Supplement to 10 CFR 50.55a Requests Associated with the Fifth Ten-Year Inservice Testing Interval
ML15258A024
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 09/11/2015
From: Gebbie J
Indiana Michigan Power Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
AEP-NRC-201 5-91
Download: ML15258A024 (3)


Text

INDIANEA Indiana Michigan Power MICHIGAN Cook Nuclear Plant Ipf*VER One Cook Place A unit of American Electric Power Indiagnaihgn, Powercom September 11, 2015 AEP-NRC-201 5-91 10 CFR 50.55a Docket Nos.: 50-315 50-316 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Donald C. Cook Nuclear Plant Units 1 and 2 Supplement to 10 CFR 50.55a Requests Associated with the Fifth Ten-Year Inservice Testing Interval

References:

1. Letter from J. P. Gebbie, Indiana Michigan Power Company (I&M), to U. S. Nuclear Regulatory Commission (NRC), "Donald C. Cook Nuclear Plant Units 1 and 2, 10 CFR 50.55a Requests Associated with the Fifth Ten-Year Inservice Testing Interval," AEP-NRC-2015-31, dated July 31,
2015, Agencywide Documents Access and Management System Accession No. ML15216A121.
2. Letter from A. W. Dietrich, NRC, to L. J. Weber, I&M, "Donald C. Cook Nuclear Plant, Units 1 and 2 - Supplemental Information Needed for Acceptance of Requested Licensing Action Re:

Relief Request REL-PP1 (TAC Nos. MF6548 and MF6549)," dated September 2, 2015.

By Reference 1, Indiana Michigan Power Company (I&M), the licensee for Donald C. Cook Nuclear Plant (CNP) Units 1 and 2, requested U. S. Nuclear Regulatory Commission (NRC) authorization for approval of the 10 CFR 50.55a relief requests associated with the Fifth Inservice Testing Interval for CNP. The NRC staff provided a request for supplemental information (Reference 2) to complete the review of Reference 1.

This letter is being submitted as a supplement to Reference 1 to correct an incorrect reference to the applicable 10 CER 50.55a paragraph in Relief Request REL-PPI.

I&M's initial submittal.

(Reference 1) identified Relief Request REL-PP1 as being requested under the provisions of 10 CFR 50.55a(z)(1), which was incorrect.

Relief Request REL-PP1 is being requested under the provisions of 10 CFR 50.55a(z)(2).

Additionally, Enclosure 2 of Reference 1 incorrectly identified Agencywide Documents Access and Management System (ADAMS) Accession No. ML061730715 as a precedent for REL-PPI. The correct ADAMS No. is ML061730175.

I&M requests approval of the relief requests prior to the start of the Fifth 10-Year Test Interval, which will begin July 1, 2016.

4QO47

U. S. Nuclear Regulatory Commission AEP-NRC-201 5-91 Page 2 This letter contains no new commitments.

Should you have any questions, please contact Mr. Michael K. Scarpello, Regulatory Affairs Manager, at (269) 466-2649.

Sincerely, Joel P. Gebbie Site Vice President JMT/ams c:

A. W. Dietrich, NRC Washington, D.C.

J. T. King, MPSC MDEQ - RMD/RPS NRC Resident Inspector C. D. Pederson, NRC Region Ill A. J. Williamson, AEP Ft. Wayne, w/o enclosures Ito AEP-NRC-2015-91 AFFI RMATI ON I, Joel P. Gebbie, being duly sworn, state that I am the Site Vice President of Indiana Michigan Power Company (I&M), that I am authorized to sign and file this request with the U. S. Nuclear Regulatory Commission on behalf of I&M, and that the statements made and the matters set forth herein pertaining to I&M are true and correct to the best of my knowledge, information, and belief.

Indiana Michigan Power Company Joel P. Gebbie Site Vice President SWORN TO AND SUBSCRIBED BEFORE ME THIS Uf DAY OFS

,,c',

2015 Notary Public ANNE M. PALMA Notary Public, State of Michigan.

County of Berrien My Commission Expires 10-).,6-2017 Acting in the Countyof.