Request for Approval of Cyber Security Plan Revised Implementation Schedule
ML14329A313
Person / Time
Site: Millstone, Kewaunee, Surry, North Anna  Dominion icon.png
Issue date: 11/17/2014
From: Clark G
Dominion Resources Services
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML14329A351 List:
References
14-306
Download: ML14329A313 (33)


Text

Dominion Resources Services, Inc.

Innsbrook Technical Center J

5000 Dominion Boulevard, 2SE, Glen Allen, VA 23060 SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 November 17, 2014 U.S. Nuclear Regulatory Commission Serial No.:

14-306 Attention: Document Control Desk NL&OS/MAE: RO Washington, D.C. 20555-0001 Docket Nos.:

50-305 50-336/423 50-338/339 50-280/281 License Nos.: DPR-43 DPR-65 NPF-49 NPF-4/7 DPR-32/37 DOMINION ENERGY KEWAUNEE, INC.

DOMINION NUCLEAR CONNECTICUT, INC.

VIRGINIA ELECTRIC AND POWER COMPANY KEWAUNEE POWER STATION MILLSTONE POWER STATION UNITS 2 AND 3 NORTH ANNA POWER STATION UNITS 1 AND 2 SURRY POWER STATION UNITS 1 AND 2 REQUEST FOR APPROVAL OF CYBER SECURITY PLAN REVISED IMPLEMENTATION SCHEDULE The NRC documented the approval of a fleet Cyber Security Plan (CSP) for Dominion Energy Kewaunee, Inc. (DEK), Dominion Nuclear Connecticut, Inc. (DNC), and Virginia Electric and Power Company (Dominion) by issuing amendments to the Operating Licenses (OLs) for Kewaunee, North Anna, and Surry Power Stations on August 31, 2011 and for Millstone Power Station on September 30, 2011.

The amendments required that all subsequent changes to the NRC-approved CSP implementation schedule be approved by the NRC pursuant to 10 CFR 50.90.

The fleet CSP implementation schedule was provided in an April 4, 2011 letter. Pursuant to 10 CFR 50.90, DEK, DNC, and Dominion are requesting a change to the fleet CSP implementation schedule, specifically Milestone 8, the full implementation date. provides an evaluation of the proposed license changes. Enclosure 2 provides the proposed OL changes. Enclosure 3 provides the proposed revised Fleet Implementation Schedule for the CSP.

The only change to the schedule is the revised regulatory commitment date for full implementation of the NRC approved CSP (Milestone 8).

DEK, DNC, and Dominion request that Enclosures 1 and 3, which contain Security-Related Enclosures 1 and 3 to this letter contain Security-Related Information which is to be withheld from public disclosure under 10 CFR 2.390. Upon removal of Enclosures 1 and 3, this letter is decontrolled.

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390--

r

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 Serial No.14-306 Page 2 of 5 Information, be withheld from public disclosure in accordance with 10 CFR 2.390.

For the proposed license conditions, DEK, DNC, and Dominion request approval of the license amendments by October 1, 2015 and implementation periods of 30 days following NRC approval of the license amendments.

If you have any questions regarding this submittal, please contact Margaret A. Earle at (804) 273-2768.

Sincerely, Gianna C. Clark Vice President - Nuclear Support Services - Evaluation of Proposed Change (Security-Related Information) - Attachment 1 - Proposed Operating License Changes (Mark-Ups) - Proposed Operating License Changes (Re-Typed) - Cyber Security Plan Implementation Schedules (Security-Related Information)

Commitments made in this letter:, Cyber Security Plan Implementation Schedule COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO The foregoing document was acknowledged before me, in and for the County and Commonwealth aforesaid, today by Gianna C. Clark, who is Vice President - Nuclear Support Services, of Dominion Energy Kewaunee, Inc., Dominion Nuclear Connecticut, Inc., and Virginia Electric and Power Company. She has affirmed before me that she is duly authorized to execute and file the foregoing document in behalf of these Companies, and that the statements in the document are true to the best of her knowledge and belief.

Acknowledged before me this I1t'kday of J6VJ.-*,,

", 2014.

My Commission Expires:

12 311 I, ICRAIG D SLY Notary Public lqtr bi I

Commonwealth of Virginia Reg. # 7518653 2, 4 My Commission Expires December 31,20&

Enclosures 1 and 3 to this letter contain Security-Related Information which is to be withheld from public disclosure under 10 CFR 2.390. Upon removal of Enclosures 1 and 3, this letter is decontrolled.

