tPA REcu UNITED STATES 0
NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 o,
April 8, 1999 Mr. D. E. Young, Vice President Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550
SUBJECT:
APPROVAL FOR THE THIRD 10-YEAR INTERVAL INSERVICE INSPECTION PROGRAM PLAN REQUEST FOR RELIEF FOR H.B. ROBINSON STEAM ELECTRIC PLANT, UNIT 2 (TAC NO MA3481)
Dear Mr. Young:
By letter dated August 31, 1998, Carolina Power & Light (CP&L) Company submitted its third 10-year interval inservice inspection (ISI) program plan for request for relief for H. B. Robinson Steam Electric Plant, Unit 2. CP&L requested relief from the Code scheduling requirements of Reactor Pressure Vessel (RPV) examination categories B-A, B-D, B-F, and B-N-1, Revision 1.
In an NRC relief request granted on March 1, 1995, the staff incorporated CP&L's commitments to perform the RPV examinations on or before October 27, 2000, that limited the period of time between RPV examinations in the third and fourth 10-year ISI intervals to 10 years. The current request is to permit you to perform the same during the Refueling Outage 20, beginning April 7, 2001, thus resulting in a delay of less than 6 months. You proposed to revise your commitment to perform RPV weld inspections at or near the end of the ISI interval without limiting the period of time between individual RPV weld or component examinations to 10 years.
The NRC staff has reviewed your request and concluded that the proposed alternative, to perform the RPV examination at or near the end of the third ISI interval, provides an acceptable level of quality and safety at the H.B. Robinson Steam Electric Plant, Unit 2. The proposed change to the CP&L commitment for Code relief will ensure that these inspections are completed in accordance with American Society of Mechanical Engineers (ASME) Boiler &
Pressure (B&PV) Code,Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components," before the end of the current third 10-year ISI interval. Therefore, the proposed alternative is authorized pursuant to 1 OCFR 50.55a(a)(3)(i) for the current interval.
9904190111 990408 PDR ADOCK 05000261 P
PDR 0
ANYJnuw
D. E. Young
-2 Further details regarding the staff's evaluation and conclusions are contained in the enclosed Safety Evaluation.
Sincerely, Sheri R. Peterson, Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-261
Enclosure:
Safety Evaluation cc w/encl: See next page
D.
April 8, 1999 Further details regarding the staff's evaluation and conclusions are contained in the enclosed Safety Evaluation.
Sincerely, Original signed by:
Sheri R. Peterson, Chief, Section 2 Project Directorate II Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-261
Enclosure:
Safety Evaluation cc w/encl: See next page DISTRIBUTION:
Docket File PUBLIC Robinson R/F JZwolinski/SBlack HBerkow GBagchi, CEGB EDunnington RSubbaratham K. Cotton RNorsworthy (e-mail SE only RCN)
- See previous concurrence DOCUMENT NAME: G:\\ROBINSON\\MA3481.WPD
- SE dated March 1, 1999 To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE PM:PDll/S26L-....
LA:PDII/S2 1 !5 SC:PDII/S,--I OGC*
CEGB*
NAME RSubbaratnam EDunnington ffy SPeterson0 RBachmann TMcLellan DATE 04/99 04/7/99 04/7/99 04/05/99 03/01/99 OFFICIAL RECORD COPY