1 West, Ebonie From:

Wanda D Craft (Generation - 6) <wanda.d.craft@dom.com>

Sent:

Thursday, July 16, 2015 1:56 PM To:

Venkataraman, Booma; Guzman, Richard

Subject:

[External_Sender] RE: Millstone Unit 3 Alternative Request IR-3-27 for Implementation of Extended Reactor Vessel Inservice Inspection Interval-CLARIFICATION (TAC NO.

MF5868)

Booma, Thestatementonpage1ofAttachment1underApplicableCodeRequirementreferstotheenddateoftheMPS3 third10yearinserviceinspectioninterval.Thethird10yearinserviceinspectionintervalforMPS3beganonApril23, 2009andisscheduledtoendonApril22,2019.

Thestatementonpage3ofAttachment1inthelastrowofTable2,ThethirdISIisscheduledfor2016,referstothe nextscheduledinspectionofthereactorvessel.Table2ofAttachment1providesasummaryofthereactorvessel inspectionsforMPS3.Thereactorvesselhasbeeninspectedeach10yearintervalforatotaloftwoprevious inspectionsasdescribedinthesecondrowofTable2.SinceMPS3iscurrentlyinthethird10yearinspectioninterval, thereactorvesselisscheduledforitsthirdinspectionduringtherefuelingoutagein2016.DNCisrequestingan extensionofthecurrentexaminationfrequencyfrom10yearsto20years.AsstatedinthelastrowofTable2,thenext reactorvesselinspectionisproposedtobeperformedin2027plusorminusonerefuelingoutage,ratherthanas currentlyscheduledfor2016.

Ifyouhaveanyfurtherquestions,pleaseletmeknow.Thanks.

Wanda D. Craft Nuclear Licensing and Operations Support Dominion Resources Services, Inc (804) 273-4687 tie-line 730-4687

From: Venkataraman, Booma [1]

Sent: Wednesday, July 15, 2015 5:15 PM To: Wanda D Craft (Generation - 6)

Cc: Guzman, Richard

Subject:

Millstone Unit 3 Alternative Request IR-3-27 for Implementation of Extended Reactor Vessel Inservice Inspection Interval-CLARIFICATION (TAC NO. MF5868)

Wanda, By letter dated March 9, 2015 (ML15075A025), Dominion Nuclear Connecticut, Inc. (DNC, the licensee), requested an alternative to the requirement of the American Society of Mechanical Engineers (ASME) Code, Section Xl, Paragraph IWB-2412, Inspection Program B, for Millstone Power Station Unit 3 (MPS3) which requires examination of identified reactor vessel pressure retaining welds (Examination Category B-A and B-D) once each 10-year interval. The proposed alternative would extend the current examination frequency from 10 years to 20 years.

NRC seeks the following clarification on the alternative request:

On page 1 of Attachment 1 of the request, under Applicable Code Requirement, the licensee states that The MPS3 third 10-year inservice inspection (ISI) interval is scheduled to end on April 22, 2019. However, on page 3 of Attachment 1, the last row of Table 2, Additional

2 Information Pertaining to Reactor Vessel Inspection for MPS3 states, The third ISI is scheduled for 2016.

Please clarify the start and end dates for the third ISI interval.

Thanks, Booma BoomaVenkataraman,P.E.

ProjectManager,NRR/DORL/LPL11 OfficeofNuclearReactorRegulation Booma.Venkataraman@nrc.gov 301.415.2934

CONFIDENTIALITY NOTICE: This electronic message contains information which may be legally confidential and or privileged and does not in any case represent a firm ENERGY COMMODITY bid or offer relating thereto which binds the sender without an additional express written confirmation to that effect. The information is intended solely for the individual or entity named above and access by anyone else is unauthorized. If you are not the intended recipient, any disclosure, copying, distribution, or use of the contents of this information is prohibited and may be unlawful. If you have received this electronic transmission in error, please reply immediately to the sender that you have received the message in error, and delete it. Thank you.