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 Serial No.14-306 Page 3 of 5 cc:

U. S. Nuclear Regulatory Commission, Region I Attn.: Regional Administrator 2100 Renaissance Blvd., Suite 100 King of Prussia, PA 19406-2713 U. S. Nuclear Regulatory Commission, Region II Attn.: Regional Administrator 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, Georgia 30303-1257 U. S. Nuclear Regulatory Commission, Region III Attn: Regional Administrator 2443 Warrenville Road Suite 210 Lisle, Illinois 60532-4352 State Health Commissioner (w/o Enclosures 1 and 3)

Virginia Department of Health James Madison Building - 7 th floor 109 Governor Street Room 730 Richmond, VA 23219 Director (w/o Enclosures 1 and 3)

Bureau of Air Management Monitoring and Radiation Division Department of Environmental Protection 79 Elm Street Hartford, Connecticut 06106-5127 Public Service Commission of Wisconsin (w/o Enclosures 1 and 3)

Electric Division P. 0. Box 7854 Madison, WI 53707 Enclosures 1 and 3 to this letter contain Security-Related Information which is to be withheld from public disclosure under 10 CFR 2.390. Upon removal of Enclosures 1 and 3, this letter is decontrolled.

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390

N, SECURITY-RELATED INFORMATION -WITHHOLD UNDER 10 CFR 2.390 Serial No.14-306 Page 4 of 5 Mr. W. C. Huffman (w/o Enclosures 1 and 3)

NRC Project Manager Kewaunee Power Station U. S. Nuclear Regulatory Commission Mail Stop 0 8 D-15 One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Mr. T. R. Smith (w/o Enclosures 1 and 3)

NRC Decommissioning Project Manager Kewaunee Power Station U. S. Nuclear Regulatory Commission Mail Stop T8-F05 One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Mr. M. C. Thadani (w/o Enclosures 1 and 3)

NRC Senior Project Manager Millstone Power Station Units 2 & 3 U. S. Nuclear Regulatory Commission Mail Stop 0 8-B 1 One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Dr. V. Sreenivas (w/o Enclosures 1 and 3)

NRC Project Manager North Anna Power Station U. S. Nuclear Regulatory Commission Mail Stop 0 8 G-9A One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Ms. K. Cotton (w/o Enclosures I and 3)

NRC Project Manager Surry Power Station U. S. Nuclear Regulatory Commission Mail Stop 0 8 G-9A One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 Enclosures 1 and 3 to this letter contain Security-Related Information which is to be withheld from public disclosure under 10 CFR 2.390. Upon removal of Enclosures 1 and 3, this letter is decontrolled.

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390

SECURITY-RELATED INFORMATION -WITHHOLD UNDER 10 CFR 2.390 Serial No.14-306 Page 5 of 5 NRC Senior Resident Inspector (w/o Enclosures 1 and 3)

Millstone Power Station NRC Senior Resident Inspector (w/o Enclosures 1 and 3)

North Anna Power Station NRC Senior Resident Inspector (w/o Enclosures 1 and 3)

Surry Power Station Enclosures 1 and 3 to this letter contain Security-Related Information which is to be withheld from public disclosure under 10 CFR 2.390. Upon removal of Enclosures 1 and 3, this letter is decontrolled.

SECURITY-RELATED INFORMATION - WITHHOLD UNDER 10 CFR 2.390 Proposed Facility Operating License Changes (Mark-Ups)

Proposed Facility Operating License Change (Re-Typed)

Dominion Energy Kewaunee, Inc.

Dominion Nuclear Connecticut, Inc.

Virginia Electric and Power Company

Serial No.14-306 Proposed Facility Operating License Changes (Mark-Ups)

Dominion Energy Kewaunee, Inc.

Dominion Nuclear Connecticut, Inc.

Virginia Electric and Power Company

Serial No.14-306, Attachment 1 Insert A is to be included as indicated on the following marked-up License pages.

Insert A:

, as supplemented by a change approved by License Amendment No.

Serial No.14-306, Attachment 1 Kewaunee Power Station License Condition Note: Markups of the current Operating License as well as the proposed Defueled Operating License are provided.

(4)

Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21 is entitled:

"Nuclear Management Company Kewaunee Nuclear Power Plant Physical Security Plan (Revision 0)" submitted by letter dated October 18, 2004, and supplemented by letter dated October 21, 2004, July 26, 2005, and May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 210,.

