ML14352A050

From kanterella
Jump to navigation Jump to search
Commitment Summary Report
ML14352A050
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 12/12/2014
From: John Carlin
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML14352A050 (4)


Text

Tennessee Valley Authority, Post Office Box 2000, Soddy Daisy, Tennessee 37384-2000 December 12, 2014 10 CFR 50.4 ATTN: Document Control Desk U. S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Sequoyah Nuclear Plant, Units 1 and 2 Facility Operating License Nos. DPR-77 and DPR-79 NRC Docket Nos. 50-327 and 50-328

Subject:

Commitment Summary Report The purpose of this letter is to provide the Sequoyah Nuclear Plant (SQN), Units 1 and 2, Commitment Summary Report for June 30, 2013, through November 30, 2014. This report, which summarizes docketed commitments the Tennessee Valley Authority (TVA) has evaluated and revised using administrative controls during this time period, is provided in accordance with the Nuclear Energy Institute's "Guidelines for Managing NRC Commitment Changes," as endorsed in Nuclear Regulatory Commission Regulatory Issue Summary 2000-17.

Please direct any questions concerning this report to Erin Henderson at (423) 843-7170.

e ctf~,

StV President Sequoyah Nuclear Plant

Enclosure:

See page 2 cc: See page 2 Th1-

U.S. Nuclear Regulatory Commission Page 2 December 12, 2014

Enclosure:

Commitment Summary Report cc (Enclosure):

NRC Regional Administrator-Region II NRC Senior Resident Inspector - Sequoyah Nuclear Plant

ENCLOSURE TENNESSEE VALLEY AUTHORITY (TVA)

SEQUOYAH NUCLEAR PLANT (SQN)

UNITS 1 AND 2 COMMITMENT

SUMMARY

REPORT E-1

COMMITMENT

SUMMARY

REPORT An evaluation of the below listed commitment was performed in accordance with NEI 99-04. The evaluation determined that the change requires NRC notification based on the provided justification. Because this commitment was initiated as a result of a response to a Bulletin; response to an information request under 10 CFR 50.54(f); or basis for a safety decision in a safety evaluation report, it has been tabulated in the commitment summary report for NRC notification.

Commitment Evaluation No./

source Summary of Summary of BaslslJustlflcatlon Commitment D.cumont Orgihal Gommltment Commitment for Changes Tracking No.

Changes 2013-Ol/

SQN Units 1 and 2 TVA will complete the SQN in-vessel Original TVA informed NRC on May 16, 2013, of our NCO0090003001 Response to downstream effects evaluation following commitment commitment to perform an evaluation of WCAP-Generic Letter issuance of the final NRC Safety was 16793-NP following NRC approval; document the 2004-02 (TAC Evaluation Report (SER) for Topical Report superseded results in appropriate site documents; and submit Nos. MC4717 and No. WCAP-16793-NP, "Evaluation of Long-and a our disposition to NRC. The original commitment MC4718) dated Term Cooling Considering Particulate, completion was superseded by the May 16 letter, and replaced February 23, 2009. Fibrous, and Chemical Debris in the date was with a commitment of the same intent with a final Recirculating Fluid." Following completion established, completion date.

of the evaluation the results will be submitted to NRC.

E-2