ML15280A284

From kanterella
Jump to navigation Jump to search

Summary of Meeting with Pacific Gas & Electric to Discuss Diablo Canyon, Units 1 and 2 Request to Adopt National Fire Protection Association NFPA 805, Performance-Based Standard for Fire Protection for LWR Generating Plants (2001 Edition),
ML15280A284
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/20/2015
From: Siva Lingam
Plant Licensing Branch IV
To: Halpin E
Office of Nuclear Reactor Regulation, Pacific Gas & Electric Co
Lingam S
References
CAC MF2333, CAC MF2334
Download: ML15280A284 (4)


Text

LICENSEE:

Pacific Gas and Electric Company FACILITY:

Diablo Canyon Power Plant, Unit Nos. 1 and 2

SUBJECT:

SUMMARY

OF AUGUST 31, 2015, TELECONFERENCE MEETING WITH PACIFIC GAS AND ELECTRIC COMPANY ON LICENSE AMENDMENT REQUEST.TO ADOPT NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 FOR DIABLO CANYON POWER PLANT, UNIT NOS. 1AND2 (CAC NOS. MF2333 AND MF2334)

On August 31, 2015, a Category 1 teleconference public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Pacific Gas and Electric Company (PG&E, the licensee) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the teleconference meeting was to discuss the license amendment request (LAA) submitted by PG&E on June 26, 2013, as supplemented, to adopt a new fire protection licensing basis for Diablo Canyon Power Plant (DCPP), Unit Nos. 1 and 2, which complies with the requirements in paragraphs 50.48(a) and (c) of Title 1 O of the Code of Federal Regulations (1 O CFR) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13196A139). Specifically, DCPP, Unit Nos. 1 and 2, would transition to a fire protection licensing basis based on the National Fire Protection Association Standard 805 (NFPA 805) Performance-Based Standard for Fire Protection For Light Water Reactor Generating Plants (2001 Edition). 1 The meeting notice and agenda dated August 14, 2015, are available at ADAMS Accession No. ML15226A306. A list of attendees is provided in the Enclosure.

The teleconference meeting was a publicly.noticed teleconference meeting held to discuss PG&E's request for additional information (RAI) response letter dated February 25, 2015 (ADAMS Accession No. ML15056A774). The main topic of the meeting was clarification of the relationship between NRC acceptance of the Westinghouse Topical Report for quantitative credit of the reactor coolant pump (RCP) seals in fire probabilistic risk assessment (PAA) and 1 Copies of NFPA 805 may be purchased from the NFPA Customer Service Department, 1 Batterymarch Park, P.O. Box 9101, Quincy, MA 02269-9101 and in PDF format through the NFPA Online Catalog (http://www.nfpa.org) or by calling 1-800-344-3555 or (617) 770-3000. Copies are also available for inspection at the NRC Library, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland 20852-2738, and at the NRC Public Document Room, Building One White Flint North, Room 01-F15, 11555 Rockville Pike, Rockville, Maryland 20852-2738. Copies are also available at the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call (202) 7 41-6030, or go to:

http://www.archives.gov/federal register/code of federal requlations/ibr locations.html.

performance of the PAA evaluations to support implementation of the NFPA 805 amendment.

Highlights from this meeting include the following:

Discussion of NRG PAA RAI 3 related to RCP seals, and the licensee's schedule to respond to this RAI.

The results of the Westinghouse SHIELD tests for the RCP seal issue will be useful in the review of the licensee's response to RAI 3.

The licensee mentioned that testing of Beaver Valley RCP seals by Westinghouse will be performed by October 15, 2015.

Two members of the public were in attendance for the teleconference meeting. One of the public members, Ms. Thomas, requested material that will enable her to understand NFPA 805 LAA, and the Project Manager agreed to mail the appropriate material to her home address. No public meeting feedback forms were submitted.

Please direct any inquiries to me at 301-415-1564 or at Siva.Linqam@nrc.gov.

Docket Nos. 50-275 and 50-323

Enclosure:

List of Attendees cc w/encl: Distribution via Listserv

~~(]*~

Siva P. Lingam, Project Manager Plant Licensing Branch IV-1 Division of Operating Reactor Licensing

  • Office of Nuclear Reactor Regulation

LIST OF ATTENDEES AUGUST 31, 2015, TELECONFERENCE MEETING WITH PACIFIC GAS AND ELECTRIC COMPANY NFPA 805 LAR FOR DIABLO CANYON POWER PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-275 AND 50-323 NAME P.Soenen M. Richardson B. Harris P. Bemis R. Dyer M. Markley M. Khanna A Klein K. Green L. Fields S. Dinsmore H. Barrett C. Moulton S. Lingam R. Thomas Mr. Alylan ORGANIZATION Pacific Gas and Electric Pacific Gas and Electric Pacific Gas and Electric Pacific Gas and Electric Pacific Gas and Electric Nuclear Regulatory Commission (NRC)

NRC NRC NRC NRC NRC NRC NRC NRC Public Member Public Member Enclosure

Meeting Notice ML15226A306; Meetmg OFFICE NRR/DORULPL4-1 /PM NRR/DORULPL4-1 /LA NAME Sling am JBurkhardt DATE 10/13/15 10/13/15 OFFICE NRR/DORULPL4-1 /BC NRR/DORULPL4-1 /PM NAME MMarkley Slingam DATE 10/20/15 10/20/15