(5)

Deleted (6)

Steam Generator Upper Lateral Supports Insert A The design of the steam generator upper lateral supports may be modified by reducing the number of snubbers from four (4) to one (1) per steam generator.

(7)

Deleted (8)

Deleted (9)

Deleted (10)

Mitigqation Strategy License Condition Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(a)

Fire fighting response strategy with the following elements:

1.

Pre-defined coordinated fire response strategy and guidance

2.

Assessment of mutual aid fire fighting assets

3.

Designated staging areas for equipment and materials

4.

Command and control

5.

Training of response personnel Amendment No. 216

-081+/et1921 (4)

Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21 is entitled:

"Nuclear Management Company Kewaunee Nuclear Power Plant Physical Security Plan (Revision 0)" submitted by letter dated October 18, 2004, and supplemented by letter dated October 21, 2004, July 26, 2005, and May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 210/

(5)

Deleted (6)

DeletedSteam42GeneraterUppier LaterFa Snppers The desogR of the steam generator upper lateral supports may be modified by reducinig the number of snubbers from four (4) t9 one (1) per setam NOTE: Deletion of License Condition 2.C.(6)

(7)

Deleted is justified separately in LAR 256.

(8)

Deleted (9)

Deleted (10)

Mitigation Strategy License Condition Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(a)

Fire fighting Response strategy with the following elements:

1.

Pre-defined coordinated fire response strategy and guidance

2.

Assessment of mutual aid fire fighting assets

3.

Designated staging areas for equipment and materials

4.

command and control

5.

Training of response personnel Renewed Operating License DPR-43

Serial No.14-306, Attachment 1 Millstone Power Station Units 2 and 3 License Conditions

Sespembe 3, 2011I (3)

Fire Protection The licensee shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report and as approved in the SER dated September 19, 1978, and supplements dated October 21, 1980, November 11, 1981, October 31, 1985, April 15, 1986, January 15, 1987, April 29, 1988, July 17, 1990, and November 3, 1995, subject to the following provision:

The licensee may make changes to the approved Fire Protection Program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

(4)

Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, submitted by letter dated October 15, 2004, as supplemented by letter dated May 15, 2006, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 0" The set contains Safeguards Information protected under 10 CFR 73.21.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 309/ ý'---Insert A (5)

Relocated Technical Specifications The licensee shall relocate certain technical specification requirements to licensee-controlled documents as described below. The location of these requirements shall be retained by the licensee.

a. This license condition approves the relocation of certain technical specification requirements to licensee-controlled documents (Technical Requirements Manual), as described in the licensee's application dated May 20, 1997, as supplemented on September 23, 1997. The approval is documented in the staffs safety evaluation dated November 19, 1997.

This license condition is effective as of its date of issuance by Amendment No. 210 and shall be implemented 90 days from the date of issuance.

Implementation shall include the relocation of technical specification requirements to the appropriate licensee-controlled document as identified in the licensee's application dated May 20, 1997, as supplemented on September 23, 1997.

Renewed License No. DPR-65 Revised by Nct, dated May 29, 200 Amendment No. 309-

-SupLumber 030@20t1-E.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training, and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, submitted by letter dated October 15, 2004, as supplemented by letter dated May 15, 2006, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 0" The set contains Safeguards Information protected under 10 CFR 73.21.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Am endm ent No. 251/

`1_..

F.

Deleted.

G.

The licensee shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.

H.

Fire Protection (Section 9.5.1. SER, SSER 2, SSER 4, SSER 5)

DNC shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report for the facility and as approved in the SER (NUREG-1031) issued July 1985 and Supplements Nos. 2, 4, and 5 issued September 1985, November 1985, and January 1986, respectively, subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

This renewed operating license is effective as of its date of issuance and shall expire at midnight on November 25, 2045.

FOR THE NUCLEAR REGULATORY COMMISSION

/ RA/

J. E. Dyer, Director Attachments:

Office of Nuclear Reactor Regulation

1. Appendix A - Technical Specifications
2. Appendix B - Environmental Protection Plan Date of Issuance: November 28, 2005 Renewed License No. NPF-49 Amendment No. 2-4,251

Serial No.14-306, Attachment 1 North Anna Power Station Units 1 and 2 License Conditions (4) The licensee is authorized to receive from the Surry Power Station, Unit Nos. 1 and 2, possess, and store irradiated Surry Power Station fuel assemblies containing special nuclear material, enriched to not more than 4.1 percent by weight U-235, subject to the following conditions:

a. Surry Power Station fuel assemblies may not be placed in North Anna Power Station, Unit Nos. I and 2, reactors.
b. Irradiated fuel shipped to North Anna Power Station shall have been removed from the Surry Power Station reactors no less than 730 days prior to shipment.
c. No more than 500 Surry Power Station irradiated fuel assemblies shall be received for storage at the North Anna Power Station, Unit Nos. 1 and 2, spent fuel pool.

