MONTHYEARML19025A0822019-01-10010 January 2019 Rancho Seco Nuclear Generating Station - Report of Changes to the Rancho Seco Quality Assurance Program That Do Not Require Prior NRC Approval ML18302A1582018-11-28028 November 2018 Revised Letter for Termination of Rancho Seco Nuclear Generating Station Operating License DPR-54 and Indemnity Agreement ML18324A5902018-10-31031 October 2018 Sacramento Municipal Utility District (Smud) - Rancho Seco - Emergency Plan Manual Update IR 05000312/20180012018-09-0505 September 2018 Independent Spent Fuel Storage Installation (ISFSI) Inspection Report 05000312/2018001 and 07200011/2018001 ML18082B0762018-08-31031 August 2018 Termination of Rancho Seco Nuclear Generating Station Operating License DPR-054 ML18143B4752018-05-15015 May 2018 Biennial Report for Period Covering 05/01/2016 Through 04/30/2016 ML18081A5792018-03-0505 March 2018 Report on Decommissioning Funding Status ML18065A1852018-02-20020 February 2018 Annual Radioactive Effluent Release Report for 2017 ML17191A6322017-06-26026 June 2017 2016 Annual Financial Report for the Sacramento Municipal Utility District ML17116A1362017-05-16016 May 2017 Review of Final Status Survey Report for Rancho Seco Nuclear Generating Station Interim Onsite Storage Building ML17118A0252017-04-20020 April 2017 Final Status Survey Report Submittal - Clarifying Information ML17108A3442017-03-30030 March 2017 Records Required to Be Forwarded to the NRC Prior to Plant 10CFR50 License Termination. with Attachment 1: Annual Radioactive Effluent Release Report for the 1st Quarter of 2017 ML17108A3492017-03-30030 March 2017 Radioactive Effluent Release Report for January 1 - March 30, 2017 ML17095A9802017-03-30030 March 2017 and Independent Spent Fuel Storage Facility - Submittal of Revised Quality Manual ML17094A4072017-03-23023 March 2017 Report on Irradiated Fuel Management Funding Status ML17083A9832017-03-22022 March 2017 Orau Independent Confirmatory Survey Summary, Results, and In-Process Inspection for the Interim On-Site Storage Building and Surrounding Area at the Rancho Seco Nuclear Generating Station ML17094A7332017-03-22022 March 2017 Report on Decommissioning Funding Status ML17090A4102017-03-20020 March 2017 Annual Report of Property Insurance Levels ML17083A2602017-03-14014 March 2017 Annual Radioactive Effluent Release Report for 2016 ML17065A0342017-02-28028 February 2017 Final Status Survey Summary Report ML17026A4332017-01-17017 January 2017 Independent Spent Fuel Storage Installation Proposed License Amendment No. 4 ML16302A0702016-10-18018 October 2016 Biennial Update to Rancho Seco License Termination Plan ML16302A0712016-10-18018 October 2016 Radioactive Material Storage and Decommissioning Safety Analysis Report Amendment 3 IR 05000312/20160022016-09-16016 September 2016 NRC Inspection Report 050-00312/2016-002 ML16208A1092016-07-14014 July 2016 Sacramento Municipal Utility District (Smud), Rancho Seco Independent Spent Fuel Storage Installation (ISFSI) - Submittal of Biennial Report for May 2014 - April 2016 IR 05000312/20160012016-06-17017 June 2016 IR 05000312/2016001 and 07200011/2016001, May 17-18, 2016, Sacramento Municipal Utility District, Rancho Seco Independent Spent Fuel Storage Installation ML16187A1922016-06-16016 June 2016 and ISFSI - Annual Financial Report for 2015 ML16106A1092016-04-0707 April 2016 Notification of Mailing Date of the Rancho Seco Report on Decommissioning Funding Status ML16097A2362016-03-31031 March 2016 Report on Irradiated Fuel Management Funding Status ML16102A0822016-03-23023 March 2016 Annual Report of Property Insurance Levels ML16102A0972016-03-14014 March 2016 Report on Decommissioning Funding Status ML16089A2932016-03-10010 March 2016 Annual Radioactive Effluent Release Report for the Period of January 1 Through December 31, 2015 ML16014A1372016-01-0707 January 2016 ISFSI - Report of Changes to the Quality Assurance Program That Do Not Require Prior NRC Approval ML15140A4212015-05-12012 May 2015 Sacramento Municipal