ML14181A642

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/94-27 on 941023-1203.Violations Noted.Major Areas Inspected:Operational Safety Verification,Surveillance & Maint Observation,Plant Safety Review Committee Activities & EP Assessment
ML14181A642
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 12/29/1994
From: Christensen H, William Orders
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14181A640 List:
References
50-261-94-27, NUDOCS 9501110459
Download: ML14181A642 (25)


See also: IR 05000261/1994027

Text

VRGo

UNITED STATES

0

NUCLEAR REGULATORY COMMISSION

REGION II

0

101 MARIETTA STREET, N.W., SUITE 2900

ATLANTA, GEORGIA 30323-0199

Report No.:

50-261/94-27

Licensee:

Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

-

License No.: DPR-23

Facility Name: H. B. Robinson Unit 2

Inspection Conducte

Oct ber 23 - December 3, 1994

Lead Inspector: ;

A

-__------------

/2 2J

/

T. Orders, Senior Resident Ingpector

Date S gned

Accompanying Inspectors:

C. R. Ogle, Resident Inspector

J. L. Starefos, Project Engineer

A. W. Salyers, Region II Inspector

Approved by:

_______________

/ Z44f

C

.'Cpristensen, Chief

Dat Si ned

Reactor Projects Section 1A

Division of Reactor Projects

SUMMARY

SCOPE:

This routine, unannounced inspection was conducted in the areas of operational

safety verification, surveillance observation, maintenance observation, plant

safety review committee activities, emergency preparedness assessment, and

followup of previously identified items. The inspection effort included

reviews of activities during non-regular work hours on October 31,

November 1, 2, 7, 8, 15, 16, and 22.

RESULTS:

In the area of Plant Operations, one violation was identified which deals with

the mispositioning of the control switch for one of the control room

ventilation fans. This configuration control issue was caused by operator

inattention to detail which led to his failing to follow the requisites of a

surveillance procedure and resulted in the system being degraded. The system

remained degraded for four days even though the control room panels were

walked down by operators once per hour during the four day period. Operator

failure to follow procedure and inattention to detail are chronic problems.

9501110459 941229

PDR ADOCK 05000261

0

PDR

2

In the area of Maintenance, one violation, three non-cited violations, and two

unresolved items were identified. The violation deals with inadequacies

associated with the licensee's power range calorimetric program, specifically

with calibration of instrumentation, control of assumptions and assessment of

errors. One of the non-cited violations concerns the licensee's failure to

adequately test redundant series mounted control room ventilation system

dampers. The second non-cited violation concerns inadequacies identified in

the procedure employed by the licensee to calibrate a component cooling water

transmitter. The third non-cited violation deals with the licensee's failure

to have a procedure to facilitate maintenance on safety-related auxiliary

feedwater flow control valves. The first unresolved item concerns the use of

unqualified oil in safety related equipment. The second unresolved item

concerns the resolution of feedwater nozzle performance

In the area of Engineering, one non-cited violation was identified which deals

with the licensee's failure to control the modification of the main control

room panels.

In the area of Plant Support, one unresolved item was identified involving the

modification of the TSC/EOF building and the resultant effect on the

ventilation system.

The licensee conducted an annual emergency preparedness exercise on

November 15, 1994. No exercises weakness, violations or deviations were

identified.

A representative from the Boise Interagency Fire Center visited Robinson on

November 30, 1994, as part of a contract to provide the NRC emergency

communications equipment should the need arise.

The objective of the site

visit was to collect logistics information for preplanning purposes.

REPORT DETAILS

1.

