ML15105A524

From kanterella
Jump to navigation Jump to search
NRR E-mail Capture - Seabrook
ML15105A524
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 04/14/2015
From: John Lamb
Plant Licensing Branch 1
To: Comley S
We The People
References
Download: ML15105A524 (3)


Text

NRR-PMDAPEm Resource From: Lamb, John Sent: Tuesday, April 14, 2015 3:08 PM To: Stephen Comley

Subject:

RE: Seabrook

Dear Mr. Comley:

As the Seabrook project manager (PM), I have the responsibility for preparing and managing the review and issuance of license amendments, exemptions, relief requests, safety evaluations, and other documents associated with the safety and regulation of Seabrook. As the PM, I serve as the licensing authority regarding the maintenance and amendment of Seabrook's licensing and design basis. My knowledge as a PM of Seabrook's licensing basis is intended to support the NRC's response to potentially significant events, generic safety issues and assessment of licensee performance.

My knowledge as a PM of Seabrooks design and licensing information makes the PM a necessary component in responding to allegations, controlled and routine correspondence, generic communications, and other requests for information from stakeholders. As the Seabrook PM, I serve as the primary licensing interface between headquarter organizations and licensees or regional offices in matters pertaining to Seabrook. As the PM, I integrate information obtained from all sources and ensure the proper dissemination to the applicable internal/external stakeholders.

Sincerely, John Lamb From: Stephen Comley [1]

Sent: Tuesday, April 14, 2015 1:46 PM To: Lamb, John

Subject:

Re: Seabrook Mr. Lamb, thank you for getting back to me?

What has prompted you to contact me? Has this originated from Mr. Mark Satorius, Executive (EDO) Director of the Nuclear (NRC) Regulatory Commission?

I was informed 4/13/2015 Ms, Jane Kreuter (Mr. Sartorius assistant) was contacted again concerning a previous e-mail I received on January 12, 2015, I was informed that date a Conference call would be arranged for Mr. Satorius and I to discuss not only my concerns about Seabrook but other matters including cover-ups within the NRC.

Please reply, Stephen B. Comley Sr.

Founder of We The People a National Whistleblower Non-Profit Organizsation 1

From: "Lamb, John" <John.Lamb@nrc.gov>

To: "scomleysr@yahoo.com" <scomleysr@yahoo.com>

Sent: Tuesday, April 14, 2015 11:29 AM

Subject:

Seabrook

Dear Mr. Comley:

My name is John Lamb. I am the project manager for Seabrook in the NRC Headquarters, located in Rockville, Maryland. I understand that you have some concerns regarding Seabrook.

Sincerely, John Lamb 2

Hearing Identifier: NRR_PMDA Email Number: 2000 Mail Envelope Properties (John.Lamb@nrc.gov20150414150800)

Subject:

RE: Seabrook Sent Date: 4/14/2015 3:08:13 PM Received Date: 4/14/2015 3:08:00 PM From: Lamb, John Created By: John.Lamb@nrc.gov Recipients:

"Stephen Comley" <scomleysr@outlook.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2545 4/14/2015 3:08:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: