ML15041A060
ML15041A060 | |
Person / Time | |
---|---|
Site: | Technical Specifications Task Force |
Issue date: | 02/05/2015 |
From: | Technical Specifications Task Force |
To: | Division of Policy and Rulemaking |
Honcharik M | |
Shared Package | |
ML15040A069 | List: |
References | |
Download: ML15041A060 (3) | |
Text
Active Travelers Summary Report (See Topics Report for More Information)
TSTF Number Applicability Description TSTF-454, Rev. 2 BWRs Extend PCIV Completion Times (NEDC-33046)
NRC Review Fees To Date: $144,882.50 (BWROG) Topic Number: 968 Status: Green Actions and Schedule Responsibility Date The NRC issued RAIs on October 19, 2012. The RAIs reopen the approved TSTF 2/27/2015 Topical Report that is the basis of the Traveler and requests that portions of the Topical Report justification be updated to the current standards.
The Licensing Committee is working with the BWROG PRA committee (IRIR) to respond to the questions.
TSTF-529, Rev. 2 All Clarify Use and Application Rules NRC Review Fees To Date: $72,933.62 (Shared) Topic Number: 1300 Status: Green Actions and Schedule Responsibility Date TSTF submitted TSTF-529, Revision 2, on January 14, 2014. TSTF 1/14/2014 NRC provided a revised review schedule on 10/29/2014: NRC 10/29/2014 Issue Notice for Comment by 03/12/2015 Issue Notice of Availability by 06/24/2015 NRC to issue Notice for Comment. NRC 3/12/2015 TSTF-531, Rev. 0 All Revision of Specification 3.8.1, Required Actions B.3.1 and B.3.2 NRC Review Fees To Date: $59,261.51 (Shared) Topic Number: 1304 Status: Green Actions and Schedule Responsibility Date The TSTF responded to NRC RAIs on May 22, 2013. NRC and TSTF met TSTF 3/31/2015 on September 25, 2013 to discuss the RAI response.
TSTF to submit a Traveler revision.
TSTF-537, Rev. 0 CE Increase CIV Completion Time; Update of TSTF-373 NRC Review Fees To Date: $67,221.17 (PWROG) Topic Number: 1211 Status: Green Actions and Schedule Responsibility Date NRC issued RAI on March 4, 2013. The RAI requests verification that the TSTF 6/30/2014 information in the supporting Topical Report (CE NPSD-1168), which was approved in December, 2000, is still valid. TSTF received supporting information from Westinghouse on January 7, 2014. TSTF to submit RAI response.
6/23/14 - RAI response submitted.
NRC to issue Notice for Comment. NRC 3/27/2015 Green status: Expected to be successfully completed by the scheduled date.
Yellow status: At risk of not to being successfully completed by the scheduled date.
Red status: Unlikely to be successfully completed by the scheduled date.
Page 1 of 3 01-Feb-15
Active Travelers Summary Report (See Topics Report for More Information)
TSTF Number Applicability Description TSTF-541, Rev. 0 All Add Exceptions to Surveillance Requirements When the Safety Function is Being Performed NRC Review Fees To Date: $154.36 (Shared) Topic Number: 1249 Status: Yellow Actions and Schedule Responsibility Date TSTF-541 submitted to the NRC on September 10, 2013. NRC to provide NRC 2/5/2015 acceptance and schedule letter.
TSTF-542, Rev. 0 BWRs Reactor Pressure Vessel Water Inventory Control NRC Review Fees Waived Topic Number: 1331 Status: Green Actions and Schedule Responsibility Date TSTF-542 and fee exemption request submitted to the NRC on 12/31/2013. TSTF 12/31/2013 NRC to issue fee exemption. NRC 2/24/2014 2/24/2014 - Fee exemption granted.
NRC to issue acceptance and schedule letter. NRC 5/21/2014 5/21/14 - Acceptance letter and RAI provided.
NRC and TSTF held a public meeting on June 5, 2014 to discuss NRC NRC 6/5/2014 questions on TSTF-542.
At the July 10, 2014 TSTF/NRC meeting, the NRC stated their schedule for NRC 7/10/2014 reviewing TSTF-542 is:
(1)NRC to provide an RAIs 10/1/2014 (2)Industry to respond 12/31/2014 (3)Notice for Comment 3/31/2015 (4)Notice of Availability 6/30/2015 NRC RAI received on 10/10/2014. NRC subsequently changed the NRC 10/16/2014 response date to the end of January, 2015.
TSTF to respond to RAI. TSTF 2/27/2015 Green status: Expected to be successfully completed by the scheduled date.
Yellow status: At risk of not to being successfully completed by the scheduled date.
Red status: Unlikely to be successfully completed by the scheduled date.
Page 2 of 3 01-Feb-15
Active Travelers Summary Report (See Topics Report for More Information)
TSTF Number Applicability Description TSTF-545, Rev. 1 All TS Inservice Testing Program Removal & Clarify SR Usage Rule Application to Section 5.5 Testing NRC Review Fees Waived Topic Number: 1367 Status: Green Actions and Schedule Responsibility Date Revision 0 submitted November 4, 2013. NRC 11/4/2013 Fee exemption was approved on 12/13/2013, available as ADAMS ML13333A807.
Revision 1 submitted on March 4, 2014. TSTF 3/4/2014 NRC provided an acceptance and review letter on November 4, 2014. NRC 10/30/2014 Notice for Comment by 6/15/2015 Notice of Availability by 9/10/2015 TSTF to submit revision incorporating comments from NRC August 22, TSTF 12/30/2014 2014 e-mail.
NRC to provide Notice for Comment. NRC 6/15/2015 TSTF-547, Rev. 0 W Clarification of Rod Position Requirements NRC Review Fees To Date: $14,937.91 (PWROG) Topic Number: 1307 Status: Green Actions and Schedule Responsibility Date Revision 0 submitted on March 6, 2014. TSTF 3/6/2014 NRC provided acceptance and schedule letter on August 14, 2014. NRC 8/30/2014 Proposed schedule:
RAIs by October 3.
RAI response by TSTF by January 9, 2015 Notice for Comment by May 29, 2015 Notice of Availability by September 28, 2015 NRC to revised the schedule since there are no RAIs. Notice for Comment NRC 4/15/2015 to be issued by April 15, 2015 and the Notice of Availability by August 6, 2015.
TSTF-551, Rev. 0 BWRs Address Transient Secondary Containment Conditions No NRC Review Fees Received Topic Number: 1386 Status: Green Actions and Schedule Responsibility Date TSTF-551, Revision 0, "Address Transient Secondary Containment TSTF 10/30/2014 Conditions" was submitted on October 30, 2014.
NRC to provided acceptance and schedule letter. NRC 1/30/2015 Active Travelers: 9 Green status: Expected to be successfully completed by the scheduled date.
Yellow status: At risk of not to being successfully completed by the scheduled date.
Red status: Unlikely to be successfully completed by the scheduled date.
Page 3 of 3 01-Feb-15