PERSONS CONTACTED

Licensee Employees:

W. Brand, Supervisor, Environmental Radiation Control

M. Brown, Manager, Design Engineering

  • A. Carley, Manager, Site Communications
  • B. Clark, Manager, Maintenance
  • D. Crook, Licensing/Regulatory Programs

C. Gray, Manager, Materials and Contract Services

D. Gudger, Licensing/Regulatory Programs

  • S. Hinnant, Vice President, Robinson Nuclear Project
  • K. Jury, Manager, Licensing/Regulatory Programs

J. Kozyra, Licensing/Regulatory Programs

  • R. Krich, Manager, Regulatory Affairs
  • B. Meyer, Manager, Operations

D. Taylor, Plant Controller

G. Walters, Manager, Support Training

  • R. Warden, Manager, Plant Support Nuclear Assessment Section

W. Whelan, Industrial Health and Safety Representative

  • D. Whitehead, Manager, Plant Support Services

T. Wilkerson, Manager,Environmental Radiation Control

L. Woods, Manager, Technical Support

  • D. Young, Plant General Manager

Other licensee employees contacted included technicians, operators,

engineers, mechanics, security force members, and office personnel.

NRC Personnel

  • W. Orders, Senior Resident Inspector

C. Ogle, Resident Inspector

  • J. Starefos, Project Engineer
  • G. Salyers, Region II Inspector

Acronyms and initialisms used throughout this report are listed in the

last paragraph.

2. PLANT STATUS AND ACTIVITIES

Operating Status

The unit operated for the entire report period with no major operational

perturbations. As of the end of the report period, the unit had been on

line for 112 days.

3.

OPERATIONS

a.

Plant Operations (71707)

The inspectors evaluated licensee activities to determine if the

facility was being operated safely and in conformance with

regulatory requirements. These activities were assessed through

direct observation, facility tours, interviews and discussions

with licensee personnel, evaluation of safety system status, and

review of facility records. The inspectors reviewed shift logs,

operation's records, data sheets, instrument traces, and records

of equipment malfunctions to assess equipment operability and

compliance with TS. The inspectors evaluated the operating staff

to determine if they were knowledgeable of plant conditions,

responded properly to alarms, adhered to procedures and applicable

administrative controls, were cognizant of in-progress

surveillance and maintenance activities, and were aware of

inoperable equipment status. The inspectors performed instrument

channel checks, reviewed component status, and reviewed safety

related parameters to determine conformance with TS. Shift

changes were routinely observed to determine if system status

continuity was maintained and that proper control room staffing

existed. Access to the control room was well managed, and in

general, operations personnel carried out their assigned duties in

an effective manner. Control room demeanor and communications

were appropriate.

Routine plant tours were conducted to evaluate equipment

operability, assess the general condition of plant equipment, and

to verify that radiological controls, fire protection controls,

physical protection controls, and equipment tagging procedures,

were properly implemented.

b.

Onsite Response to Events (93702)

Control Room Ventilation Misalignment

At 8:35 p.m. on November 15, 1994, an operator found the control

switch for control room air conditioning system fan HVA-1B in the

"STOP" position instead of the required "AUTO" position. The

switch was immediately placed in the "AUTO" position which

returned the fan to operable status. In this mis-configuration,

the fan would not have auto started during certain design basis

accident scenarios.

Background

The control room air conditioning system, is comprised of two sub

systems; an environmental control system and air cleanup system.

The system is nuclear safety related and redundancy is provided

for safety-related active components.

3

The environmental control system operates continuously during

normal and emergency conditions. This system consists of two

redundant 100 percent capacity centrifugal fans and gravity

dampers arranged in parallel, and a stainless steel housing

containing a medium efficiency filter and redundant cooling coils.

Redundant safety-related equipment and controls are powered from

separate safety-related power supplies. A nonsafety-related fan

provides exhaust from the control room through the kitchen and

toilet areas to the outdoors during normal operation.

The air cleanup system normally operates only during emergency

conditions. This system consists of redundant centrifugal fans

and gravity dampers arranged in parallel, and a stainless steel

housing containing filter and charcoal absorber banks. The system

contains a single outside air intake with connecting duct work

containing redundant parallel air operated control dampers. The

control room kitchen and toilet exhaust duct work contains

redundant air operated control dampers arranged in series.

The system is designed to provide three operational modes, normal

ventilation, emergency pressurization, and emergency

recirculation.

During normal ventilation, one train of the environmental control

system is in operation in conjunction with the kitchen and toilet

area exhaust fan.

During emergency pressurization, a single train of both the

environmental control system and the air cleaning system are in

operation. The kitchen and toilet air exhaust fan is shutdown and

exhaust dampers closed. A positive pressure is maintained in the

control room envelope with respect to adjacent areas and the

outdoors. A safety injection signal or a signal from the control

room radiation monitor will automatically place the system in the

emergency pressurization operating mode. The emergency

pressurization mode may also be manually initiated.

The emergency recirculation mode of operation is achieved by first

placing the system in the emergency pressurization and then

closing both outside air intake dampers via their control switches

in the control room. This mode of operation is not a design basis

requirement, but is provided to allow isolation of the control

room outside air makeup.

Event Details

On the morning of November 15, 1994, an operator found the control

switch for control room air conditioning system fan HVA-1B in the

STOP position instead of the required AUTO position. The switch

was immediately placed in the AUTO position which returned the

system to operable status. In this erroneous configuration, the

fan would not have automatically started during design basis

  • 0'

4

accident scenarios. The licensee determined that the switch had

been placed in the STOP position on November 11, 1994, when an

operator, who was performing operations surveillance test OST-750,

Control Room Emergency Ventilation System, placed the switch in

STOP when the procedure required that he verify that the fan was

OFF. Since the fan was already off, he should have merely verified

that the fan was not running.

As described above, the system is designed to automatically align

to the emergency pressurization mode upon the receipt of either a

safety injection or control room high radiation signal.

Upon the

receipt of either of these signals, one of the redundant air

cleanup fans start, the redundant control room exhaust dampers

close, and outside air is used to pressurize the control room. To

perform this pressurization function, at least one of the

environmental control fans HVA-1A or HVA-1B must also be in

operation. Although these fans do not get a direct AUTO start

signal, one of the two redundant fans is always running, and the

other is designed to start upon the receipt of a low flow signal

from the opposite fan. With the switch for the HVA-1B fan in the

STOP position, and assuming the single active failure of the A

diesel generator, the system would not have been capable of

pressurizing the control room without manual action by the

operators to start fan HVA-1B.

It should be noted that the inspectors verified that current, in

place, emergency procedures would have prompted the operators to

verify that the system was operating properly and take action, if

necessary, to initiate system function.

Concl usion

The operator performing OST-750 on November 11, 1994, failed to

follow the requisites of the procedure which resulted in making

the B train of the system inoperable.

The inspectors noted that even though the reactor operators

performed a control panel walkdown once per hour during the period

in question and the STA performed a control panel walkdown once

every four hours, the mispositioned switch was not detected for

four days. This event is of concern to the NRC because it is an

example of inattention to detail on the part of the operating

staff. It should also be noted that operators failing to follow

procedures and not being aware of the status of controls and

indications in the control room is a chronic problem.

Technical Specification 3.15.1 requires that during all modes of

plant operation, the control room air conditioning system shall be

operable with two trains of active safety-related components and

shared safety-related passive components.

5

Technical Specification 3.15.1 requires the control room air

conditioning system be operable during all modes of plant

operation, including two trains of active safety-related

components and shared safety-related passive components.

OST-750, Control Room Emergency Ventilation System requires in

step 7.2.1 that HVA-1B be verified to be OFF but does not require

the operator to take the switch to the STOP position.

On November 11, 1994, an operator failed to follow the requisites

of operations surveillance test OST-750, Control Room Emergency

Ventilation System, when he placed the control switch for idle

control room air conditioning system fan

HVA-1B in STOP when the

procedure required that he verify that the fan was OFF. This mis

configuration resulted in the B train of the system being

inoperable for four days, and rendered the system incapable of

performing its intended safety function, assuming an active single

failure in the opposite train.

This is a Violation, VIO 94-27-01:

Operator Procedure Non-Compliance Results In Control Room

Ventilation Inoperability.

c.

Effectiveness of Licensee Control in Identifying, Resolving, and

Preventing Problems (40500)

The inspectors evaluated certain activities of the PNSC to

determine whether the onsite review functions were conducted in

accordance with TS and other regulatory requirements. In

particular, the inspectors attended the PNSC meeting held on

November 18, 1994, which dealt with a NAD audit of operations. It

was determined that provisions of the TS dealing with membership,

review process, frequency, and qualifications were satisfied. The

inspectors also reviewed selected previously identified PNSC

activities to independently determine if that corrective actions

were progressing satisfactorily.

Based on the information obtained during the inspection, except as noted

above, the operations program was adequately implemented.

4.

MAINTENANCE

a.

Maintenance Observation (62703)

The inspectors observed safety-related maintenance activities on

systems and components to ascertain that these activities were

conducted in accordance with TS, approved procedures, and

appropriate industry codes and standards. The inspectors

determined that these activities did not violate LCOs and that

required redundant components were operable. The inspectors

verified that required administrative, material, testing,

6

radiological, and fire prevention controls were adhered to. In

particular, the inspectors observed/reviewed the following

maintenance activities detailed below:

WR/JO 94-BWP471

Calibrate The Component Cooling Loop

Flow Instrumentation (FT-613 only)

WR/JO 94-CBY003

End Of Core Life (EOL) Calibration

Of Rod Insertion Limits

WR/JO 94-AQQJ1

Assist Tech Support In Testing

Control Room Ventilation System

CCW Flow Transmitter Calibration

The inspectors witnessed calibration of FT-613 Component Cooling

Water Flow transmitter accomplished in accordance with Process

Instrument Calibration Procedure, PIC-002, D/P Electronic

Transmitter (4-20 mA Output). While the overall conduct of the

calibration was adequate, the inspectors noted several procedural

deficiencies.

The generic transmitter isolation and restoration sequence

specified in Attachment 8.3 of PIC-002 was inadequate. The valves

shown on the valve manifold sketch in this attachment are labelled

"A", "B", and "C."

No designation is provided as to which letter

represents the high and low pressure isolation valves. The

generic isolation and restoration sequence is provided in terms of

the "A", "B", and "C" designations only. The inspectors observed

that the physical arrangement of these valves does vary in the

plant between transmitters. This lack of specificity coupled with

the in-plant variations in manifold configuration could result in

a transmitter isolation or restoration in the reverse of the order

specified.

The inspectors also noted that PIC-002 fails to provide

instructions on repositioning the equalizing valve in the interval

between instrument isolation and calibration as well as between

calibration and restoration. Following instrument isolation, the

equalizing valve is open. No procedural guidance exists in PIC

002 to shut this valve when the calibration is performed. (The

equalizing valve must be shut in order to apply a differential

pressure to the transmitter.)

Likewise, following calibration

nothing in PIC-002 prompts the technician to open the equalizing

valve prior to performing the manifold block restoration sequence.

The inspectors also noted that the transmitter tolerance specified

on the calibration data sheet was incorrect.

Instead of a 20

millivolt tolerance, the calibration data sheet specified a 200

millivolt tolerance.

The inspectors noted that none of these errors was especially

significant and the technician was able to accomplish the

calibration in spite of the procedural deficiencies.

7

Nevertheless, the inspectors concluded that the procedure was not

correct as written. The licensee committed to correcting the

procedure to address the items identified above.

Technical Specification 6.5.1.1, Procedures, Tests, and

Experiments, requires in part, that written procedures be

established, implemented and maintained for the activities

specified in Appendix A of Regulatory Guide 1.33, Rev. 2, February

1972, including maintenance.

Process Instrument Calibration Procedure, PIC-002, D/D Electronic

Transmitter (4-20 mA Output) is provided for calibration of

differential pressure transmitters including FT-613, Component

Cooling Loop Flow.

On November 21, 1994, PIC-002 was inadequate in that not only did

it not contain all necessary steps to perform the calibration, but

if followed as written, it would have resulted in valving out the

transmitter in reverse sequence.

