2015 Fermi Power Plant Initial License Examination Form ES-201-1
ML15287A289
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 10/13/2015
From:
Division of Reactor Safety III
To:
Detroit Edison, Co
Zoia, C D
Shared Package
ML15268A032 List:
References
Download: ML15287A289 (1)


Text

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Fermi Power Plant, Unit 2 Date of Examination: 8/24-28/2015 Developed by: Written:

Facility NRC

//

Operating Facility NRC Target Date*

Task Description (Reference)

Chief Examiners Initials

-180

1.

Examination administration date confirmed (C.1.a; C.2.a and b)

MEB

-150

2.

NRC examiners and facility contact assigned (C.1.d; C.2.e)

MEB

-150

3.

Facility contact briefed on security and other requirements (C.2.c)

MEB

-150

4.

Corporate notification letter sent (C.2.d)

MEB

[-120]

5.

Reference material due (C.1.e; C.3.c; Attachment 3)

N/A

{-90}

6.

Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1, ES-401-1/2, ES-401N-1/2, ES-401-3, ES-401N-3, ES-401-4, and ES-401N-4, as applicable (C.1.e and f; C.3.d)

MEB

{-85}

7.

Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)

MEB

{-60}

8.

Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, ES-401N-6, and any Form ES-201-2, ES-201-3, ES-301-1, or ES-301-2 updates), and reference materials due (C.1.e, f, g and h; C.3.d)

MEB

-45

9.

Written exam and operating test reviews completed. (C.3.f)

MEB

-30

10.

Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202)

MEB

-21

11.

Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f)

MEB

-21

12.

Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g)

MEB

-14

13.

Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202)

MEB

-14

14.

Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h)

MEB

-7

15.

Facility licensee management queried regarding the licensees views on the examination. (C.2 j)

MEB

-7

16.

Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; ; ES-202, C.2.e; ES-204)

MEB

-7

17.

Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k)

MEB

-7

18.

Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i)

MEB

  • Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.

ES-201 Examination Preparation Checklist Form ES-201-1 Facility: Fermi Power Plant, Unit 2 Date of Examination: 8/24-28/2015 Developed by: Written:

Facility NRC

//

Operating Facility NRC Target Date*

Task Description (Reference)

Chief Examiners Initials

-180

1.

Examination administration date confirmed (C.1.a; C.2.a and b)

MEB

-150

2.

NRC examiners and facility contact assigned (C.1.d; C.2.e)

MEB

-150

3.

Facility contact briefed on security and other requirements (C.2.c)

MEB

-150

4.

Corporate notification letter sent (C.2.d)

MEB

[-120]

5.

Reference material due (C.1.e; C.3.c; Attachment 3)

N/A

{-90}

6.

Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1, ES-401-1/2, ES-401N-1/2, ES-401-3, ES-401N-3, ES-401-4, and ES-401N-4, as applicable (C.1.e and f; C.3.d)

MEB

{-85}

7.

Examination outline(s) reviewed by NRC and feedback provided to facility licensee (C.2.h; C.3.e)

MEB

{-60}

8.

Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6, ES-401N-6, and any Form ES-201-2, ES-201-3, ES-301-1, or ES-301-2 updates), and reference materials due (C.1.e, f, g and h; C.3.d)

MEB

-45

9.

Written exam and operating test reviews completed. (C.3.f)

MEB

-30

10.

Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; ES-202)

MEB

-21

11.

Examination approved by NRC supervisor for facility licensee review (C.2.h; C.3.f)

MEB

-21

12.

Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g)

MEB

-14

13.

Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; ES-202)

MEB

-14

14.

Written examinations and operating tests approved by NRC supervisor (C.2.i; C.3.h)

MEB

-7

15.

Facility licensee management queried regarding the licensees views on the examination. (C.2 j)

MEB

-7

16.

Final applications reviewed; 1 or 2 (if >10) applications audited to confirm qualifications / eligibility; and examination approval and waiver letters sent (C.2.i; ; ES-202, C.2.e; ES-204)

MEB

-7

17.

Proctoring/written exam administration guidelines reviewed with facility licensee (C.3.k)

MEB

-7

18.

Approved scenarios, job performance measures, and questions distributed to NRC examiners (C.3.i)

MEB

  • Target dates are generally based on facility-prepared examinations and are keyed to the examination date identified in the corporate notification letter. They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.

[Applies only] {Does not apply} to examinations prepared by the NRC.