Utility District - 2014 Annual Financial Report ML15105A0812015-03-31031 March 2015 Voluntary Submission of Pending Licensing Actions (RIS 2014-13 Response) ML15099A5742015-03-31031 March 2015 Independent Spent Fuel.Storage Installation, 10 CFR 20.2206 Annual Report of Individual Monitoring ML15099A5832015-03-30030 March 2015 and Independent Spent Fuel Storage Installation - 2014 Annual Radiological Environmental Operating Report for the Period of January 1, 2014 Through December 31, 2014 ML15093A0582015-03-23023 March 2015 Report on Decommissioning Funding Status ML15093A0592015-03-23023 March 2015 Annual Radioactive Effluent Release Report for 2014 ML15093A0562015-03-23023 March 2015 Annual Report of Property Insurance Levels ML15036A0472015-01-0707 January 2015 Report of Changes to the Rancho Seco Quality Assurance Program That Do Not Require Prior NRC Approval ML14352A3402015-01-0505 January 2015 Change in Project Manager Ltr Rancho Seco ML14310A1972014-10-30030 October 2014 Biennial Update to Rancho Seco License Termination Plan ML14310A2962014-10-23023 October 2014 Radioactive Material Storage and Decommissioning Safety Analysis Report Amendment 2 ML14308A0562014-10-22022 October 2014 Annual Notification of Foreign Ownership, Control, or Influence Status IR 05000312/20140072014-08-20020 August 2014 IR 050003122014007, on 06/23-25/2014 - 07/28-30/2014, Rancho Seco Nuclear Generating Station, NRC Inspection Report ML14219A3272014-07-24024 July 2014 Biennial Report ML14195A0272014-06-19019 June 2014 Submitting the 2013 Annual Financial Report for the Sacramento Municipal Utility District ML14142A3802014-05-0101 May 2014 Annual Notification of Foreign Ownership, Control, or Influence Status ML14154A1182014-04-30030 April 2014 Request to Register as User of Energysolutions 10-160B Package 2019-01-10
[Table view] Category:Status Report
MONTHYEARML18081A5792018-03-0505 March 2018 Report on Decommissioning Funding Status ML17118A0252017-04-20020 April 2017 Final Status Survey Report Submittal - Clarifying Information ML17094A7332017-03-22022 March 2017 Report on Decommissioning Funding Status ML16097A2362016-03-31031 March 2016 Report on Irradiated Fuel Management Funding Status ML16102A0972016-03-14014 March 2016 Report on Decommissioning Funding Status ML14099A2402014-03-31031 March 2014 Report on Decommissioning Funding Status ML15093A0552014-03-23023 March 2014 Rancho Seco Report on Irradiated Fuel Management Funding Status ML13098A1002013-03-14014 March 2013 Rancho Seco Report on Decommissioning Funding Status ML1110100162011-03-29029 March 2011 Rancho Seco, Submittal of Report on Decommissioning Funding Status ML1009800612010-03-25025 March 2010 Report on Decommissioning Funding Status ML0925703472009-09-0101 September 2009 001 FSS Final Report 5, Rev. 1 ML0908303142009-03-0505 March 2009 Transmittal of Final Status Survey Report, Including Cover Letter and Final Status Survey Report 5 ML0908303222009-03-0202 March 2009 Final Status Survey Report for March 2, 2009 Tank Farm Nw Quadrant Survey Unit F8100021 ML0908305732009-03-0202 March 2009 Final Status Survey Report for March 2, 2009, Tank Farm SW Quad, a Steam Sump & Sf Cooler Pad Areas, Survey Unit F8100011 ML0910003742009-02-26026 February 2009 Final Status Survey Report for February 26, 2009, Western IA (Northern Omission), Survey Unit F8000073 ML0908305452009-02-26026 February 2009 Final Status Survey Report for February 26, 2009, Northern IA Paved Surfaces, Survey Unit F8000142 ML0909007722009-02-26026 February 2009 Final Status Survey Summary Report for February 26, 2009, Tank Farm - Bwst Pad, Survey Unit F8100043 ML0909306622009-02-25025 February 2009 Final Status Survey Summary Report for February 19, 2009, Containment Floor, (-) 27' El., Survey Unit F8110114 ML0909007752009-02-24024 February 2009 Final Status Survey Summary Report for February 24, 2009, Trench 1 Surface, Survey Unit F8100052 ML0908305432009-02-24024 February 2009 Final Status Survey Report for February 24, 2009, IA