MONTHYEARML24197A0622024-07-15015 July 2024 Retake Exam Form 5.1-1 Postexamination Check Sheet IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A0992024-06-14014 June 2024 Retake Exam Form 1.3-1 Examination Security Agreement ML24173A1002024-06-14014 June 2024 Retake Exam Form 2.1-1 Examination Preparation Checklist ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24173A0862024-06-0505 June 2024 Retake Exam Form 2.3-2 Operating Test Quality Checklist NRC-24-0038, Retake Exam Proposed Exam Submittal Letter2024-05-22022 May 2024 Retake Exam Proposed Exam Submittal Letter NRC-24-0031, Retake Exam Outline Submittal Letter2024-04-22022 April 2024 Retake Exam Outline Submittal Letter ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 ML24149A1102024-03-13013 March 2024 Form 1.3-1, Examination Security ML24149A1152024-03-13013 March 2024 Form 5.1-1 Post Examination Check Sheet (Fermi 2024) ML24149A1132024-03-13013 March 2024 Form 2.1-1, Examination Preparation Checklist (Fermi 2024) ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 ML24149A0702024-02-14014 February 2024 Form 3.4-1 Events and Evolutions Checklist (Fermi 2024 Ile - Final) ML24149A0682024-02-14014 February 2024 NRC Form 2.3-1 Examination Outline Quality Checklist ML24149A0862024-01-0505 January 2024 Form 2.3-4, Written Exam Quality Checklist, Fermi 2024 Ile ML24149A0852024-01-0505 January 2024 Form 2.3-2, Operating Test Quality Checklist, Fermi 2024 Ile NRC-23-0078, Initial Licensed Operator Exam Materials - NRC Cover Letter 75-Day2023-12-13013 December 2023 Initial Licensed Operator Exam Materials - NRC Cover Letter 75-Day NRC-23-0067, NRC-23-0067 signed-150 Day Outline Submittal2023-09-29029 September 2023 NRC-23-0067 signed-150 Day Outline Submittal IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21326A1532021-06-16016 June 2021 ES-401-1 and ES-401-3_Initial ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A0922021-06-16016 June 2021 ES-301-6 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1202021-06-16016 June 2021 ES-201-2 2024-07-09
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24197A0622024-07-15015 July 2024 Retake Exam Form 5.1-1 Postexamination Check Sheet IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A0992024-06-14014 June 2024 Retake Exam Form 1.3-1 Examination Security Agreement ML24173A1002024-06-14014 June 2024 Retake Exam Form 2.1-1 Examination Preparation Checklist ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24173A0862024-06-0505 June 2024 Retake Exam Form 2.3-2 Operating Test Quality Checklist NRC-24-0038, Retake Exam Proposed Exam Submittal Letter2024-05-22022 May 2024 Retake Exam Proposed Exam Submittal Letter NRC-24-0031, Retake Exam Outline Submittal Letter2024-04-22022 April 2024 Retake Exam Outline Submittal Letter ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 ML24149A1102024-03-13013 March 2024 Form 1.3-1, Examination Security ML24149A1152024-03-13013 March 2024 Form 5.1-1 Post Examination Check Sheet (Fermi 2024) ML24149A1132024-03-13013 March 2024 Form 2.1-1, Examination Preparation Checklist (Fermi 2024) ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 ML24149A0702024-02-14014 February 2024 Form 3.4-1 Events and Evolutions Checklist (Fermi 2024 Ile - Final) ML24149A0682024-02-14014 February 2024 NRC Form 2.3-1 Examination Outline Quality Checklist ML24149A0862024-01-0505 January 2024 Form 2.3-4, Written Exam Quality Checklist, Fermi 2024 Ile ML24149A0852024-01-0505 January 2024 Form 2.3-2, Operating Test Quality Checklist, Fermi 2024 Ile NRC-23-0078, Initial Licensed Operator Exam Materials - NRC Cover Letter 75-Day2023-12-13013 December 2023 Initial Licensed Operator Exam Materials - NRC Cover Letter 75-Day NRC-23-0067, NRC-23-0067 signed-150 Day Outline Submittal2023-09-29029 September 2023 NRC-23-0067 signed-150 Day Outline Submittal IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23213A0302023-08-11011 August 2023 Form 5.1-1 Postexamination Check