Category:Letter
MONTHYEARIR 05000461/20230042024-02-0202 February 2024 Integrated Inspection Report 05000461/2023004 ML23361A1572024-01-24024 January 2024 Audit Plan in Support of Review of License Amendment Request Regarding Revision of Technical Specifications Related to Reactor Water Cleanup Isolation ML24004A0792024-01-18018 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0041 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000461/20234022023-12-27027 December 2023 Security Baseline Inspection Report 05000461/2023402 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 IR 05000461/20235012023-12-0505 December 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000461/2023501 ML23284A2512023-11-22022 November 2023 Amendment No. 250 to Adopt TSTF-332 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000461/20230032023-11-0808 November 2023 Integrated Inspection Report 05000461/2023003 ML22300A2212023-11-0202 November 2023 Preliminary Decommissioning Cost Estimate and Fuel Management Plan RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans IR 05000461/20233012023-09-12012 September 2023 NRC Initial License Examination Report 05000461/2023301 RS-23-090, Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2023-09-0707 September 2023 Annual Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000461/20234202023-08-29029 August 2023 Security Baseline Inspection Report 05000461/2023420 RS-23-081, Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2023-08-21021 August 2023 Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20230022023-08-0404 August 2023 Integrated Inspection Report 05000461/2023002 RS-23-085, Supplemental Information Related to Request for Partial Site Release2023-08-0303 August 2023 Supplemental Information Related to Request for Partial Site Release ML23209A8102023-07-28028 July 2023 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23198A0152023-07-27027 July 2023 License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23202A0992023-07-24024 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2023004 ML23200A2592023-07-24024 July 2023 June 27, 2023, Clinton Power Station License Renewal Environmental Pre-application Public Meeting-Meeting Summary IR 05000461/20234012023-07-19019 July 2023 Cyber Security Inspection Report 05000461/2023401 ML23194A1662023-07-19019 July 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Request for Partial Site Release ML23191A8772023-07-11011 July 2023 Operator Licensing Examination Approval Clinton Power Station July 2023 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-073, Request for Partial Site Release2023-06-0707 June 2023 Request for Partial Site Release IR 05000461/20230102023-05-26026 May 2023 Triennial Fire Protection Inspection Report 05000461/2023010 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23143A3182023-05-23023 May 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Clinton Power Station, Unit 1 IR 05000461/20230012023-05-0404 May 2023 Integrated Inspection Report 05000461/2023001 ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) RS-23-039, Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air2023-03-0101 March 2023 Request for License Amendment to Revise Technical Specifications Section 3.8.3, Diesel Fuel Oil, Lube Oil, and Starting Air ML23031A2972023-03-0101 March 2023 Issuance of Amendment No. 248 Adoption of TSTF-269, Revision 2 RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 ML23039A1852023-02-10010 February 2023 Integrated Inspection Report 05000461/2022004 07201046/2022001 RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 IR 05000461/20220112023-01-27027 January 2023 Biennial Problem Identification and Resolution Inspection Report 05000461/2022011 RS-23-002, Application to Adopt TSTF-332, ECCS Response Time Testing2023-01-13013 January 2023 Application to Adopt TSTF-332, ECCS Response Time Testing ML23005A0682023-01-0505 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000461/2023010 ML22341A6042022-12-0808 December 2022 Confirmation of Initial License Examination IR 05000461/20224022022-12-0606 December 2022 Security Baseline Inspection Report 05000461/2022402 RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI 2024-02-02
[Table view] |
See also: RIS 2014-05
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, IL 60532-4352
January 28, 2015
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS,
CLINTON STATION, UNIT 1
Dear Mr. Hanson:
We have received your corporate letter RS-14-164, dated May 29, 2014, in response to
U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2014-05, Preparation
and Scheduling of Operator Licensing Examinations. In the letter, you requested an initial
operator licensing examinations be scheduled for October 2016, and October 2018, at the
Clinton Station. These dates have changed from your previous submittal in corporate letter
RS-13-183 and our NRC response letter dated January 27, 2014.
In response, we have scheduled initial operator licensing examinations for the weeks of:
- November 28 and December 5, 2016, with an on-site validation date the week of
October 31, 2016.
- October 29 and November 5, 2018, with an on-site validation date the week of
October 1, 2018.
In the unlikely event that we are unable to support the examination during the scheduled weeks,
we will inform you immediately, upon discovery, of such conditions and make arrangements to
administer the examination at a mutually acceptable date.
We understand that your staff will develop the examinations, unless we determine it is
necessary for the NRC to develop an examination in which case, we will notify you immediately.
The examinations have been individually scheduled for two weeks because your letter indicated
that there were more than nine applicants being considered for each of these examinations.
Please inform us if the number of candidates change for any examination as this will impact the
examination schedule. Also, please inform us at your earliest opportunity if you discover you
need to change the scheduled dates for the examinations.
A supplementary letter will be sent to the training department approximately 120 days prior to
the examination informing the training manager of the chief examiners name. The letter will
also outline examination security expectations, list the materials required by the NRC to conduct
the examination, reconfirm the examination date, and reconfirm the number of candidates you
have in the Training Program.
B. Hanson -2-
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
of this letter will be available electronically for public inspection in the NRCs Public Document
Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide
Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC
Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief
Operations Branch
Division of Reactor Safety
Docket No. 50-461
License No. NPF-62
cc: Distribution via LISTSERV
B. Hanson -2-
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
of this letter will be available electronically for public inspection in the NRCs Public Document
Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide
Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC
Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Hironori Peterson, Chief
Operations Branch
Division of Reactor Safety
Docket No. 50-461
License No. NPF-62
cc: Distribution via LISTSERV
DISTRIBUTION:
Kimyata MorganButler
RidsNrrDorlLpl3-2 Resource
RidsNrrPMClinton Resource
RidsNrrDirsIrib Resource
Cynthia Pederson
Darrell Roberts
Eric Duncan
Allan Barker
Carole Ariano
Linda Linn
DRSIII
DRPIII
Jim Clay
Carmen Olteanu
Scott Sloan
ADAMS Accession Number ML15030A088
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII RIII RIII RIII
NAME RKWalton:jw HPeterson
DATE 01/23/15 01/28/15
OFFICIAL RECORD COPY