Letter Sequence Withdrawal |
---|
TAC:MF2863, Clarify Application of Setpoint Methodology for LSSS Functions (Withdrawn, Closed) |
|
MONTHYEARGO2-13-138, License Amendment Request for Adoption of TSTF-493, Revision 4, Option a2013-10-0202 October 2013 License Amendment Request for Adoption of TSTF-493, Revision 4, Option a Project stage: Request ML13317C1042013-11-13013 November 2013 NRR E-mail Capture - Acceptance Review Project stage: Acceptance Review ML14111A0932014-04-30030 April 2014 Request for Additional Information - License Amendment Request to Adopt TSTF-493-A, Revision 4, Clarify Application of Setpoint Methodology for LSSS Functions, Option a Project stage: RAI GO2-14-103, Proposed Revision to License Amendment Request to Adopt TSTF-493, Revision 4, Option a, and Response to Request for Additional Information2014-06-19019 June 2014 Proposed Revision to License Amendment Request to Adopt TSTF-493, Revision 4, Option a, and Response to Request for Additional Information Project stage: Response to RAI ML14211A1332014-07-30030 July 2014 NRR E-mail Capture - Fyi: Follow Up Question for Columbia, Regarding Implementation of TSTF-493, Option a Project stage: Other ML14251A0802014-09-0505 September 2014 NRR E-mail Capture - Follow Up Question for Columbia, Regarding Implementation of TSTF-493, Option a Project stage: Other ML14307A8692014-11-0303 November 2014 Agenda for Meeting with TSTF Project stage: Request GO2-14-164, Response to NRC Request for Additional Information Re License Amendment Request for Adoption of TSTF-493, Revision 4, Option a2014-11-17017 November 2014 Response to NRC Request for Additional Information Re License Amendment Request for Adoption of TSTF-493, Revision 4, Option a Project stage: Response to RAI ML14349A4942014-12-0909 December 2014 Withdrawal of License Amendment Request for Adoption of TSTF-493, Revision 4, Option a Project stage: Withdrawal ML14351A4412014-12-22022 December 2014 Letter, Withdrawal of License Amendment Request, Adoption of TSTF-493-A, Revision 4, Clarify Application of Setpoint Methodology for LSSS Functions, Option a Project stage: Withdrawal ML15008A0042015-01-13013 January 2015 Correction Letter, Withdrawal of License Amendment Request, Adoption of TSTF-493-A, Revision 4, Clarify Application of Setpoint Methodology for LSSS Functions, Option a Project stage: Withdrawal ML14352A0802015-01-13013 January 2015 Federal Register Notice, Withdrawal of License Amendment Request, Adoption of TSTF-493-A, Revision 4, Clarify Application of Setpoint Methodology for LSSS Functions, Option a Project stage: Withdrawal NRC-2014-0010, Federal Register Notice, Withdrawal of License Amendment Request, Adoption of TSTF-493-A, Revision 4, Clarify Application of Setpoint Methodology for LSSS Functions, Option a2015-01-13013 January 2015 Federal Register Notice, Withdrawal of License Amendment Request, Adoption of TSTF-493-A, Revision 4, Clarify Application of Setpoint Methodology for LSSS Functions, Option a Project stage: Withdrawal 2014-12-09
[Table View] |
|
---|
Category:Letter
MONTHYEARGO2-24-004, License Amendment Request to Revise Emergency Plan2024-01-30030 January 2024 License Amendment Request to Revise Emergency Plan IR 05000397/20230042024-01-29029 January 2024 Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001 GO2-24-003, Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing2024-01-29029 January 2024 Relief Requests for the Columbia Generating Station Fifth Ten-Year Interval Inservice Testing ML24011A1522024-01-10010 January 2024 March 2024 Emergency Preparedness Exercise Inspection-Request for Information GO2-24-005, Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-1702024-01-0808 January 2024 Docket No. 50-397 Supplement to Reply to a Notice of Violation; EA-21-170 GO2-23-136, Guarantee of Payment of Deferred Premium2023-12-20020 December 2023 Guarantee of Payment of Deferred Premium GO2-23-135, Notice of Readiness for Supplemental Inspection2023-12-14014 December 2023 Notice of Readiness for Supplemental Inspection GO2-23-130, Reply to a Notice of Violation; EA-23-0542023-12-14014 December 2023 Reply to a Notice of Violation; EA-23-054 GO2-23-105, Licensing Basis Document Update and Biennial Commitment Change Report2023-12-12012 December 2023 Licensing Basis Document Update and Biennial Commitment Change Report ML23288A0002023-12-0707 December 2023 Issuance of Amendment No. 272 to Adopt TSTF-541, Revision 2, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-107, Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation2023-12-0505 