ML14191A954

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/88-14 on 880613-17.No Violations or Deviations Noted.Major Areas Inspected:Hydrostatic Testing, Review of Program & Review of Complete Test Procedures & Evaluations
ML14191A954
Person / Time
Site: Robinson 
Issue date: 07/01/1988
From: Blake J, Coley J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14191A953 List:
References
50-261-88-14, NUDOCS 8807260037
Download: ML14191A954 (4)


See also: IR 05000261/1988014

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA ST., N.W.

ATLANTA, GEORGIA 30323

Report No.:

50-261/88-14

Licensee: Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.:

DPR-23

Facility Name: H. B. Robinson

Inspection C

ed:

June 13-17, 1988

Inspector:

7/

ley

Date Signed

Approved y:

Blake, Chief

Date Signed

Ma erials and Processes Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine, unannounced inspection was conducted in the areas of

hydrostatic testing - review of program and review of completed test

procedures and evaluations.

Results: In the areas inspected, violations or deviations were not identified.

8807260037 880707

PDR

ADOCK 05000261

Q

-PNU

7- --

7..7...

-'r

REPORT DETAILS

1. Persons Contacted

Licensee Employees

  • G. Beatty, Jr., Vice President, Robinson Nuclear Project Department (RNPD)
  • S. Clark, Project Engineer, Design Engineering
  • J. Curley, Director, Regulatory Compliance
  • W. Flanagan, Manager, Technical Support
  • A. McCauley, Principle Engineer, Onsite Nuclear Safety
  • R. Morgan, General Manager, RNPD
  • D. Weber, Specialist, Technical Support

Other licensee employees contacted during this inspection included

engineers,

security force members,

technicians,

and administrative

personnel.

NRC Resident Inspector

  • L. Garner, Senior Resident Inspector
  • Attended exit interview

2. Review of Licensee's Activities Pertaining.to Hydrostatic Testing -

Unit 2

(73051, 73052, 73755)

The inservice hydrostatic testing programs for the first and second

inspection intervals at Carolina Power and Light (CP&L) Company's Robinson

facility, were written to the requirements of Section XI of the ASME Code,

77S78 Edition and Addenda.Section XI requires that piping and components

of boiling and pressurized water reactor plants be examined and tested for

40 year service lifetime of the plant.

These examinations and tests are

to be completed during each of four ten-year intervals.

These ten-year

intervals are calculated from the start date of commercial operation of

the facility. CP&L is presently starting the third and final period of

their second interval.

Since all hydrostatic testing at the Robinson

facility is conducted in the third period of the interval no second

interval hydrostatic testing has been initiated. Therefore, the inspector

was required to review the testing performed in the first inspection

interval in order to obtain clear perspective of testing which has been

performed. The extent of the inspector's review is delineated below.

a. Review of Program

The first interval inservice inspection (ISI) program which had been

written to conform with the 74S75 Edition and Addenda of the ASME

Code, was submitted to NRC on August 5, 1977. During meetings with

the licensee on August 22 and 23, 1978,

NRC requested and obtained

2

additional information to complete the review of that program.

On

October 25,

1978,

the licensee submitted- a.revised ISI program in

response to questions raised on its earlier program.

CP&L however,

had not allowed adequate time for NRC to review the revised program

before the interval ended and therefore NRC never granted interim

approval for this program.

In addition, in a letter dated

January 27,

1982,

CP&L requested permission from NRC to upgrade the

hydrostatic test portion of -their program to the 77S78 Edition -and

Addenda of the ASME Code. NRC granted this approval by letter dated

February 22, 1982. CP&L contracted Gilbert and Associates to develop

the hydrostatic program to the 77S78 Code.

This included walking

down the systems, writing test procedures,

performing tests and

furnishing CP&L a completed report of all testing.

The inspector

reviewed the contractor's completed report and discovered that the

contractor had identified 18 waivers concerning components which were

not tested in accordance with the program and possibly the ASME Code.

There was no documented evidence that the licensee had conducted a

review of the contractor waivers (which the contractors had

considered Code deviations) to determine if relief was in fact

required in accordance with 10 CFR 50.55a(a)(3),

50.55a(g)(5),

50.55a(g)6 and Robinson Technical Specifications. The inspector met

with licensee cognizant personnel to determine whether any of the

constructor waivers would effect operation and require shutdown or

justification for continued operation.

.

Prior to the meeting,

the licensee was unable to analyze all 18

waivers, so only waivers that appeared to have the greatest effect on

operation and for which no alternate testing was performed were

discussed in this meeting.

The meeting concluded that although,

CP&L's hydrostatic testing program was violated,

no conditions

associated with any of the waivers reviewed would have required the

licensee to shutdown or justify continued operation.

The licensee

will continue their evaluation of the waivers during the week of

June 20-24, 1988.

The inspector will return on June 27, 1988 to

review the licensee's analyses of these exceptions and corrective

actions taken.

This item was identified to the licensee as

  • Unresolved Item 50-261/88-14-01, Licensee Review of Contractor Code

Waivers.

b. Review of Hydrostatic Test Procedures and Evaluation of Test Data

The inspector reviewed the following completed test procedures:

System

Test No.

Test Blocks

Component Cooling Water

CCW -

3/2

1 & 2

Service Water

SW - 3

1, 2, 3 & 4

Service Water

SW -

2/3

1 & 2

  • Unresolved items are matters about which more information is required to

determine whether they are acceptable or may involve violations or deviations.

The inspector concluded from the review of the eight tests involved

that the contractor had written. excellent procedures. AllIvalves in

the test were identified, aligned properly, and documented clearly.

Changes to the procedures were well documented and approved.

The

technical content was adequate and presented in an organized manner.

Test boundaries were properly identified and exceptions

and

discrepancies were clearly addressed.

All contractor activities

appeared to-have been conservatively executed-in-an effective technical

manner.

However, the inspector did not have time to integrate the

138 test procedures involved in the program on complete system

drawings to determine if all of the systems in the hydrostatic test

program had been completely tested. The inspector will pursue this

matter as well as the unresolved item addressed in 2.a. above in NRC

Inspection Report No. 261/88-17.

In addition,

to the above reviews the inspector reviewed the

certification records of the personnel involved.

The training and

certification of the following individuals were reviewed:

Level II & I Examiners Per ANSI N45-2.6

T.S.B.

J.W.B.

L.C.C.

D.H.K.

J.G.K.

A.A.L.

K.L.R.

E.L.T.

R.J.W.

Level III Examiners Per ANSI N45-2.6

T.J.A.

J.F.H.

T.G.L.

J.T.S.

J.R.V.

Within the areas examined,

violations or deviations were not

identified.

3. Exit Interview

The inspection scope and results were summarized on June 17,

1988, with

those persons indicated in paragraph 1. The inspector described the areas

inspected and discussed in detail the inspection results listed below.

Proprietary information is not contained in this report.

Dissenting

comments were not received from the licensee.

(Open)

Unresolved Item 50-216/88-14-01,

"Licensee Review of Contractor

Code Waivers."