(5) Environmental Protection Plan The Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 197, is hereby incorporated in the renewed license.

The licensee shall operate the facility in accordance with the Environmental Protection Plan.

D. Fire Protection VEPCO shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report for the facility and as approved in the SER dated February 1979 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No.264/

NORTH ANNA - UNIT I Renewed License No. NPF-4 Amendment No. -264-

-e8-3444- (4) The licensee is authorized to receive from the Surry Nuclear Power Station, Unit Nos. 1 and 2, possess, and store irradiated Surry Power Station fuel assemblies containing special nuclear material, enriched to not more than 4.1 percent by weight U-235, subject to the following conditions:

a. Surry Power Station fuel assemblies may not be placed in North Anna Power Station, Unit Nos. 1 and 2, reactors.
b. Irradiated fuel shipped to North Anna Power Station shall have been removed from the Surry Power Station reactors no less than 730 days prior to shipment.
c. No more than 500 Surry Power Station irradiated fuel assemblies shall be received for storage at the North Anna Power Station, Unit Nos. I and 2, spent fuel pool.

(5) Environmental Protection Plan The Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 178, is hereby incorporated in the renewed license.

The licensee shall operate the facility in accordance with the Environmental Protection Plan.

D. Fire Protection VEPCO shall implement and maintain in effect all provisions of the approved-fire protection program as described in the licensee's Updated Final Safety Analysis Report for the facility and as approved in the SER dated February 1979 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 245/,-_.__lsrt NORTH ANNA - UNIT 2 I

Renewed License No. NPF-7 Amendment No. 24&5

Serial No.14-306, Attachment 1 Surry Power Station Units 1 and 2 License Conditions

-ea~si~ii~ July 23, 1992), and the Safety Evaluation issued December 16, 1998, for Technical Specification Amendment No. 217 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

J. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 276y, K. Deleted by Amendment 227

"'"lsrA L. Deleted by Amendment 227 M. Deleted by Amendment 227 N. Deleted by Amendment No. 203

0. Deleted by Amendment 227 P Updated Final Safety Analysis Report (1) The Updated Final Safety Analysis Report supplement submitted pursuant to 10 CFR 54.21(d), as revised on July 25, October 1, November 4, and December 2, 2002, describes certain future inspection activities to be completed before the period of extended operation. The licensee shall complete these activities no later than May 25, 2012, and shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection.

Surry - Unit 1 Renewed License No. DPR-32 Amendment No. 276-I. Fire Protection The licensee shall implement and maintain in effect the provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report and as approved in the SER dated September 19, 1979 (and Supplements dated May 29, 1980, October 9, 1980, December 18, 1980, February 13, 1981, December 4, 1981, April 27, 1982, November 18, 1982, January 17, 1984, February 25, 1988, and July 23, 1992), and the Safety Evaluation issued December 16, 1998, for Technical Specification Amendment No. 217 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

J. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 2 7 6 1 K. Deleted by Amendment 227 L. Deleted by Amendment 227 Insert A M. Deleted by Amendment 227 N. Deleted by Amendment 203

0. Deleted by Amendment 227 Surry - Unit 2 Renewed License No. DPR-37 Amendment No. 2%-

q Serial No.14-306 Proposed Facility Operating License Change (Re-Typed)

Dominion Energy Kewaunee, Inc.

Dominion Nuclear Connecticut, Inc.

Virginia Electric and Power Company

Serial No.14-306 Kewaunee Power Station License Condition Note: Re-Typed pages of the current Operating License as well as the proposed Defueled Operating License are provided.

(4)

Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21 is entitled:

"Nuclear Management Company Kewaunee Nuclear Power Plant Physical Security Plan (Revision 0)" submitted by letter dated October 18, 2004, and supplemented by letter dated October 21, 2004, July 26, 2005, and May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 210, as supplemented by a change approved by License Amendment No.