December 2023 Application to Revise Technical Specifications to Adopt TSTS-584, Eliminate Automatic RWCU System Isolation on SLC Initiation GO2-23-126, Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-012023-11-28028 November 2023 Docket No. 50-397 Voluntary Response to Regulatory Issue Summary 2023-01 GO2-23-121, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-27027 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000397/20230122023-11-20020 November 2023 Commercial Grade Dedication Inspection Report 05000397/2023012 ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV IR 05000397/20230102023-11-0909 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000397/2023010 IR 05000397/20230932023-11-0101 November 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023093 ML23299A2072023-10-26026 October 2023 Biennial Requalification Inspection Request for Information IR 05000397/20230032023-10-25025 October 2023 Integrated Inspection Report 05000397/2023003 IR 05000397/20230112023-10-0404 October 2023 License Renewal Phase 2 Report 05000397/2023011 IR 05000397/20234012023-09-11011 September 2023 Security Baseline Inspection Report 05000397/2023401 GO2-23-097, In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26)2023-09-0606 September 2023 In-Service Inspection Summary Report for the Twenty-Sixth Refueling Outage (R26) ML24032A2182023-09-0101 September 2023 Information Request, Security IR 2024401 GO2-23-100, Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication2023-08-31031 August 2023 Technical Specification Section 5.6.4 Post Accident Monitoring Instrumentation 14-Day Report for Inoperable Suppression Pool Level Indication GO2-23-056, Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2023-08-29029 August 2023 Application to Revise Technical Specifications to Adopt TSTF-230, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000397/20230052023-08-22022 August 2023 Updated Inspection Plan for Columbia Generating Station (Report 05000397/2023005) - Mid Year Letter IR 05000397/20230022023-08-0101 August 2023 Integrated Inspection Report 05000397/2023002 GO2-23-093, Supplement to Reply to a Notice of Violation: EA-21-1702023-07-27027 July 2023 Supplement to Reply to a Notice of Violation: EA-21-170 ML23206A2442023-07-25025 July 2023 Energy Northwest Columbia Generating Station, Response to Apparent Violation in NRC Inspection Report 05000397/2023092; EA-23-054 GO2-23-068, Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation2023-07-19019 July 2023 Notification of Completion of Commitments Required Prior to Entry Into the Period of Extended Operation GO2-23-090, Reply to a Notice of Violation2023-07-12012 July 2023 Reply to a Notice of Violation ML23143A1202023-06-27027 June 2023 Request Number 4ISI-11 to the American Society of Mechanical Engineers Boiler and Pressure Vessel Code Regarding Alternate Examination of Reactor Vessel Welds GO2-23-073, Notification of NPDES Permit Issuance2023-06-26026 June 2023 Notification of NPDES Permit Issuance ML23163A2502023-06-12012 June 2023 Summary of Changes and Analysis for Revision 41 of Plant Procedures Manual 13.8.1 Emergency Dose Projection System Operations GO2-23-072, Cycle 27 Core Operating Limits Report2023-06-0505 June 2023 Cycle 27 Core Operating Limits Report ML23157A2702023-06-0101 June 2023 4-2022-011 -022 Letter - OI Closure to Licensee IR 05000397/20230922023-06-0101 June 2023 NRC Inspection Report 05000397/2023092 and Preliminary White Finding IR 05000397/20230902023-06-0101 June 2023 Final Significance Determination of a White Finding, Notice of Violation and Follow-Up Assessment Letter; NRC Inspection Report 05000397/2023090 GO2-23-055, Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Independent Spent Fuel Storage Installation, 2022 Annual Radiological Environmental Operating Report IR 05000397/20230012023-05-0505 May 2023 Integrated Inspection Report 05000397/2023001 - April 26, 2023 GO2-23-006, License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications2023-05-0101 May 2023 License Amendment Request to Clean-Up Operating License and Appendix a Technical Specifications IR 05000397/20233012023-05-0101 May 2023 NRC Examination Report 05000397/2023301 GO2-23-053, 2022 Annual Environmental Operating Report2023-04-26026 April 2023 2022 Annual Environmental Operating Report GO2-23-057, 2022 Annual Radioactive Effluent Release Report2023-04-25025 April 2023 2022 Annual Radioactive Effluent Release