letter dated July 23, 2015, the NRC provided the licensee with the results of the investigation, and offered the opportunity to provide a written response to the apparent violations, to attend a Predecisional Enforcement Conference, or to request ADR with the NRC.

In response to the NRC letter, the licensee requested ADR. An ADR mediation session was held on October 15, 2015, and a preliminary settlement agreement was reached. The settlement actions include, but are not limited to: (1) restore compliance for all affected DSCs, (2) revise procedures to require direct licensee oversight for contractors performing NDE on DSC closure welds, (3) present at an industry forum to discuss the events that led to the confirmatory order, (4) submit an article to an industry publication describing the circumstances of the violations, the root and contributing causes, and the corrective actions, and (5) assess the effectiveness of improvements in the oversight of supplemental workers.

It should be noted that the licensee has not been specifically informed of this enforcement action. The schedule of issuance and notification is:

Mailing of Notice December 21, 2015 Telephone Notification of Licensee December 21, 2015 The State of Minnesota will be notified.

CONTACTS: Kyle Hanley, OE/EB John Wray, OE/EB (301) 415-1975 (301) 415-1288

DISTRIBUTION: EN-15-032 December 15, 2015 OWFN OWFN TWFN 3WFN Regional Offices Chairman Burns EDO OCFO NSIR RI RII Comm. Svinicki DEDR OIS OP Center RIII RIV Comm. Ostendorff DEDMRT RES Comm. Baran OE ACRS MAIL SECY OGC NRO ADAMS OCA NRR NMSS OE staff OPA OI OIP OIG Electronic DISTRIBUTION:

P. Holahan, OE N. Hilton, OE K. Hanley, OE OE r/f EN binder X PUBLIC X NON-SENSITIVE ADAMS ACCESSION NO.: ML15349A834 OFFICE OE:ES OE:BC NAME KHanley JWray DATE 12/15/2015 12/15/2015 OFFICIAL RECORD COPY

December 15, 2015 EN 15-032 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee: Northern States Power Company, Minnesota EA-14-193 Monticello Nuclear Generating Plant Docket No. 05000263

Subject:

ISSUANCE OF CONFIRMATORY ORDER This is to inform the Commission that a publicly available Confirmatory Order will be issued on or about December 21, 2015, to Northern States Power Company, Minnesota (licensee) confirming commitments reached as part of an alternative dispute resolution (ADR) settlement agreement addressing violations identified through an investigation at Monticello Nuclear Generating Plant (Monticello).

The violations involved two contractor technicians at Monticello who deliberately failed to perform nondestructive examinations (NDEs) on the Dry Shielded Canisters (DSCs) in accordance with procedural requirements, and the falsification of records when recording the NDE results, contrary to the requirements in Title 10 of the Code of Federal Regulations (10 CFR) 72.158, Control of special processes, 10 CFR 72.11, Completeness and accuracy of information, and 10 CFR 72.154(c), Control of purchased material, equipment, and services.

In a letter dated July 23, 2015, the NRC provided the licensee with the results of the investigation, and offered the opportunity to provide a written response to the apparent violations, to attend a Predecisional Enforcement Conference, or to request ADR with the NRC.

In response to the NRC letter, the licensee requested ADR. An ADR mediation session was held on October 15, 2015, and a preliminary settlement agreement was reached. The settlement actions include, but are not limited to: (1) restore compliance for all affected DSCs, (2) revise procedures to require direct licensee oversight for contractors performing NDE on DSC closure welds, (3) present at an industry forum to discuss the events that led to the confirmatory order, (4) submit an article to an industry publication describing the circumstances of the violations, the root and contributing causes, and the corrective actions, and (5) assess the effectiveness of improvements in the oversight of supplemental workers.

It should be noted that the licensee has not been specifically informed of this enforcement action. The schedule of issuance and notification is:

Mailing of Notice December 21, 2015 Telephone Notification of Licensee December 21, 2015 The State of Minnesota will be notified.

CONTACTS: Kyle Hanley, OE/EB John Wray, OE/EB (301) 415-1975 (301) 415-1288

DISTRIBUTION: EN-15-032 December 15, 2015 OWFN OWFN TWFN 3WFN Regional Offices Chairman Burns EDO OCFO NSIR RI RII Comm. Svinicki DEDR OIS OP Center RIII RIV Comm. Ostendorff DEDMRT RES Comm. Baran OE ACRS MAIL SECY OGC NRO ADAMS OCA NRR NMSS OE staff OPA OI OIP OIG Electronic DISTRIBUTION:

P. Holahan, OE N. Hilton, OE K. Hanley, OE OE r/f EN binder X PUBLIC X NON-SENSITIVE ADAMS ACCESSION NO.: ML15349A834 OFFICE OE:ES OE:BC NAME KHanley JWray DATE 12/15/2015 12/15/2015 OFFICIAL RECORD COPY