TurkeyPointLANPEm Resource From: Tomonto, Bob [Bob.Tomonto@fpl.com]

Sent: Saturday, July 19, 2014 12:46 PM To: Klett, Audrey

Subject:

FW: Revised TS Page for the Emergency LAR for Turkey Point Attachments: PTN UHS TS 3.7.4 Mark-up_Limit Only Temporary Change, R0.pdf From: Tomonto, Bob Sent: Saturday, July 19, 2014 11:56 AM To: 'Klett, Audrey'

Subject:

FW: Revised TS Page for the Emergency LAR for Turkey Point

Audry, In response to our discussion with the NRC staff yesterday, FPL is generating a revision to the emergency LAR to address the proposed changes as highlighted on the attached TS page.

If the staff has any questions, please do not hesitate to contact me.

Robert J. (Bob) Tomonto PE Florida Power & Light Company Turkey Point Nuclear plant Licensing Manager (cell) 786-229-5353 1

Hearing Identifier: TurkeyPoint_LA_NonPublic Email Number: 348 Mail Envelope Properties (BC11E06857D1C6439A83B4D1D937E6912C4408F8)

Subject:

FW: Revised TS Page for the Emergency LAR for Turkey Point Sent Date: 7/19/2014 12:46:15 PM Received Date: 7/19/2014 1:16:39 PM From: Tomonto, Bob Created By: Bob.Tomonto@fpl.com Recipients:

"Klett, Audrey" <Audrey.Klett@nrc.gov>

Tracking Status: None Post Office: GOXSA1809.fplu.fpl.com Files Size Date & Time MESSAGE 596 7/19/2014 1:16:39 PM PTN UHS TS 3.7.4 Mark-up_Limit Only Temporary Change, R0.pdf 473431 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

PLANT SYSTEMS 3/4.7.4 ULTIMATE HEAT SINK LIMITING CONDITION FOR OPERATION 3.7.4 The ultimate heat sink shall be OPERABLE with an average supply water temperature less than or equal to 100qF. **

APPLICABILITY: MODES 1. 2, 3. and 4.

ACTION:

With the requirements of the above specification not satisfied, be in at least HOT STANDBY within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and In COLD SHUTDOWN within the following 30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br />. This ACTION shall be applicable to both units simultaneously.

i SURVEILLANCE REQUIREMENTS 4.7.4 The ultimate heat sink shall be determined OPERABLE at least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> by verifying the average supply water temperature* to be within its limit.

a. At least once per 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> by verifying the average supply water temperature* is less than or equal to 100ºF.
b. Verify average supply water temperature* is less than or equal to 103ºF at least once per hour when water temperature exceeds 100ºF**.
  • Portable monitors may be used to measure the temperature.
    • During the period July XX, 2014 to October 3, 2014 only, the ultimate heat sink shall be OPERABLE with an average supply water temperature* less than or equal to 103ºF.

TURKEY POINT - UNITS 3 & 4 3/4 7-17 AMENDMENT NOS. 260 AND 255