Report ML23110A2642023-04-20020 April 2023 Request for Information License Renewal Phase 2 Inspection GO2-23-012, Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position2023-03-27027 March 2023 Application to Revise Technical Specifications to Adopt Tstf-541, Add Exceptions to Surveillance Requirements for Valves and Dampers Locked in the Actuated Position GO2-23-041, Generation Station - Level of Financial Protection - Annual Reporting Requirement2023-03-15015 March 2023 Generation Station - Level of Financial Protection - Annual Reporting Requirement GO2-23-038, Plant Decommissioning Fund Status Report2023-03-15015 March 2023 Plant Decommissioning Fund Status Report ML23013A0812023-03-15015 March 2023 Issuance of Amendment No. 270 Revision to Technical Specifications to Adopt TSTF 505, Revision 2, Provide Risk-Informed Extended Completion Times-RITSTF Initiative 4B GO2-23-034, Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.462023-03-13013 March 2023 Report of Changes or Errors in Emergency Core Cooling System Loss of Coolant Accident Analysis Models Pursuant to 10 CFR 50.46 2024-01-08
[Table view] |
Text
Alex L. Javorik ENERGY Box 968,Station Generating ColumbiaP.O. PE04 Richland, WA 99352-0968 509.377.8555 Ph.aljavorik@ 1F. 509.377.2354 energy-northwest.com DEC 0 9 2014 G02-14-169 10 CFR 50.90 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001
Subject:
COLUMBIA GENERATING STATION, DOCKET NO. 50-397 WITHDRAWAL OF LICENSE AMENDMENT REQUEST FOR ADOPTION OF TSTF-493, REVISION 4, OPTION A
References:
- 1) Letter G02-13-138 dated October 2, 2013, A. L. Javorik (Energy Northwest) to NRC, "License Amendment Request for Adoption of TSTF-493, Revision 4, Option A"
- 2) Letter dated April 30, 2014, C. F. Lyon (NRC) to M. E. Reddemann (Energy Northwest), "Columbia Generating Station - Request for Additional Information related to License Amendment Request to Adopt TSTF-493, Revision 4, Option A (TAC No. MF2863)"
- 3) Letter G02-14-103 dated June 19, 2014, A. L. Javorik (Energy Northwest) to NRC, "Proposed Revision to License Amendment Request to Adopt TSTF-493, Revision 4, Option A, and Response to Request for Additional Information"
- 4) E-mail dated October 9, 2014, A. E. George (NRC) to L. L. Williams (Energy Northwest), "FW: TSTF-493 request"
- 5) Letter G02-14-164 dated November 17, 2014, A. L. Javorik (Energy Northwest) to NRC, "Response to NRC Request for Additional Information related to License Amendment Request for Adoption of TSTF-493, Revision 4, Option A"
Dear Sir or Madam:
In Reference 1, Energy Northwest submitted a License Amendment Request (LAR) to adopt TSTF-493, Revision 4, Option A. In References 2 and 4, the Nuclear Regulatory Commission (NRC) requested additional information in order to complete the review.
Energy Northwest submitted responses to the NRC requests via References 3 and 5.
ADO
WITHDRAWAL OF LICENSE AMENDMENT REQUEST FOR ADOPTION OF TSTF-493, REVISION 4, OPTION A Page 2 of 2 After further consideration, following discussion with NRC staff, Energy Northwest respectfully withdraws the proposed LAR. As discussed at the November 13, 2014, meeting between NRC and the Technical Specification Task Force (TSTF) (ADAMS Accession No. ML14307A869), the TSTF is planning to clarify the intent of the terminology "change to a setpoint value." This may result in a potential revision to the traveler and the associated model application and model Safety Evaluation for TSTF-493 Option A. The TSTF is also planning to work with NRC on the required content of license applications proposing to adopt Option B of TSTF-493. Option B adds a new program to the Administrative Controls section of the Technical Specifications titled the Setpoint Control Program and allows the relocation of instrument Allowable Values from the Technical Specifications to licensee control. Energy Northwest plans to monitor the status of these activities in order to determine the best option to pursue in the future.
No new regulatory commitments are being made in this submittal.
Should you have any questions or require additional information regarding this matter, please contact Ms. L. L. Williams, Licensing Supervisor, at (509)377-8148.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on _-"xeYQOe-r 7 , 2014.
A. L. Javorik Vice President, Engineering cc: NRC Region IV Administrator NRC NRR Project Manager NRC Sr. Resident Inspector - 988C MA Jones- BPA/1 399 (email)
WA Horin - Winston & Strawn (email)
RR Cowley - WDOH (email)
JO Luce - EFSEC (email)