This NRC identified violation is not being cited because criteria

specified in Section VII.B of the NRC Enforcement Policy were

satisfied.

This item is identified as a non-cited violation NCV

94-27-02: Inadequate FT-613 Calibration Procedure.

The inspectors noted that FT-613 was also isolated at the

instrument root stops in accordance with a local clearance and

test request. The inspectors were advised that instruments are

not always isolated at the root stops for calibration. However,

when they are, the inspectors were informed that Operations

personnel do not manipulate the manifold block equalizing valve

when hanging or removing the clearance. (The operator who removed

the FT-613 root valve clearance told the inspectors that he did

not manipulate the equalizing valve when removing the clearance on

the FT-613 root isolation valves.)

The inspectors concluded that

as a minimum this strategy can defeat the licensee's isolation and

restoration sequence at the manifold valves. At worst, the

manipulation of the root stops by Operations has the potential to

subject one side of the transmitter to system pressure without

corresponding system counter pressure on the other side of the

transmitter diagram.

The inspectors also questioned the licensee's method for

transmitter restoration and isolation. The inspectors were

advised that the I & C technicians are trained that when isolating

a differential pressure transmitter, the licensee's sequence is to

shut the high side valve, open the equalizing valve, and shut the

low pressure side valve. Conversely on restoration, the sequence

is to open the low pressure side valve, close the equalizing

valve, and open the high side valve. The inspectors were advised

that this method is specified consistently in the licensee's

procedures.

8

Following inspector questions on this technique, the licensee

received the manufacturer's recommended practice for valving

differential pressure transmitters in and out of service. The

manufacturer recommends that when isolating a transmitter the

desired sequence is to open the equalizing valve and then shut the

low and high side valves. When restoring the transmitters to

service, the manufacturer's recommended sequence is open the

equalizing valve, open the high side and low side valves, and shut

the equalizing valve. The manufacturer's letter on this subject

stated that this technique "...insures that neither the

transmitter high or low side will be subjected to an overpressure

condition during the valve in and valve out process."

Further,

the letter stated that failure to properly equalize the

transmitter "...can result in an overpressure condition which will

cause a shift in transmitter zero." The manufacturer stated that

this overpressure condition would not damage the transmitter. The

inspectors were advised that the licensee's valve operating

sequence was in part, developed to minimize potential consequences

which could occur as a result of equalizing the two sides of the

transmitters. The inspectors acknowledge that in some situations,

use of the manufacturers' technique may have undesirable side

effects. However, these potential shortcomings do not apply to

the FT-613 configuration. Further, the licensee was unable to

furnish any historical analysis of the consequences of potential

zero shifts on transmitters resulting from the licensee's

procedure. The licensee is evaluating the potential for

transmitter zero shifts using their technique. The inspectors

will monitor this effort.

Use Of Unqualified Oil In WCCU

During the morning of November 30, 1994, the inspectors observed

that the Texaco Capella Premium 68 oil being used in the ongoing

maintenance on WCCU-1A was not designated as to its.procurement

quality. The inspectors questioned this and following a

subsequent licensee review were advised that the oil was non-Q.

At 2:00 p.m., that day, the licensee declared WCCU-1B out-of

service due to the fact that the oil installed in the unit was

also non-Q. Since WCCU-1A was inoperable for ongoing maintenance,

the licensees entered TS 3.15.1b. This TS required that at least

one WCCU be restored to an operable status within 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> or the

unit be placed in hot shutdown within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br />. At 9:07 p.m., that

evening, the licensee exited TS 3.15.1b when the WCCU-IB was

declared back in service. This declaration occurred following the

licensee's dedication of the Texaco Capella Oil Premium 68

installed in the WCCUs. This was based on analysis of samples of

the Texaco Capella Oil Premium 68.

Pending a review of the licensee's procurement practices for oil

for the WCCUs this item is identified as an unresolved item, URI

94-27-03: WCCU Oil Procurement Practices

9

Failure to Provide Procedure For Maintenance On Auxiliary

Feedwater Valves

On November 9, 1994, during a routine inspection of the motor

driven auxiliary feedwater pumps, the inspectors noted that the

jam nuts designed to assist in securing the valve stem to actuator

coupling on flow control FCV-1424 and FCV-1425 appeared to be

improperly adjusted. Valve FCV-1424 had four jam nuts, all of

which were located at the actuator end of the threaded coupling.

Valve FCV-1425 had only three jam nuts, one of which was located

at the valve end of the coupling and the other two were located at

the actuator end. The licensee later determined that the nuts

were loose.

The inspectors notified the system engineer of the observation,

and reviewed the technical manual for the ITT Barton (Hydramotor)

actuators. The manual clearly identified the correct location of

the jam nuts as being two at either end of the coupling and

specified a torque value of 100 inch pounds to be applied to the

nuts. This meant that both FCV-1424 and FCV-1425 were set up

incorrectly.

The system engineer contacted the vendor for the valve actuators

to determine the significance of the as-found configuration.

According to the engineer, the vendor stated that in the case of

valves FCV-1424 and FCV-1425 which employs an ITT Barton NH-91

actuator with a Grinnel gate valve, the jam nuts were not

necessary since no torque is applied to the coupling which could

cause valve stroke misadjustment if the coupling become loosened.

During their inspection to determine why the actuator couplings

were found improperly adjusted, the inspectors determined that

these same jam nuts had been found loose on FCV-1424 in January

1991, and on FCV-1425 in June 1992. The inspectors also determined

that although the valves are safety-related equipment, no

procedure existed for maintenance on their actuators despite the

fact that a request for a procedure was generated in September of

1993. The need for a procedure had also been identified in

September of 1994, when an operability determination (94-035) was

performed after it was determined that the flow controllers

associated with the valves had been calibrated without a

procedure.

The licensee has committed to write a procedure to provide

specific instruction for the installation and required maintenance

of the actuator/valve assemblies.

Failure to have a procedure for maintenance on safety-related

equipment is a violation of TS 6.5.1.1.

However, since this event

meets the criteria specified in Section VII.B of the NRC

Enforcement Policy, the violation will not be cited. This item

10

will be tracked as non-cited violation NCV 94-27-04, Failure To

Provide Procedure For Safety-Related Maintenance.

b.

Surveillance Observation (61726)

The inspectors observed certain safety-related surveillance

activities on systems and components to ascertain that these

activities were conducted in accordance with license requirements.

For the surveillance test procedures listed below, the inspectors

determined that precautions and LCOs were adhered to, the required

administrative approvals and tagouts were obtained prior to test

initiation, testing was accomplished by qualified personnel in

accordance with an approved test procedure, test instrumentation

was properly calibrated, the tests were completed at the required

frequency, and that the tests conformed to TS requirements. Upon

test completion, the inspectors verified the recorded test data

was complete, accurate, and met TS requirements, test

discrepancies were properly documented and rectified, and that the

systems were properly returned to service. Specifically, the

inspectors witnessed/reviewed portions of the following test

activities:

OST-010

Power Range Calorimetric During Power

Operation

Control Room Exhaust Dampers

Unresolved Item, URI 94-23-05, documents the resident inspectors'

concerns associated with testing of the control room exhaust

dampers, CR-D1A and CR-D1B. These in-series redundant dampers

automatically close as part of the control room emergency

pressurization sequence. Though both dampers were tested together

during existing surveillance tests, the licensee performed no

routine test of the capability of a single damper to close and

facilitate control room pressurization.

On November 9, 1994, the licensee conducted testing which

demonstrated the capability of the exhaust dampers to individually

seal, thereby permitting adequate control room pressurization.

This testing was performed using a revised version of EST-023,

Control Room Emergency Ventilation System. The inspectors

witnessed portions of the test and reviewed the completed EST and

observed that the control room was pressurized adequately using

either damper individually.

The failure of the licensee to test the capability of the

individual control room exhaust dampers to individually permit

control room pressurization is a violation of 10 CFR 50,

Appendix B, Criterion XI, Test Control, which requires in part

that a test program be established to assure that all testing

required to demonstrate that systems will perform satisfactorily

in service is identified and performed in accordance with written

test procedures which incorporate the acceptance limits contained

in the applicable design documents.

The licensee's Updated Final Safety Analysis Report (UFSAR)

sections 6.4 and 9.4.2 require, in part, that the control room

ventilation system be capable of maintaining the control room at a

positive differential pressure with respect to adjacent areas and

the outdoors when the system is operated in the emergency

pressurization mode of operation.

Further, this reference

specifies that the system will remain operable given the failure

of a single active component. Each exhaust damper is an active

component.

From February 1, 1991, until November 9, 1994, the licensee did

not implement adequate testing to verify that the control room

ventilation system was capable of performing its design function.

Specifically, testing did not demonstrate that a positive pressure

could be maintained in the control room assuming that a single

exhaust damper failed to shut. This NRC identified violation is

not being cited because criteria specified in Section VII.B of the

NRC Enforcement Policy were satisfied. This item will be tracked

as a non-cited violation NCV 94-27-05, Inadequate Testing Of

Control Room Ventilation Dampers.

Assessment Of Calorimetric Program (61726, 61706)

The inspectors reviewed the licensee's power range calorimetric

program. This inspection effort consisted of witnessing

performances of OST-010, Power Range Calorimetric During Power

Operation; verification of portions of the logic and assumptions

used in the ERFIS calorimetric calculation; and a review of

calibration of instruments used in the calorimetric.

Additionally, the inspectors attempted to conduct a rudimentary

cross-check of reactor power using diverse indications as a check

on the validity of the calorimetric calculation.

Operations

While witnessing the performance of OST-010, the inspectors

observed that the auxiliary operators collect differential

pressure data from Barton differential pressure instruments

installed in the turbine building. For feed flow, the

operators record three differential pressure readings one

minute apart, while for blowdown flow, a single differential

pressure reading is taken. Using these readings, a control

room operator calculates the average feed flow Barton

differential pressures. This information is subsequently

entered into the ERFIS calorimetric program to calculate the

flow. The inspectors noted that the three-minute averaging

of feed flow is not specified in the procedure. Further, the

Barton readings are recorded on a scrap piece of paper which

is not retained, hence eliminating any second check or

12

review of the data or the averaging process. The inspectors

also noted that the timing of the reading of the Bartons and

the automatic acquisition of other data points performed by

the calorimetric program was not procedurally specified and

varied among operators. While the calorimetric procedure

specifies that plant power be held constant, the inspectors

noted that slight variations in-plant parameters used in the

calorimetric do occur. The inspectors concluded that given

these variations, the lack of procedural guidance to specify

the timing of these two separate steps in the data

acquisition process could introduce errors.

The inspectors also observed that the computer generated

data sheet for OST-010 states that F,, the feed flow nozzle

thermal area factor, is obtained from Attachment 8.3. No

such attachment exists for OST-010. This error does not

impact the performance of the calorimetric.

Instrument Calibration

The inspectors reviewed the licensee's calibration of

instruments which provide inputs to the calorimetric. The

following deficiencies were noted:

The inspectors observed that the feedwater temperature RTDs,

used in the calculation of feedwater enthalpy are not

included in the licensee's calibration program. A portion

of the feedwater temperature signal path in ERFIS is

calibrated, however, this calibration would not detect

degradation in the sensors or the remaining portion of the

circuits.

The inspectors also determined that no routine verification

of feedwater flow nozzle performance is performed. The

inspectors were advised by the licensee that a visual

inspection of the three nozzles is conducted on a refueling

interval basis. Further, the licensee advised the

inspectors that these inspections have not detected problems

with the nozzles. The inspectors reviewed the nozzle

inspection work packages from the last outage and noted that

the inspection results consisted of a single sentence which

described the nozzles as being in a satisfactory condition.

