ML15348A292

From kanterella
Jump to navigation Jump to search
License Termination Plan Presentation
ML15348A292
Person / Time
Site: La Crosse  File:Dairyland Power Cooperative icon.png
Issue date: 12/07/2015
From:
Dairyland Power Cooperative
To:
Office of Nuclear Material Safety and Safeguards
Marlayna Vaaler, 301-415-3178
Shared Package
ML15348A285 List:
References
Download: ML15348A292 (22)


Text

La Crosse Boiling Water Reactor License Termination Plan Presentation to NRC Staff December 7, 2015

Topics for Discussion



Site Overview



Current Status of LACBWR Restoration Project



Project Milestones



Characterization Summary and Survey Unit Classification



Groundwater



Radionuclides of Concern



End State Description



Demonstrating Compliance with Radiological Criteria



Final Status Surveys and Source Term Surveys



Supplement to Environmental Report



Q & A

Site Overview

 BWR (50MWe)

 AEC demonstration reactor

 Owned by Dairyland Power Cooperative (DPC)

 Operated from 1967 to 1987

 Licensed site shared with operational fossil plant

Decommissioning to Date

 LACBWR staff performed limited dismantlement work between 1996 and 2004

 In 2005, efforts shifted to RPV and Class B/C waste removal that was successfully completed in 2007

 EnergySolutions (ES) performed the removal and disposal of the RPV and B/C waste at the Barnwell disposal facility

 Fuel transfer to dry storage commenced in 2008 and was completed September 19, 2012

 Additional dismantlement work completed in 2012 - 2014 including removal of fuel racks and completion of main turbine generator component removal

General Project Milestones



Q1/2016 Submit LTP to NRC



Q2/2016 License Transfer from DPC to LaCrosseSolutions



Q2/2016 Mobilization Complete



Q3/2016 Stack Demolition Complete



Q3/2017 LTP Approval by NRC



Q3/2017 Component Removal Complete



Q4/2017 Building Demolition Complete



Q4/2018 Transportation and Disposal Complete



Q4/2018 Site Remediation Complete



Q4/2018 Final Radiation Surveys Complete



Q1/2019 Site Restoration Complete



Q1/2019 Submit Remaining FRS Reports to NRC



Q1/2019 Submit License Transfer from LaCrosseSolutions to DPC



Q1/2020 License Transfer to DPC Approved by NRC



Q1/2020 LACBWR License Termination Approval by NRC

Characterization Summary



Historical Site Assessment performed in August 1999



October of 2005, DPC performed limited characterization of LSE prior to placing in SAFSTOR condition



October 2014 through August 2015, more detailed characterization of entire 165.3 acre licensed site for LTP development and accelerated decommissioning



Non-Impacted and Impacted Land Areas



Surface/subsurface soil, asphalt, concrete and coal ash samples



Angle coring (GeoProbe) beneath Turbine Building (drains)



Gamma scans using 2x2 NaI detector



87 of 163.5 acres deemed Non-Impacted (G-3 land and across highway)



Non-Impacted Structures



Structures associated with G-3 Coal Plant verified as Non-Impacted



Based on alpha/beta-gamma proportional detector scan/static measurements biased toward roofs, entryways, travel paths, low points, etc.



Gamma spectroscopy of roof material and other bulk materials



G-3 High Pressure Service Water and LACBWR Water Well buried Piping also designated as non-impacted based on operating history



Impacted Structures



Obtained basic radiological data on all above-grade structures



Obtained concrete core samples from basement floors/walls



Continuing characterization



Soils under/adjacent to structures, soils under concrete or asphalt, underlying concrete in RB after liner removal, currently inaccessible structure surfaces, interiors of buried pipe

Survey Unit Classifications

Groundwater Evaluation

 Preparation of Hydrogeological Conceptual Site Model (Haley &

Aldrich)

 Preparation of Hydrogeological Investigation Report for the La Crosse Boiling Water Reactor (Haley & Aldrich)

 Groundwater is encountered 20 BGL and is in direct communication with the Mississippi River

 On-going monitoring well sample collection and analysis Very low concentrations of plant-derived radionuclide's identified in groundwater near Turbine Building

Groundwater Evaluation

Radionuclides of Concern

 NUREG/CR-3474, NUREG/CR-4289, WINCO-1191 reviewed

 Eliminated noble gases, theoretical neutron activation products with an abundance less than 0.01% total activity and radionuclides with half-lives less than two years

 An initial suite of 22 radionuclides produced for use in characterization

 Based on radionuclide mixture from characterization cores and applying dose modeling results, the insignificant contributors were eliminated (those representing aggregate dose less than10% of the 25 mrem/yr criteria)

 Remaining ROCs and mixtures and percent of total activity :

Cs-137 / 97.6%

Co-60 / 1.4%

Sr-90 / 1.0%

Dose Modeling Objectives NUREG-1757, Volume 2, Revision 1, Appendix I, Section 1.2.3 states that, generally, the licensees dose modeling should have one of the following objectives:

Develop DCGLs commensurate with demonstrating compliance with the dose-based release criterion, and then demonstrate through FSS that residual radioactivity concentrations at the site are equal to or below the DCGLs.