N-S Roadway East of Bwb, Survey Unit F8000105 ML0908305442009-02-23023 February 2009 Final Status Survey Report for February 22, 2009, Central Industrial Area Paved Roadways, Survey Unit F8000106 ML0909300712009-02-17017 February 2009 Final Status Survey Summary Report for February 16, 2009, Containment Interior Walls, (-) 27' El. to (+) 25' El., Survey Unit F8110113 ML0908303192009-02-12012 February 2009 Final Status Survey Report for February 12, 2009, Western IA (Barrel Farm West), Survey Unit F8000072 ML0910003712009-02-11011 February 2009 Final Status Survey Summary Report 02/11/09, Auxiliary Building Exterior Wall North, Survey Unit F8132144 ML0910003832009-02-11011 February 2009 Final Status Survey Summary Report 02/11/09, Auxiliary Building Exterior East East Wall, Survey Unit F8132143 ML0908305472009-02-10010 February 2009 Final Status Survey Report for February 10, 2009, Cooling Tower Buffer (West), Survey Unit F8080032 ML0908305412009-02-10010 February 2009 Final Status Survey Report for February 10, 2009, Folsom Intake, Helo Pad, South Scrap Yard Combined Survey, Survey Unit F8000011, Revision 1 ML0909306632009-02-10010 February 2009 Final Status Survey Summary Report for February 10, 2009, Containment Building Exterior Walls, Survey Unit F8113001 ML0908305462009-02-0808 February 2009 Final Status Survey Report for February 8, 2009, Cooling Tower Buffer (South), Survey Unit F8080031 ML0909007312009-02-0404 February 2009 Final Status Survey Report for February 4, 2009, Switch Yard South/Retention Basin Buffer, Survey Unit F8510005 ML0909803852009-02-0303 February 2009 Final Status Survey Summary Report Revision 1, February 3, 2009, AB -20' Corridor Column R-T Survey Unit F8130161 ML0909907312009-01-20020 January 2009 Final Status Survey Summary Report for January 19, 2009, Fuel Storage Building (+) 40' El. Floor, Survey Unit F8121001 ML0910003862009-01-15015 January 2009 Final Status Survey Summary Report for January 13, 2009, Fuel Storage Building/Auxiliary Building Gap, (-) 6' El. to (+) 40' El, Survey Unit F8120171 ML0910003872009-01-13013 January 2009 Final Status Survey Summary Report for January 13, 2009, Fuel Storage Building (-) 6' El. to (+) 15' El. South Exterior Wall, Class 1 Area, Survey Unit F812181 ML0908303212009-01-0909 January 2009 Final Status Survey Report for January 9, 2009, Tank Farm S.W. Quadrant - Subsurface Soil - Including a Stm Sump and Sf Cooler Pad Areas, Survey Unit F8100012 ML0908303232009-01-0808 January 2009 Final Status Survey Report for January 8, 2009, Tank Farm - N.W. Quadrant Subsurface Soil, Survey Unit F8100022 ML0908305482009-01-0707 January 2009 Final Status Survey Report for January 7, 2009, Cooling Tower Buffer (East), Survey Unit F8080033 ML0909007292009-01-0606 January 2009 Final Status Survey Report for January 6, 2009, Tank Farm N.E. Quadrant - Subsurface Soil, Survey Unit F8100032 ML0908303242009-01-0505 January 2009 Final Status Survey Report for December 29, 2008, Tank Farm N.E. Quadrant - Surface Soil, Survey Unit F8100031 ML0909803912008-12-31031 December 2008 Final Status Survey Summary Report, December 31, 2008 Auxiliary Building Room 109 Survey Unit F8130942 ML0908505542008-12-16016 December 2008 Final Status Survey Report for December 16, 2008, North Laydown Area Adjacent to Turbine Building, Survey Unit F8260251 ML0909300722008-12-10010 December 2008 Final Status Survey Summary Report for December 10, 2008, Tank Farm Trench #1 Eastern Portion Subsurface Soil, Survey Unit F8100053 ML0909300742008-12-10010 December 2008 Final Status Survey Summary Report for December 10, 2008, Containment Interior Walls, (+) 25' El. to (+) 75' El, Survey Unit F8110112 ML0909007302008-12-0505 December 2008 Final Status Survey Report for December 2, 2008, Rhut/Aux Boiler Pad Area Sub-Surface Soil, Survey Unit F8370002 ML0909803842008-11-19019 November 2008 Final Status Survey Summary Report for November 6, 2008 East Decay Heat Removal Pump Room - Upper Walls Survey Unit F8130041 ML0909803942008-11-17017 