(5)

Deleted (6)

Steam Generator Upper Lateral Supports The design of the steam generator upper lateral supports may be modified by reducing the number of snubbers from four (4) to one (1) per steam generator.

(7)

Deleted (8)

Deleted (9)

Deleted (10)

Mitigation Strategy License Condition Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(a)

Fire fighting response strategy with the following elements:

1.

Pre-defined coordinated fire response strategy and guidance

2.

Assessment of mutual aid fire fighting assets

3.

Designated staging areas for equipment and materials

4.

Command and control

5.

Training of response personnel Renewed Operating License DPR-43 Amendment No.

I (2)

Technical Soecifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 214, are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications.

(3)

Deleted (4)

Physical Protection The licensee shall fully implement and maintain In effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21 is entitled:

"Nuclear Management Company Kewaunee Nuclear Power Plant Physical Security Plan (Revision 0)" submitted by letter dated October 18, 2004, and supplemented by letter dated October 21, 2004, July 26, 2005, and May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 210, as supplemented by a change approved by License Amendment No.

(5)

Deleted (6)

Deleted (7)

Deleted (8)

Deleted (9)

Deleted (10)

Mitigation Strateg License Condition Develop and maintain strategies for addressing large fires and explosions and that include the following key areas:

(a)

Fire fighting response strategy with the following elements:

1.

Pre-defined coordinated fire response strategy and guidance

2.

Assessment of mutual aid fire fighting assets

3.

Designated staging areas for equipment and materials

4.

Command and control

5.

Training of response personnel Renewed Operating License DPR-43 Amendment No.

I

Serial No.14-306 Millstone Power Station Units 2 and 3 License Conditions (3)

Fire Protection The licensee shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report and as approved in the SER dated September 19, 1978, and supplements dated October 21, 1980, November 11, 1981, October 31, 1985, April 15, 1986, January 15, 1987, April 29, 1988, July 17, 1990, and November 3, 1995, subject to the following provision:

The licensee may make changes to the approved Fire Protection Program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

(4)

Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, submitted by letter dated October 15, 2004, as supplemented by letter dated May 15, 2006, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 0" The set contains Safeguards Information protected under 10 CFR 73.21.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 309, as supplemented by a change approved by License Amendment No. _

(5)

Relocated Technical Specifications The licensee shall relocate certain technical specification requirements to licensee-controlled documents as described below. The location of these requirements shall be retained by the licensee.

a.

This license condition approves the relocation of certain techriical specification requirements to licensee-controlled documents (Technical Requirements Manual), as described in the licensee's application dated May 20, 1997, as supplemented on September 23, 1997. The approval is documented in the staff's safety evaluation dated November 19, 1997.

This license condition, is effective as of its date of issuance by Amendment No. 210 and shall be implemented 90 days from the date of issuance.

Implementation shall include the relocation of technical specification requirements to the appropriate licensee-controlled document as identified in the licensee's application dated May 20, 1997, as supplemented on September 23, 1997.

Renewed License No. DPR-65 Re.isid by Lot.o dated May 20, 2007 Amendment No. 3W E.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training, and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, submitted by letter dated October 15, 2004, as supplemented by letter dated May 15, 2006, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program, Revision 0" The set contains Safeguards Information protected under 10 CFR 73.21.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 251, as supplemented by a change approved by License Amendment No. _

F.

Deleted.

G.

The licensee shall have and maintain financial protection of such type and in such amounts as the Commission shall require in accordance with Section 170 of the Atomic Energy Act of 1954, as amended, to cover public liability claims.

H.

Fire Protection (Section 9,5.1. SER. SSER 2..SSER 4, SSER 5)

DNC shall implement and maintain in effect all provisions of the approved fire protection program as described in the Final Safety Analysis Report for the facility and as approved in the SER (NUREG-1031) issued July 1985 and Supplements Nos. 2, 4, and 5 issued September 1985, November 1985, and January 1986, respectively, subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

This renewed operating license is effective as of its date of issuance and shall expire at midnight on November 25, 2045.