Sheet ML23212A8732023-07-31031 July 2023 Form 1.3-1 Examination Security Checklist ML23200A2552023-06-28028 June 2023 Post-Exam Letter with Comments and Exam Analysis ML23200A2182023-06-28028 June 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Final ML23200A2572023-06-19019 June 2023 Form 2.1-1 Examination Prep Checklist ML23200A2562023-06-19019 June 2023 IP 21 Operator Licensing Exam Schedule ML23166A0892023-06-15015 June 2023 Operator Licensing Examination Approval Fermi Power Plant, June 2023 ML23200A1852023-06-0202 June 2023 Form 2.3-2 Operating Test Quality Checklist ML23200A1862023-06-0202 June 2023 Form 2.3-4 Written Exam Quality Checklist ML23200A1842023-04-0606 April 2023 Proposed Exam Submittal Letter ML23074A1972023-03-16016 March 2023 Confirmation of Initial License Examination February 2024 ML23200A2212023-02-0808 February 2023 Form 2.3-1 Outline Quality Checklist ML23200A2162023-01-20020 January 2023 Outline Submittal Letter ML23200A2172023-01-20020 January 2023 Form 3.4-1 Scenario Events & Evolutions Checklist RO & SRO Draft ML22322A1082022-11-18018 November 2022 Confirmation of Initial License Examination ML21258A0602021-09-15015 September 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21326A1532021-06-16016 June 2021 ES-401-1 and ES-401-3_Initial ML21327A4272021-06-16016 June 2021 Post Exam Submittal Letter ML21327A4252021-06-16016 June 2021 ES-403-1 ML21327A4242021-06-16016 June 2021 ES-201-3 ML21327A4212021-06-16016 June 2021 ES-201-1 ML21327A1062021-06-16016 June 2021 Proposed Exam Submittal Letter ML21327A1042021-06-16016 June 2021 ES-301-4 ML21327A0952021-06-16016 June 2021 ES-301-3 ML21327A0922021-06-16016 June 2021 ES-301-6 ML21326A1242021-06-16016 June 2021 Licensee Outline Submittal Letter ML21326A1212021-06-16016 June 2021 ES-301-5 ML21326A1202021-06-16016 June 2021 ES-201-2 2024-07-09
[Table view] |
Text
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Fermi 2 Date of Examination: 8/24/2015 Exam Level: RO SRO-I SRO-U Operating Test Number: 2015-1 Control Room Systems 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U Safety System / JPM Title Type Code*
Function
- a. Perform Rod Pattern Adjustment with Difficult Rod Movement A,D,E,P,S SF-1
[K/A 201003 A2.01] 3.4/3.6 315-0110-406
- b. Startup SBFW System after an RFP Trip A,D,S SF-2
[K/A 259001 A4.02] 3.9/3.7 315-0118-002
- c. Perform Main Steam Line Isolation Functional Test A,D,P,S SF-3
[K/A 239001 A4.01] 4.2/4.0 315-0105-402
- d. Place Div 1 RHR in SDC, Following Removal For <2 Hrs A,D,L,S SF-4
[K/A 205000 A4.01] 3.7/3.7 315-0141-405
- e. Vent the Drywell using 29.ESP.07 N,S SF-5
[K/A 295024 EA1.14] 3.4/3.5 315-0119-002
- f. Loss 64B and EDG 11 Fails to Start EN,D,S SF-6
[K/A 262001 A2.04] 3.8/4.2 315-0158-401
- g. Jockey Fire Pump failure, start of Electric Fire Pump N,S SF-8
[K/A 286000 A2.06] 3.1/3.2 315-0172-001
- h. Respond to Refuel Floor High Radiation A,N,P,L,S SF-9
[K/A 272000 A2.12] 3.3/4.0 315-0150-402 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. Defeat ARI Logic Trips E,D SF-1
[K/A 295037 EA1.03] 4.1/4.1 802-3006-305
- j. Manually Initiate EDG CO2 - Alt Path E,D SF-8
[K/A 286000 A2.08] 3.2/3.3 315-0272-401
- k. Shutdown the Plant from the RPS Cabinet A,E,D,R SF-7
[K/A 295016 AA1.01] 3.8/3.9 802-2001-216
- All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank <9 / <8 / <4 (E)mergency or abnormal in-plant >1 / >1 / >1 (EN)gineered safety feature >1 / >1 / > 1 (control room system)
(L)ow-Power / Shutdown >1 / >1 / >1 (N)ew or (M)odified from bank including 1(A) >2 / >2 / >1 (P)revious 2 exams <3 / <3 / < 2 (randomly selected)
(R)CA >1 / >1 / >1 (S)imulator
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Fermi 2 Date of Examination: 8/24/2015 Exam Level: RO SRO-I SRO-U Operating Test Number: 2015-1 Control Room Systems 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U Safety System / JPM Title Type Code*
Function
- e. Vent the Drywell using 29.ESP.07 N,S SF-5