November 2008 Final Status Survey Summary Report, November 17, 2008 Fuel Pool Piping System Survey Unit F8990441 ML0909803922008-11-10010 November 2008 Final Status Survey Summary Report, November 10, 2008 Decay Heat Drains Reactor Building Survey Unit F8990111 ML0909803932008-11-10010 November 2008 Final Status Summary Survey Report, November 10, 2008 Reactor Building Drains Survey Unit F8990401 ML0909803832008-11-0505 November 2008 Final Status Survey Summary Report for November 5, 2008 West Decay Heat Removal Pump Room - Ceiling Survey Unit F8130022 ML0909300992008-11-0303 November 2008 Final Status Survey Summary Report for November 3, 2008, Spent Fuel Pool North Wall, (+) 0' El. to (+) 40' El., Survey Unit F8120004 2018-03-05
[Table view] |
Text
Powering forward. Together.
- SMUD DPG 15-071 March 23, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Docket No. 50-312 Rancho Seco Nuclear Generating Station License No. DPR-54 RANCHO SECO REPORT ON IRRADIATED FUEL MANAGEMENT FUNDING STATUS Attention: Jack Parrott As required by 10 CFR 50.82(a)(8)(vii), this letter provides the information on the status of financial assurance for irradiated fuel management funding for Rancho Seco as a supplement to the Annual Report on Decommissioning Funding Status. Note that the costs for decommissioning are provided separately and include all costs required to maintain the licenses until they are terminated following removal of irradiated materials from the facility. In estimating costs for irradiated fuel management, SMUD assumes that all fuel is to be removed from the site by 2021 in accordance with the DOE's "Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste" issued (January 2013).
Irradiated Fuel Management Cost Estimate In accordance with 10 CFR 50.82(a)(8)(vii)(B), an estimate is provided in Attachment 1 for the costs of managing irradiate fuel until the Department of Energy takes possession of the material. In summary, the estimated costs for irradiated fuel management at Rancho Seco total $37.5 million.
Rancho Seco Nuclear Generating Station I 14440 Twin Cities Road I Herald, CA 95638-9799 I 1.209.333.2935 I smud.org
DPG 15-071 Page 2 of 4 Irradiated Fuel Management Funding Status In accordance with 10 CFR 50.82(a)(8)(vii)(A), SMUD is reporting that on December 4, 2014 the SMUD Board of Directors approved annual funding in the amount of
$4,339,854 for management of irradiated fuel for 2015. SMUD approved these funds through the annual budgeting process. Therefore, at the end of 2014, SMUD had committed and accumulated $4,339,854 for the management of irradiated fuel for 2015.
In general, SMUD holds the position that it is not financially responsible for the cost of irradiated fuel management. This statement is supported by Federal Court decisions that have, without ambiguity, determined that the Federal Government is responsible for the ongoing costs of irradiated fuel and Greater-Than-Class-C (GTCC) waste management. However, SMUD will continue to provide funding, on an annual budget basis, for ongoing costs for irradiated fuel management, including the costs of implementing changing regulations, relicensing and unforeseen circumstances. SMUD is committed to providing for the safe storage of the material and a high level of compliance with NRC regulatory requirements as long as it remains at the Rancho Seco facility.
Irradiated Fuel Management Funding Plan In accordance with 10 CFR 50.82(a)(8)(vii)(C), SMUD provides the following plan for accumulation of funds. This plan, once approved, will be included as an amendment to the Post Shutdown Decommissioning Activities Report and provided to the NRC.
As noted above, the Federal Government is financially responsible for the ongoing costs of managing the irradiated fuel and GTCC waste. Nevertheless, SMUD intends to fund the ongoing management of the materials through annual budgets, and by taking the appropriate legal actions for periodic reimbursement of those costs from the Federal Government.