Assess dose associated with actual concentrations of residual radioactivity distributed across the site to determine whether the concentrations will result in a dose that is not equal to or below the regulatory dose criterion.

Surface and Sub-Surface Soil Buried Piping Backfilled Basements/Structures Groundwater FSS STS

End State Structures

End State Basement Structure

Below Ground Basements/Structures to Remain in End State Basement/Structure Material remaining Floor and Wall Surface Area (m2)

Floor Elevation (feet AMSL)

Reactor Building Concrete 511.54 612 Waste Treatment Building Concrete 101.90 630 Waste Gas Tank Vault Concrete 460.04 621 Remaining Structures Piping and Ventilation Tunnels Concrete 177.07 629 Reactor/Generator Plant Concrete 359.59 629 Chimney Slab Concrete 117.86 635 Turbine Sump Concrete 5.64 618 Turbine Pit Concrete 7.09 618

Basement Fill Model

 Dose from residual radioactivity remaining in backfilled Basements calculated using the Basement Fill Model (BFM)

 End State Basements demolished to three feet below grade and physically altered to a condition where it is implausible that future land use would include excavating fill material and occupying backfilled Basements

 BFM conceptual model differs from Zion:

 basements are small

 generally above water table

 insufficient volume below water table to support a well installed directly into basement

 source term modeled as a layer of sub-surface soil contamination with no credit for structure resistance to flow

 Average Member of Critical Group (AMCG) at LACBWR is the Industrial Worker

Basement Fill Model

 The BFM conceptual model includes two source term geometries



the In situ geometry where the concrete remains in the as-left configuration at the time of license termination (including Drilling Spoils scenario) and



the Excavation geometry where the concrete is excavated and brought to the surface.

BFM Industrial Use Exposure Pathways

 Direct exposure to external radiation in as-left End State geometry

 Inhalation of airborne radioactivity in as-left End State geometry

 Ingestion of concrete or fill material in as-left End State geometry

 Ingestion of water from onsite well

 Direct exposure, inhalation dose and ingestion dose from contaminated drilling spoils brought to the surface during installation of the onsite well that contacts basement concrete floor

 Direct exposure, inhalation dose and ingestion dose from concrete that is brought to the surface by excavation The agricultural and gardening pathways are not applicable to industrial land use. The meat, grain and vegetable ingestion pathways are therefore not included

Source Term Surveys



ISOCS Instrumentation used for Basements

 Determines total inventory with depth in concrete

 Allows remote access; minimizes hands on scan/static surveys or sampling (coring)

 Nominal FOV of (10-30 m2)



STS Survey Units

 BFM not sensitive to activity levels and size of elevated areas

 Each footprint (area) broken into survey units based on access, physical configuration and contamination potential Performed on Basement Surfaces (No Embedded Piping or Penetrations at LACBWR)

Source Term Surveys

 Areal Coverage

 Estimated mean activity and standard deviation derived from characterization and/or remediation data

 Graded approach similar to MARSSIM but based on expected fraction of allowable hypothetical total inventory level for each basement rather than expected fraction of a DCGL

 Data Quality Objectives (increase sample size if necessary based on statistical design)

 Locations randomly chosen

 Data Assessment

 Perform Sign Test at Type I error of 5%

 If the Sign Test passes then the STS results are acceptable and the mean value is used for source term in the BFM compliance calculation

 If the Sign test fails then additional remediation will be performed and the STS is re-designed and performed again

Final Status Surveys



Planning, designing, implementing and evaluating the FSS done in accordance with MARSSIM



Survey Packages developed for each Survey Unit



Turnover, Isolation and Control Measures



Data Quality Objectives



Instrument Sensitivity



Survey Methods: scan/static measurements, volumetric sampling of soil and buried piping



Data Assessment including application of Statistical Tests



Quality Assurance



Reporting (FSS Survey Unit Release Records/Final Reports)

Performed on impacted Open Land Areas (surface/subsurface soil/roadways) and Buried Piping that remain at time of License Termination; Above grade remaining buildings and misc.

structures (duct banks) will undergo Unconditional Release Survey with Default DCGLs

Supplement to Environmental Report

 Review of generic and site-specific environmental impacts

 Evaluation followed approach outlined in NUREG-0586

 All environmental impacts considered to be Small

Questions?