Discusses Negotiations W/Licensee on NUREG-0737 Items Re Emergency Operating Procedures,Per 830601 & 0712 Memos
ML14188C183
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 09/09/1983
From: Requa G
Office of Nuclear Reactor Regulation
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 NUDOCS 8403060470
Download: ML14188C183 (1)


Text

Distribution Ek11L i

D. Eisenhut September 9, 1983 NRC PDR G. Lainas Local PDR Docket 'No.

50-261 ORB#l File R. Purple S. Varga G. Requa MEMORANDUM FOR:

Darrell G. Eisenhut, DIrector, Division of Licensing, NRR THRU:

Steven A. Varga, Chief, Operating Reactors Branch No. 1, DL Gus C. Lainas, Assistant Director for Operating Reactors, Division of Licensing FROM:

Glode Requa, Project Manager, Operating Reactors Branch No. 1, DL

SUBJECT:

H. B. ROBINSON UNIT 2 - NEGOTIATIONS WITH THE LICENSEE ON NUREG 0737 ITEMS Per direction provided in your July 12 and June 1, 1983 memoranda, I have documented the reasons for accepting the late implementation dates for the following items.

EJerencyOperating Procedures - J. Lyons, Lead PM Guidance provides that "without further negotiation, Procedure Generation Submittal dates through December 31, 1984 are acceptable."

WOG pr mised 10 &L Rev. 1 guidelines in August '83 (April 15 CP&L Letter). Consequently CP&L did not provide a procedure package to Rev. 0 NRC approval guidelines because they could have provided a package to Reve 1 by December 1983. Recently, however, WOG informed CP&L that guidelines would be delayed to December '83 due to complications. HBR-2 will be refueling at this time, -operate for a few months then shut down for a 9 month outage in June for steam generator replacement.,

It does hot seem reasonable for CP&L to produce a procedure generation package to Rev. 0 guidelines for only a few months operation when Rev. I would be, available by the end of the S/G outage. Rev. 1 guidelines would be submitted for approval about March '89.

I have discussed the procedure generation package delay with Brent Clayton in light of the HBR-2 extended outage and he agreed that the proposed date of two months after receipt of ihformation from owners group (about March '84) is acceptable.

Glode Requa, Project Manger Operating Reactors Branch No. 1 S840:306040 PO ~- ----

Division of Licensing PDR ADOCK 05000261 P _PDR ORB#1C