SMUD also demonstrates that it has the means to provide ongoing funding as it is a municipal utility incorporated under the California MUD Act. As such, SMUD has full legal authority to establish its own rates and charges and has legal authority to recover its costs from ratepayers. Irradiated fuel management is funded by our ratepayers through operating revenues. As an operating expense, these costs are senior to any debt service payment. The rate covenants in SMUD's bond resolutions require that revenues, after operating expenses (excluding non-cash type expenses such as depreciation), must be greater than SMUD's debt service each year. Thus, the covenants provide assurance that cash necessary to fund irradiated fuel management will be available in any given year.
In addition, SMUD, as a municipal utility, cannot avoid its obligation to provide for irradiated fuel management through bankruptcy or dissolution proceedings. The Bankruptcy Code allows for a municipal reorganization where the municipal's liabilities and obligations must eventually be paid. The California Government Code affords
DPG 15-071 Page 3 of 4 similar protection and would require any successor to SMUD to satisfy all debts and obligations including the costs of irradiated fuel management, before any part of SMUD's electric system could be sold or encumbered.
SMUD believes that the information provided in this letter provides reasonable assurance that SMUD can provide for the safe management of the irradiated fuel and GTCC waste until the materials are accepted by the DOE.
If you or members of your staff have questions or require additional information, please contact me by email at einar.ronninqenasmud.orq or by phone at (916) 732-4817.
Sincerely, Einar T. Ronningen Superintendent, Rancho Seco Assets (ETR) : 2015 Rancho Seco Irradiated Fuel Management Cost Estimate CC with
Attachment:
NRC, Region IV
DPG 15-071 Page 4 of 4 ATTACHMENT 1 2015 IRRADIATED FUEL MANAGEMENT COST ESTIMATE
2015 RANCHO SECO h
IRRADIATED FUEL MANAGEMENT COST ESTIMATE Irradiated Fuel Management Costs by Year 2015 2016 2017 2018 2019 2020 2021 Totals SMUD Labor $ 485,000 $ 485,000 $ 485,000 $ 485,000 $ 485,000 $ 634,911 $ 634,911 $ 3,694,821 Relicensing $ 260,000 $ 260,000 $ 260,000 $ 260,000 $ 260,000 $ 1,300,000 Aging Management $ 105,063 $ 105,063 $ 210,125 Materials $ 24,400 $ 24,400 $ 24,400 $ 24,400 $ 24,400 $ 19,903 $ 19,903 $ 161,806 Dues & Publications $ 4,000 $ 4,000 $ 4,000 $ 4,000 $ 4,000 $ 182,148 $ 182,148 $ 384,296 Licenses & Fees $ 250,000 $ 250,000 $ 250,000 $ 250,000 $ 250,000 $ 309,873 $ 309,873 $ 1,869,747 Other $ 31,714 $ 31,714 $ 31,714 $ 31,714 $ 31,714 $ 31,714 $ 31,714 $ 222,001 Training & Travel $ 20,000 $ 20,000 $ 20,000 $ 20,000 $ 20,000 $ 10,506 $ 10,506 $ 121,013 Outside Services $2,050,000 $2,050,000 $2,050,000 $2,050,000 $2,050,000 $2,050,537 $ 2,050,537 $ 14,351,074 Insurance $ 390,000 $ 390,000 $ 390,000 $ 390,000 $ 390,000 $ 491,693 $ 491,693 $ 2,933,385 Overhead $ 240,000 $ 240,000 $ 240,000 $ 240,000 $ 240,000 $ 304,904 $ 304,904 $ 1,809,809 Facilities & Grounds $ 75,000 $ 75,000 $ 75,000 $ 75,000 $ 75,000 $ 452,488 $ 452,488 $ 1,279,977 Fuel Loading Costs $ 6,306,439 $ 6,306,439 Contingency (10%) $ 383,011 $ 383,011 $ 383,011 $ 383,011 $ 383,011 $ 459,374 $ 459,374 $ 2,833,805 Total Annual Costs $4,213,126 $4,213,126 $4,213,126 $4,213,126 $4,213,126 $5,053,115 $11,359,553 Total Irradiated Fuel Management CostsI $ 37,478,297