Text
ES-201 Examination Preparation Checklist Form ES-201-1 Facility: DC Cook Nuclear Power Plant U1/U2 Date of Examination: 08/01/2014 Examinations Developed by: NRC Chief Target Examiner=s Task Description (Reference)
Date*
Initials k
-180 1. Examination administration date confirmed (C.1.a; C.2.a and b) dm
-120 2. NRC examiners and facility contact assigned (C.1.d; C.2.e) dm
-120 3. Facility contact briefed on security and other requirements (C.2.c) dm
-120 4. Corporate notification letter sent (C.2.d) dm
[-90] [5. Reference material due (C.1.e; C.3.c; Attachment 2)] dm
-75 6. Integrated examination outline(s) due, including Forms ES-201-2, ES-201-3, ES-301-1, ES-301-2, ES-301-5, ES-D-1's, ES-401-1/2, ES-401-3, and dm ES-401-4, as applicable (C.1.e and f; C.3.d)
-70 7. Examination outline(s) reviewed by NRC and feedback provided to facility dm licensee (C.2.h; C.3.e)
-45 8. Proposed examinations (including written, walk-through JPMs, and scenarios, as applicable), supporting documentation (including Forms dm ES-301-3, ES-301-4, ES-301-5, ES-301-6, and ES-401-6), and reference materials due (C.1.e, f, g and h; C.3.d)
-30 9. Preliminary license applications (NRC Form 398's) due (C.1.l; C.2.g; dm ES-202)
-14 10. Final license applications due and Form ES-201-4 prepared (C.1.l; C.2.i; dm ES-202)
-14 11. Examination approved by NRC supervisor for facility licensee review dm (C.2.h; C.3.f)
-14 12. Examinations reviewed with facility licensee (C.1.j; C.2.f and h; C.3.g) dm
-7 13. Written examinations and operating tests approved by NRC supervisor dm (C.2.i; C.3.h)
-7 14. Final applications reviewed; examination approval and waiver letters sent dm (C.2.i; Attachment 4; ES-204)
-7 15. Proctoring/written exam administration guidelines reviewed dm with facility licensee (C.3.k)
-7 16. Approved scenarios, job performance measures, and questions dm distributed to NRC examiners (C.3.i)
- Target dates are keyed to the examination date identified in the corporate notification letter.
They are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.
[ ] Applies only to examinations prepared by the NRC.