[K/A 295024 EA1.14] 3.4/3.5 315-0119-002
- f. Loss 64B and EDG 11 Fails to Start EN,D,S SF-6
[K/A 262001 A2.04] 3.8/4.2 315-0158-401
- h. Respond to Refuel Floor High Radiation A,N,P,L,S SF-9
[K/A 272000 A2.12] 3.3/4.0 315-0150-402 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. Defeat ARI Logic Trips E,D SF-1
[K/A 295037 EA1.03] 4.1/4.1 802-3006-305
- k. Shutdown the Plant from the RPS Cabinet A,E,D,R SF-7
[K/A 295016 AA1.01] 3.8/3.9 802-2001-216
- All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank <9 / <8 / <4 (E)mergency or abnormal in-plant >1 / >1 / >1 (EN)gineered safety feature >1 / >1 / > 1 (control room system)
(L)ow-Power / Shutdown >1 / >1 / >1 (N)ew or (M)odified from bank including 1(A) >2 / >2 / >1 (P)revious 2 exams <3 / <3 / < 2 (randomly selected)
(R)CA >1 / >1 / >1 (S)imulator
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Fermi 2 Date of Examination: 8/24/2015 Exam Level: RO SRO-I SRO-U Operating Test Number: 2015-1 Control Room Systems 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U Safety System / JPM Title Type Code*
Function
- a. Perform Rod Pattern Adjustment with Difficult Rod Movement A,D,E,P,S SF-1
[K/A 201003 A2.01] 3.4/3.6 315-0110-406
- b. Startup SBFW System after an RFP Trip A,D,S SF-2
[K/A 259001 A4.02] 3.9/3.7 315-0118-002
- c. Perform Main Steam Line Isolation Functional Test A,D,P,S SF-3
[K/A 239001 A4.01] 4.2/4.0 315-0105-402
- d. Place Div 1 RHR in SDC, Following Removal For <2 Hrs A,D,L,S SF-4
[K/A 205000 A4.01] 3.7/3.7 315-0141-405
- e. Vent the Drywell using 29.ESP.07 N,S SF-5
[K/A 295024 EA1.14] 3.4/3.5 315-0119-002
- f. Loss 64B and EDG 11 Fails to Start EN,D,S SF-6
[K/A 262001 A2.04] 3.8/4.2 315-0158-401
- g. Jockey Fire Pump failure, start of Electric Fire Pump N,S SF-8
[K/A 286000 A2.06] 3.1/3.2 315-0172-001
- h. Respond to Refuel Floor High Radiation A,N,P,L,S SF-9
[K/A 272000 A2.12] 3.3/4.0 315-0150-402 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. Defeat ARI Logic Trips E,D SF-1
[K/A 295037 EA1.03] 4.1/4.1 802-3006-305
- j. Manually Initiate EDG CO2 - Alt Path E,D SF-8
[K/A 286000 A2.08] 3.2/3.3 315-0272-401
- k. Shutdown the Plant from the RPS Cabinet A,E,D,R SF-7
[K/A 295016 AA1.01] 3.8/3.9 802-2001-216
- All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank <9 / <8 / <4 (E)mergency or abnormal in-plant >1 / >1 / >1 (EN)gineered safety feature >1 / >1 / > 1 (control room system)
(L)ow-Power / Shutdown >1 / >1 / >1 (N)ew or (M)odified from bank including 1(A) >2 / >2 / >1 (P)revious 2 exams <3 / <3 / < 2 (randomly selected)
(R)CA >1 / >1 / >1 (S)imulator
ES-301 Control Room/In-Plant Systems Outline Form ES-301-2 Facility: Fermi 2 Date of Examination: 8/24/2015 Exam Level: RO SRO-I SRO-U Operating Test Number: 2015-1 Control Room Systems 8 for RO; 7 for SRO-I; 2 or 3 for SRO-U Safety System / JPM Title Type Code*
Function
- e. Vent the Drywell using 29.ESP.07 N,S SF-5
[K/A 295024 EA1.14] 3.4/3.5 315-0119-002
- f. Loss 64B and EDG 11 Fails to Start EN,D,S SF-6
[K/A 262001 A2.04] 3.8/4.2 315-0158-401
- h. Respond to Refuel Floor High Radiation A,N,P,L,S SF-9
[K/A 272000 A2.12] 3.3/4.0 315-0150-402 In-Plant Systems (3 for RO); (3 for SRO-I); (3 or 2 for SRO-U)
- i. Defeat ARI Logic Trips E,D SF-1
[K/A 295037 EA1.03] 4.1/4.1 802-3006-305
- k. Shutdown the Plant from the RPS Cabinet A,E,D,R SF-7
[K/A 295016 AA1.01] 3.8/3.9 802-2001-216
- All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions; all 5 SRO-U systems must serve different safety functions; in-plant systems and functions may overlap those tested in the control room.
- Type Codes Criteria for RO / SRO-I / SRO-U (A)lternate path 4-6 / 4-6 / 2-3 (C)ontrol room (D)irect from bank <9 / <8 / <4 (E)mergency or abnormal in-plant >1 / >1 / >1 (EN)gineered safety feature >1 / >1 / > 1 (control room system)
(L)ow-Power / Shutdown >1 / >1 / >1 (N)ew or (M)odified from bank including 1(A) >2 / >2 / >1 (P)revious 2 exams <3 / <3 / < 2 (randomly selected)
(R)CA >1 / >1 / >1 (S)imulator