Request for Withholding Information from Public Disclosure for Peach Bottom Atomic Power Station, Unit No. 2
ML15124A295
Person / Time
Site: Peach Bottom Constellation icon.png
Issue date: 05/20/2015
From: Richard Ennis
Plant Licensing Branch 1
To: Bryan Hanson
Exelon Nuclear
Ennis R, NRR/DORL/LPLI-2, 415-1420
References
TAC MF6169
Download: ML15124A295 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 20, 2015 Mr. Bryan C. Hanson President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE FOR PEACH BOTTOM ATOMIC POWER STATION, UNIT NO. 3 (TAC NO. MF6169)

Dear Mr. Hanson:

By letter to the Nuclear Regulatory Commission (NRC) dated April 30, 2015 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML15120A290), Exelon Generation Company, LLC (Exelon) submitted a Global Nuclear Fuel - Americas (GNF-A) affidavit dated March 12, 2015, executed by Mr. Lukas Trosman (Attachment 6 to Exelon's letter). Exelon requested that the information contained in Attachment 4 to its letter be withheld from public disclosure pursuant to Title 10 of the Code of Federal Regulations ( 10 CFR)

Section 2.390. Specifically, Exelon requested that the following document be withheld:

GNF report 002N5030 R1-P, Revision 0, "GNF Additional Information Regarding the Requested Changes to the Technical Specification SLMCPR [Safety Limit Minimum Critical Power Ratio], Peach Bottom Unit 3 Cycle 21" A non-proprietary copy of the document (Attachment 5 to Exelon's letter) has been placed in the NRC's Public Document Room and added to the Agencywide Documents Access and Management System Public Electronic Reading Room.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(4)a. Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by GNF-A's competitors without license from GNF-A constitutes a competitive economic advantage over other companies; and (4 )b. Information that, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product.

We have reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the

B. Hanson submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure. Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390{b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the document. If the need arises, we may send copies of this information to our consultants working in this area. We will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, I may be reached at 301-415-1420.

Sincerely, Richard B. Ennis, Senior Project Manager Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-278 cc: Mr. Lukas Trosman Engineering Manager, Reload Design and Analysis Global Nuclear Fuel - Americas LLC 3901 Castle Hayne Road Wilmington, NC 28401 Additional Distribution via Listserv

ML15124A295 OFFICE LPL 1-2/PM LPL 1-2/LA SRXB/BC LPL 1-2/BC LPL 1-2/PM NAME REnnis ABaxter CJackson DBroaddus REnnis DATE 05/04/2015 05/12/2015 05/19/2015 05/20/2015 05/20/2015