IR 05000445-13-502 and 05000446-13-502,December 31, 2013, Comanche Peak, Units 1 and 2, NRC Emergency Preparedness Annual Inspection
ML14198A631
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 07/17/2014
From: Haire M S
Plant Support Branch-1
To: Flores R
Luminant Generation Co
References
IR-13-502
Download: ML14198A631 (2)


See also: IR 05000445/2013502

Text

July 17, 2014

Rafael Flores, Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Luminant Generation Company LLC Comanche Peak Nuclear Power Plant P. O. Box 1002 Glen Rose, TX 76043

SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000445/2013502 AND 05000446/2013502

Dear Mr. Flores:

On December 31, 2013, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Comanche Peak Nuclear Power Plant, Units 1 and 2. This inspection began on January 1, 2013. Issuance of this letter closes NRC Inspection Report 05000445/2013502 and 05000446/2013502. The inspection results associated with the 2013-502 reports are documented in integrated Resident Inspector Reports 2013-002, 2013-003, 2013-004, and 2013-005.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/ Mark S. Haire, Chief Plant Support Branch 1 Division of Reactor Safety

Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89 Electronic Distribution to Comanche Peak Nuclear Power Plant July 17, 2014 Rafael Flores, Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Luminant Generation Company LLC Comanche Peak Nuclear Power Plant P. O. Box 1002 Glen Rose, TX 76043

SUBJECT: COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2 - NRC EMERGENCY PREPAREDNESS ANNUAL INSPECTION REPORT 05000445/2013502 AND 05000446/2013502

Dear Mr. Flores:

On December 31, 2013, the Nuclear Regulatory Commission (NRC) staff completed its annual inspection of the Emergency Preparedness Program at the Comanche Peak Nuclear Power Plant, Units 1 and 2. This inspection began on January 1, 2013. Issuance of this letter closes NRC Inspection Report 05000445/2013502 and 05000446/2013502. The inspection results associated with the 2013-502 reports are documented in integrated Resident Inspector Reports 2013-002, 2013-003, 2013-004, and 2013-005.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,/RA/ Mark S. Haire, Chief Plant Support Branch 1 Division of Reactor Safety

Dockets: 50-445; 50-446 Licenses: NPF-87; NPF-89 Electronic Distribution to Comanche Peak Nuclear Power Plant Distribution: M. Haire P. Elkmann L. Williams DOCUMENT NAME: R:\_REACTORS\_CP\CP2013502-LTR-pje.docx ML14198A631 SUNSI Review By: MHaire ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive Keyword: RGN-002 OFFICE C:PSB1 NAME MHaire/dch SIGNATURE /RA/ DATE 7/17/14 OFFICIAL RECORD COPY