FOR THE NUCLEAR REGULATORY COMMISSION I RA/

J. E. Dyer, Director Attachments:

Office of Nuclear Reactor Regulation

1. Appendix A - Technical Specifications
2. Appendix B - Environmental Protection Plan Date of Issuance: November 28, 2005 Renewed License No. NPF-49 Amendment No. 243, 31-

Serial No.14-306 North Anna Power Station Units 1 and 2 License Conditions (4) The licensee is authorized to receive from the Surry Power Station, Unit Nos. I and 2, possess, and store irradiated Surry Power Station fuel assemblies containing special nuclear material, enriched to not more than 4.1 percent by weight U-235, subject to the following conditions:

a, Surry Power Station fuel assemblies may not be placed in North Anna Power Station, Unit Nos. I and 2, reactors.

b. Irradiated fuel shipped to North Anna Power Station shall have been removed from the Surry Power Station reactors no less than 730 days prior to shipment.
c. No more than 500 Surry Power Station irradiated fuel assemblies shall be received for storage at the North Anna Power Station, Unit Nos. 1 and 2, spent fuel pool.

(5) Environmental Protection Plan The Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 197, is hereby incorporated in the renewed license.

The licensee shall operate the facility in accordance with the Environmental Protection Plan.

D. Fire Protection VEPCO shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report for the facility and as approved in the SER dated February 1979 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 264, as supplemented by a change approved by License Amendment No.

NORTH ANNA - UNIT I Renewed License No. NPF-4 Amendment No.

(4) The licensee is authorized to receive from the Surry Nuclear Power Station, Unit Nos. 1 and 2, possess, and store irradiated Surry Power Station fuel assemblies containing special nuclear material, enriched to not more than 4.1 percent by weight U-235, subject to the following conditions:

a. Surry Power Station fuel assemblies may not be placed in North Anna Power Station, Unit Nos. 1 and 2, reactors.
b. Irradiated fuel shipped to North Anna Power Station shall have been removed from the Surry Power Station reactors no less than 730 days prior to shipment.
c. No more than 500 Surry Power Station irradiated fuel assemblies shall be received for storage at the North Anna Power Station, Unit Nos. 1 and 2, spent fuel pool.

(5) Environmental Protection Plan The Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 178, is hereby incorporated in the renewed license.

The licensee shall operate the facility in accordance with the Environmental Protection Plan.

D. Fire Protection VEPCO shall implement and maintain in effect all provisions of the approved fire protection program as described in the licensee's Updated Final Safety Analysis Report for the facility and as approved in the SER dated February 1979 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

E. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 245, as supplemented by a change approved by License Amendment No.

NORTH ANNA - UNIT 2 Renewed License No. NPF-7 Amendment No.

Serial No.14-306 Surry Power Station Units 1 and 2 License Conditions July 23, 1992), and the Safety Evaluation issued December 16, 1998, for Technical Specification Amendment No. 217 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

J. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 276, as supplemented by a change approved by License Amendment No.

K. Deleted by Amendment 227 L. Deleted by Amendment 227 M. Deleted by Amendment 227 N. Deleted by Amendment No. 203

0. Deleted by Amendment 227 P Updated Final Safety Analysis Report (1) The Updated Final Safety Analysis Report supplement submitted pursuant to 10 CFR 54.21 (d), as revised on July 25, October 1, November 4, and December 2, 2002, describes certain future inspection activities to be completed before the period of extended operation. The licensee shall complete these activities no later than May 25, 2012, and shall notify the NRC in writing when implementation of these activities is complete and can be verified by NRC inspection.

Surry-Unit I Renewed License No. DPR-32 Amendment No. _

I. Fire Protection The licensee shall implement and maintain in effect the provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report and as approved in the SER dated September 19, 1979 (and Supplements dated May 29, 1980, October 9, 1980, December 18, 1980, February 13, 1981, December 4, 1981, April 27, 1982, November 18, 1982, January 17, 1984, February 25, 1988, and July 23, 1992), and the Safety Evaluation issued December 16, 1998, for Technical Specification Amendment No. 217 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

J. Physical Protection The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, guard training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822) and to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans, which contains Safeguards Information protected under 10 CFR 73.21, is entitled: "Millstone, North Anna and Surry Power Stations' Security Plan, Training, and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program" with revisions submitted through May 15, 2006.

The licensee shall fully implement and maintain in effect all provisions of the Commission-approved Kewaunee, Millstone, North Anna, and Surry Power Stations Cyber Security Plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 276, as supplemented by a change approved by License Amendment No. __.

K. Deleted by Amendment 227 L. Deleted by Amendment 227 M. Deleted by Amendment 227 N. Deleted by Amendment 203

0. Deleted by Amendment 227 Surry - Unit 2 Renewed License No. DPR-37 Amendment No.