MONTHYEARBVY 13-095, Request for Approval of Certified Fuel Handler Training Program2013-10-31031 October 2013 Request for Approval of Certified Fuel Handler Training Program Project stage: Request BVY 13-105, Request for Rescission of Security Orders2013-12-18018 December 2013 Request for Rescission of Security Orders Project stage: Request BVY 14-010, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition2014-03-28028 March 2014 Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition Project stage: Request BVY 14-030, Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 12014-04-24024 April 2014 Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 1 Project stage: Supplement ML14140A3102014-05-20020 May 2014 NRR E-mail Capture - Acceptance Review for Vermont Yankee Defueled TS Amendment Project stage: Acceptance Review BVY 14-037, Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 22014-06-0909 June 2014 Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 2 Project stage: Supplement BVY 14-049, Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 32014-06-11011 June 2014 Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 3 Project stage: Supplement ML14210A1612014-07-29029 July 2014 NRR E-mail Capture - RAI - Defueld Technical Specification Amendment Project stage: RAI ML14231A0172014-08-13013 August 2014 Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 4 Project stage: Supplement BVY 15-001, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2015-01-12012 January 2015 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel Project stage: Request ML15033A0532015-01-30030 January 2015 NRR E-mail Capture - VY RAI from Dss/Srxb for MF3714 Project stage: RAI BVY 15-012, Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 52015-05-0404 May 2015 Technical Specifications Proposed Change No. 309, Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition - Supplement 5 Project stage: Supplement ML15117A5512015-10-0707 October 2015 Issuance of Amendment for Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition Project stage: Approval 2014-06-09
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML21075A1582021-03-15015 March 2021 E-mail from T. Silko to J. Parrott, NMSS, Vermont Yankee on the State of Vermont Comments on the Review of the Draft Final SER and EA for 20.2002 Alternate Disposal Request ML21006A0242020-12-22022 December 2020 E-mail from J. Parrott to J. Tierney and N. Creed Vermont Yankee Request to NRC for Alternate Disposal of Wastewater ML20358A0702020-12-22022 December 2020 E-mail Acceptance Review for Request for Indirect License Transfer (License DPR-28, Docket No. 50-271) ML20175A2122020-06-23023 June 2020 Acceptance Review of Request for Alternate Disposal of Wastes Under 10 CFR 20.2002 (License DPR-28, Docket No. 50-271) ML19289A1292019-10-11011 October 2019 Email from Daniel Doyle to Mark Leyse Status of PRM-50-93 and PRM-50-95 ML19288A0292019-10-11011 October 2019 NRC Acceptance Review - Northstar Request for Exemption from 10 CFR 20, App G, Section Iii.E (License DPR-28, Docket No. 50-271) ML19198A2512019-06-20020 June 2019 Alternate Disposal Request - Rail Shipments (License DPR-28, Docket No. 50-271) ML19059A1782019-02-28028 February 2019 Acceptance Review Results for Relief Request No. EN-19-RR-1 to Use ASME Code Case N-831-1 for Entergy Fleet ML18289A3622018-10-11011 October 2018 Email from Daniel Doyle to Mark Leyse Status of PRM-50-93 and PRM-50-95 ML18127A5582018-04-25025 April 2018 Email to State of Vermont on Vermont Yankee Nuclear Power Station - Forthcoming Issuance of a License Amendment Regarding the Requirement for the VYNPS to Have a Cyber Security Plan ML18045A0862018-01-25025 January 2018 Email Request for Review of the Draft Safety Evaluation for Implementation of a Revised Emergency Plan at Vermont Yankee to Reflect an ISFSI-only Configuration ML17353A0092017-12-18018 December 2017 E-Mail from William Irwin, Vermont Department of Health to Y. Chen/Dsfm Response: Draft Environmental Assessment: Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation ML17289A4222017-10-16016 October 2017 E-Mail from Y. J. Chen to W. Irwin Draft Environmental Assessment Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation ML17257A0022017-09-14014 September 2017 Email to VY Shpo W Ltr Re VYNPS Exemption Load Campaign - Sept 2017 ML17229B4842017-08-16016 August 2017 Request for Supplemental Documentation to Support Review of the Physical Security Plan ML17219A0472017-08-0303 August 2017 8/03/2017, E-Mail from Y. J. Chen/Nmss to T. B. Silko/Vermont Yankee Regarding Need for Additional Information Entergy'S Exemption Request for Vermont Yankee ISFSI, Dated May 16, 2017 (ML17142A358) ML17144A0452017-05-23023 May 2017 5/23/2017, E-Mail to I. William/Vermont Dept. of Health from Y. Chen/Nrc Response: Draft Environment Assessment: Exemption Request for Vermont Yankee Independent Spent Fuel Storage Installation (W/Attachment Ltr to Address Comments on EA) ML17080A4752017-03-16016 March 2017 3/16/2017, E-Mail from I. William/Vermont Department of Health to Yen-Ju Chen/Dsfm/Sflb, Providing Comments on Draft Environmental Assessment for Entergy/Vermont Yankee'S Exemption from Requirement of 10 CFR 72.7 for CoC No. 72-1014, Amendm ML17055A6262017-02-24024 February 2017 Cover Email from VY Shpo W Concurrence on No Effects Determination ML17040A3372017-02-0909 February 2017 Email and Letter to Vermont Shpo ISFSI Exemption No Effects Determination ML17038A4682017-02-0707 February 2017 2/07/2017, E-mail from Yen-Ju Chen/NRC-DSFM to W. Irwin/Vermont Dept. of Health Draft Environment Assessment for Entergy/Vermont Yankee'S Exemption from Requirement of 10 CFR 72.7 for Certificate of Compliance No. 72-1014, Amendment 10 ML17012A2472017-01-11011 January 2017 E-mail - State of Vermont Comments Regarding Vermont Yankee'S 10 CFR 20.2002 Request ML16349A2492016-12-13013 December 2016 E-Mail to T. B. Silko/Entergy from Yen-Ju Chen/Dsfm Regarding Need for Supplemental Information for Entergy'S Exemption Request for Vermont Yankee ISFSI, Dated November 9, 2016 (ML16319A102) ML17013A2502016-12-12012 December 2016 Email Requesting Review of Draft EA and SER for Vermont Yankee Request to NRC for Alternate Disposal of Waste ML16231A0282016-08-11011 August 2016 Response to NRC Questions Related to Request for 20.2002 Disposal of Contaminated Water ML16231A2192016-07-28028 July 2016 Follow-up Questions Related to Entergy Request for 20.2002 Disposal of Contaminated Water ML16069A0952016-03-0303 March 2016 Request for 20.2002 Disposal, Request for Additional Information ML16053A5152016-02-17017 February 2016 Comment (037) of Emma Stamas on ANPR-26, 50, 52, 73, and 140 - Regulatory Improvements for Decommissioning Power Reactors ML15329A1802015-11-24024 November 2015 E-mail from J. Whited Draft RAIs Re Duke License Amendment Request to Adopt TSTF-523 (CAC Nos. MF6413 Through MF6422) ML15295A2132015-10-21021 October 2015 NRR E-mail Capture - VY RAI for Off-site Insurance Exemption (10 CFR 140.11) - MF3980 ML15289A6002015-09-24024 September 2015 La 3 - Vermont Yankee Draft Responses or Edits 9 24 15.docx ML15289A6012015-09-23023 September 2015 La 3 - Nrr_Vermont Yankee Nuclear Power Station Decommissioning Status.Docx ML15288A3532015-09-21021 September 2015 La 3 - VY Dtf LAR - Status ML15257A6172015-09-14014 September 2015 La 3 - Testing the New Profile for Vermont Yankee La 3 - Public ML15195A3592015-07-14014 July 2015 NRR E-mail Capture - Acceptance Review for Vermont Yankee Amendment -Revise Cyber Security Plan Implementation ML15289A0022015-06-17017 June 2015 La 3 - Question from Ma ML15289A5982015-06-0909 June 2015 La 3 - FW: Docket No. 50-271 (Vermont Yankee); June 5 2015 Letter from Vermont, Vynpc, and Gmp to NRC Attached ML15289A0072015-06-0505 June 2015 La 3 - Information Regarding Vermont Yankee Decommissioning Trust Fund Exemption ML15289A2432015-06-0404 June 2015 La 3 - FW: Docket No. 50-271 (Vermont Yankee); June 4 2015 Vermont Letter to NRC Attached ML15289A0062015-06-0404 June 2015 La 3 - FW: Information Regarding Vermont Yankee Decommissioning Trust Fund Exemption ML15288A3592015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A3602015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A3622015-06-0101 June 2015 La 3 - Vermont Yankee LA3 - Availability for Oral Argument ML15288A4822015-05-22022 May 2015 La 3 - Vermont Reply to NRC & Entergy Answers Re VY LA-3 ML15289A0042015-05-19019 May 2015 La 3 - New Proposal Dates for Phone Call with VT ML15289A0052015-05-11011 May 2015 La 3 - ML Numbers for Disbursement Letters for Vermont Yankee ML15289A5992015-05-0808 May 2015 La 3 - Call with State of VT ML15289A0032015-05-0707 May 2015 La 3 - Other than for Comanche Peak, ML15289A1252015-05-0606 May 2015 La 3 - FRN Review - VY Dtf Exemption ML15128A0232015-04-27027 April 2015 NRR E-mail Capture - Petitioners Response to Request for Comments on the Proposed Director'S Decision on the 2.206 Petition Regarding Financial Qualifications of Entergy 2021-03-15
[Table view] |
Text
NRR-PMDAPEm Resource From: Kim, James Sent: Tuesday, July 29, 2014 9:01 AM To: Couture III, Philip Cc: Chappell, Coley; Meyer, Jeffrey T
Subject:
RAI - Defueld Technical Specification Amendment (TAC No. MF3714)
Mr. Couture, The Nuclear Regulatory Commission staff is reviewing the submittal and has determined that additional information is needed to complete its review. The specific request for additional information (RAI) questions are shown below. Based on our discussions we understand that a response to the RAI will be provided by August 29, 2014.
Jim Kim NRR/DORL Vermont Yankee PM 301-415-4125 REQUEST FOR ADDITIONAL INFORMATION BY CONTAINMENT AND VENTILATION BRANCH VERMONT YANKEE NUCLEAR POWER STATION, TECHNICAL SPECIFICATION CHANGES AND REVISED LICENSE CONDITION FOR PERMANENTLY DEFUELED CONDITION DOCKET NO. 50-271 In a letter dated March 28, 2014 (Reference 1), pursuant to Section 50.90 of Title 10 of the Code of Federal Regulations (CFR), Entergy Nuclear Operations, Inc. (ENO) submitted a license amendment request to Renewed Facility Operating License (OL) DPR-28 for Vermont Yankee Nuclear Power Station (VY). The submitted amendment revises the OL and revises the associated Technical Specifications (TS) to Permanently Defueled Technical Specifications (PDTS). ENO is requested to provide response to the following RAIs for NRC staff to complete its review:
SCVB-RAI-1 The staff understands that in the defueled state, the fuel pool cooling will be performed by the non-safety related fuel pool cooling system and also should to be backed up by a safety-related system in case the non-safety pool cooling is lost due to an event, such as a seismic event, or loss of offsite power. In case there is no safety-related pool cooling back up system and given the secondary containment and the standby gas treatment system have been removed from TS, please respond to the following questions:
(a) Would the fuel pool be allowed to boil with offsite steam release?
(b) What system will provide the makeup water to the spent fuel pool to maintain its level?
(c) What will be the offsite dose from the steam release, and verify that it is within the 10 CFR 100 allowed limit.
SCVB-RAI-2 1
Please confirm that spent fuel keff will not increase while the entire fuel is in the spent fuel pool. In case it increases, please discuss the effects of its increase on the decay heat generated in the pool, the pool temperature, and the offsite dose.
REFERENCES
- 1. Letter from Entergy Nuclear Operations, Inc. to NRC dated March 28, 2014, Technical Specifications Proposed Change No. 309 Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition Vermont Yankee Nuclear Power Station Docket No. 50-271, (ADAMS Accession Number ML14091A291) 2
Hearing Identifier: NRR_PMDA Email Number: 1458 Mail Envelope Properties (James.Kim@nrc.gov20140729090100)
Subject:
RAI - Defueld Technical Specification Amendment (TAC No. MF3714)
Sent Date: 7/29/2014 9:01:19 AM Received Date: 7/29/2014 9:01:00 AM From: Kim, James Created By: James.Kim@nrc.gov Recipients:
"Chappell, Coley" <cchappe@entergy.com>
Tracking Status: None "Meyer, Jeffrey T" <jmeyer5@entergy.com>
Tracking Status: None "Couture III, Philip" <pcoutur@entergy.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2721 7/29/2014 9:01:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: