NRR E-mail Capture - Diablo Canyon Power Plant, Unit 2 - ASME Section XI ISI Program RR NDE-PNS-U2A to Allow Use of Alternate Examination Volume Coverage Requirements for Pressurizer Nozzle-to-Head Welds
ML15132A307
Person / Time
Site: Diablo Canyon Pacific Gas & Electric icon.png
Issue date: 05/12/2015
From: Siva Lingam
Plant Licensing Branch IV
To: Richardson M
Pacific Gas & Electric Co
References
TAC MF6073
Download: ML15132A307 (2)


Text

NRR-PMDAPEm Resource From: Lingam, Siva Sent: Tuesday, May 12, 2015 9:06 AM To: mjrm@pge.com Cc: Markley, Michael; Klos, John; Young, Austin; Poehler, Jeffrey; Regner, Lisa; Soenen, Philippe R (PNS3@pge.com); Schrader, Kenneth (KJSe@pge.com)

Subject:

Diablo Canyon Power Plant, Unit 2 - ASME Section XI ISI Program RR NDE-PNS-U2A to Allow Use of Alternate Examination Volume Coverage Requirements for Pressurizer Nozzle-to-Head Welds (TAC No. MF6073)

By letter dated April 9, 2015 (ADAMS Accession No. ML15099A409), Pacific Gas and Electric Company submitted a relief request NDE-PNS-U2A for Diablo Canyon Power Plant (DCPP), Unit 2 Third Inservice Inspection Interval. The relief is requested from the requirements of American Society of Mechanical Engineers Boiler and Pressure Vessel Code, for examination coverage of Class 1 pressurizer nozzle-to-head welds. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this relief request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed relief request in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me.

Siva P. Lingam U.S. Nuclear Regulatory Commission Project Manager (NRR/DORL/LPL4-1)

Cooper Nuclear Station Diablo Canyon Nuclear Power Plant Location: O8-D5; Mail Stop: O8-B3 Telephone: 301-415-1564; Fax: 301-415-1222 E-mail address: siva.lingam@nrc.gov 1

Hearing Identifier: NRR_PMDA Email Number: 2059 Mail Envelope Properties (Siva.Lingam@nrc.gov20150512090600)

Subject:

Diablo Canyon Power Plant, Unit 2 - ASME Section XI ISI Program RR NDE-PNS-U2A to Allow Use of Alternate Examination Volume Coverage Requirements for Pressurizer Nozzle-to-Head Welds (TAC No. MF6073)

Sent Date: 5/12/2015 9:06:20 AM Received Date: 5/12/2015 9:06:00 AM From: Lingam, Siva Created By: Siva.Lingam@nrc.gov Recipients:

"Markley, Michael" <Michael.Markley@nrc.gov>

Tracking Status: None "Klos, John" <John.Klos@nrc.gov>

Tracking Status: None "Young, Austin" <Austin.Young@nrc.gov>

Tracking Status: None "Poehler, Jeffrey" <Jeffrey.Poehler@nrc.gov>

Tracking Status: None "Regner, Lisa" <Lisa.Regner@nrc.gov>

Tracking Status: None "Soenen, Philippe R (PNS3@pge.com)" <PNS3@pge.com>

Tracking Status: None "Schrader, Kenneth (KJSe@pge.com)" <KJSe@pge.com>

Tracking Status: None "mjrm@pge.com" <mjrm@pge.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2104 5/12/2015 9:06:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: