Discusses Licensee Response to NRC Bulletin 88-11, Pressurizer Surge Line Thermal Stratification, for Plant. Issue Re Stress Index Under Generic Review & No Plant Specific Issues Identified
ML15260A285
Person / Time
Site: Oconee  
Issue date: 04/17/1992
From: Wiens L
Office of Nuclear Reactor Regulation
To: Hampton J
DUKE POWER CO.
References
IEB-88-011, IEB-88-11, TAC-M72148, TAC-M72149, TAC-M72150, NUDOCS 9205010222
Download: ML15260A285 (4)


Text

April 11, 1992 Docket Nos. 50-269, 50-270 and 50-287 Mr. J. W. Hampton Vice President, Oconee Site Duke Power Company P. 0. Box 1439 Seneca, South Carolina 29679

Dear Mr. Hampton:

SUBJECT:

CLOSEOUT OF BULLETIN 88-11, "PRESSURIZER SURGE LINE THERMAL STRATIFICATION," FOR OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 (TACS M72148/M72149/M72150)

By letter dated September 6, 1991, we forwarded a safety evaluation report of the NRC staff's review of the Babcock &

Wilcox Owners Group (BWOG) report (BAW-2127) on generic final analysis of surge line thermal stratification. One issue involving the stress index used in calculating thermal expansion stress for surge line elbows remained open pending a revised response from the BWOG. Licensing activities relating to NRC Bulletin 88-11 remained open for the Oconee Nuclear Site pending resolution of this issue, since you had verified the applicabili ty of BAW-2127 to Oconee, Units 1, 2, and 3.

Although this issue is still under generic review, no plant specific issues have been identified. If, after NRC staff review of the BWOG proposed resolution, a revision to BAW-2127 is determined to be necessary, you will be requested, as a separate action, to provide verification of the applicability of the revised program and results to Oconee, Units 1, 2, and 3.

Therefore, no further plant-specific reviews will be performed for these activities and this letter completes NRC action for the above TACs.

If you have questions regarding this matter, contact me at (301) 504-1495.

Sincerely,

/s/

Leonard A. Wiens, Project Manager Project Directorate 11-3 Division of Reactor Projects-I/II Office of Nuclear Reactor Regulation cc: See next page DISTRIBUTION:

SEE NEXT PAGE PDII-3:L PDI

.PM D:

-3 LERRY LWIENS:CW D

THEWS

/W/9

/11/92

/ 1/92 FJL NAME:

A:/BLT8811 9205010222 920417 w

PDR ADOCK 05000269 a 0 PDR J/

G p~jkREG~Zq UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555 April 17, 1992 Docket Nos. 50-269, 50-270 and 50-287 Mr. J. W. Hampton Vice President, Oconee Site Duke Power Company P. 0. Box 1439 Seneca, South Carolina 29679

Dear Mr. Hampton:

SUBJECT:

CLOSEOUT OF BULLETIN 88-11, "PRESSURIZER SURGE LINE THERMAL STRATIFICATION," FOR OCONEE NUCLEAR STATION, UNITS 1, 2, AND 3 (TACS M72148/M72149/M72150)

By letter dated September 6, 1991, we forwarded a safety evaluation report of the NRC staff's review of the Babcock &

Wilcox Owners Group (BWOG) report (BAW-2127) on generic final analysis of surge line thermal stratification. One issue involving the stress index used in calculating thermal expansion stress for surge line elbows remained open pending a revised response from the BWOG. Licensing activities relating to NRC Bulletin 88-11 remained open for the Oconee Nuclear Site pending resolution of this issue, since you had verified the applicabili ty of BAW-2127 to Oconee, Units 1, 2, and 3.

Although this issue is still under generic review, no plant specific issues have been identified.

If, after NRC staff review of the BWOG proposed resolution, a revision to BAW-2127 is determined to be necessary, you will be requested, as a separate action, to provide verification of the applicability of the revised program and results to Oconee, Units 1, 2, and 3.

Therefore, no further plant-specific reviews will be performed for these activities and this letter completes NRC action for the above TACs.

If you have questions regarding this matter, contact me at (301) 504-1495.

Sincerely, Leonard A. Wiens, Project Manager Project Directorate 11-3 Division of Reactor Projects-I/II Office of Nuclear Reactor Regulation cc: See next page

Mr. J. W. Hampton Duke Power Company Oconee Nuclear Station cc:

Mr. A. V. Carr, Esquire Mr.. E. Patrick Duke Power Company Compliance 422 South Church Street Duke Power Company Charlotte, North Carolina 28242-0001 Oconee Nuclear Site P. 0. Box 1439 J. Michael McGarry, III, Esquire Seneca, South Carolina 29679 Winston and Strawn 1400 L Street, NW.

Mr. Alan R. Herdt, Chief Washington, DC 20005 Project Branch #3 U. S. Nuclear Regulatory Commission Mr. Robert B. Borsum 101 Marietta Street, NW. Suite 2900 Babcock & Wilcox Atlanta, Georgia 30323 Nuclear Power Division Suite 525 Ms. Karen E. Long 1700 Rockville Pike Assistant Attorney General Rockville, Maryland 20852 North Carolina Department of Justice Manager, LIS P. 0. Box 629 NUS Corporation Raleigh, North Carolina 27602 2650 McCormick Drive, 3rd Floor Clearwater, Florida 34619-1035 Mr. R. L. Gill, Jr.

Licensing Senior Resident Inspector Duke Power Company U. S. Nuclear Regulatory Commission P. 0. Box 1007 Route 2, Box 610 Charlotte, North Carolina 28201-1007 Seneca, South Carolina 29678 Regional Administrator, Region II U. S. Nuclear Regulatory Commission 101 Marietta Street, NW. Suite 2900 Atlanta, Georgia 30323 Mr. Heyward G. Shealy, Chief Bureau of Radiological Health South Carolina Department of Health and Environmental Control 2600 Bull Street Columbia, South Carolina 29201 Office of Intergovernmental Relations 116 West Jones Street Raleigh, North Carolina 27603 County Supervisor of Oconee County Walhalla, South Carolina 29621

Apr 7, 1992 DISTRIBUTION:

Docket FiT e NRC/Local PDRs PDII-3 R/F Oconee R/F SVarga GLainas DMatthews LWiens LBerry OGC, 15B18 ACRS (10), P-315 LReyes, RII JShea, 14E21 SHou, 7H15 JNorberg,. 7E23