The licensee was unable to provide any quantitative data to

demonstrate that feedwater flow nozzle characteristics have

not changed over the last 24 years of service. The

inspectors concluded that the lack of a quantitative

assessment of feedwater nozzle performance could prevent

detection of gradual feedwater flow nozzle degradation.

Given the dramatic direct impact that even small changes in

feedwater flow have on the calorimetric results, this

shortcoming represents a key vulnerability in the licensee's

13

calorimetric program. This potential shortcoming was

identified to the licensee. Pending the licensee's

resolution of feedwater flow nozzle performance, this item

will be tracked as an unresolved item, URI 94-27-06:

Resolution of Feedwater Nozzle Performance and Impact On

Calorimetric.

The inspectors reviewed completed calibration data sheets

for the instruments used in the calorimetric.

From this

review, the inspectors determined that the licensee has not

applied consistent controls to these instruments if an out

of tolerance condition is identified. Specifically, the

calibration data sheet for the feedwater flow Bartons

requires that an operating supervisor be notified if the

instrument is found out of calibration. However, no similar

requirement exists for the steam generator blowdown Bartons.

In fact, on January 7, 1994, DPI-1328B, Steam Generator B

Blowdown Differential Pressure, was found out of tolerance

during a licensee calibration.

An assessment of this out

of tolerance condition on the bottom of the calibration data

sheet stated: "Indicating needle had moved; possibly due to

a pressure shock, non-Q application non-reportable." No

documentation existed which shows that the effect of this

out of tolerance condition had on the calorimetric was

considered at the time .

During the course of the

inspection, the inspectors were advised that data sheets for

the blowdown Barton calibration are being revised to require

review if out of tolerance conditions are detected.

Additionally, the inspectors were advised that the licensee

has implemented a post-calibration review for data sheets

for trending purposes. A subsequent licensee assessment

determined that this instrument miscalibration introduced an

error of less than 1.5 megawatts thermal.

The inspectors also noted from their review of the

calibration data sheets that the licensee is calibrating the

feedwater flow and steam generator blowdown Bartons to a

tolerance four times less restrictive than that specified by

the manufacturer. (Manufacturer +1/2%; licensee + 2%.) A

review of the completed calibration sheets revealed that all

three steam generator blowdown Bartons have exceeded the

more restrictive manufacturer's tolerance on at least one

calibration point during the most recent calibration.

(All

three Bartons met the licensee's less restrictive

calibration tolerance.)

Furthermore, DPI 1328B, Steam

Generator B Blowdown Differential Pressure, has been

readjusted during each of the last four calibrations (June

1991 to June 1994).

It was not apparent to the inspectors

that the impact on the calorimetric of this relaxed

instrument tolerance or the repetitive adjustment had been

evaluated by the licensee.

14

On October 20, 1994, the inspectors observed that the ERFIS

indication for steam generator pressure for loop 3 channel 2

differed by approximately 40 psig from the corresponding

RTGB indication.

Steam generator pressure as recorded in

ERFIS is used in the calorimetric. Similar, but smaller

deviations between the RTGB indication and ERFIS existed on

all other steam generator pressure channels. Subsequent

licensee reviews on October 26 and October 27, 1994,

indicated a deviation of between 47 psig and 48 psig for the

loop 3 channel 2 steam generator pressure indicators. The

licensee subsequently determined that the deviation was a

result of signal isolator PM-494D (ERFIS input) being out of

tolerance low and PI-494 (RTGB indicator) being out of

tolerance high. This condition was corrected by the

licensee on October 31, 1994. Simultaneous licensee

calorimetrics performed with RTGB steam generator pressures

versus ERFIS values performed on October 26, 1994, revealed

that this disparity in pressure readings for all steam

generators translated into a little less than a 2 megawatt

difference in core thermal power.

The calorimetric is equipped with routines which verify that

the input data falls within acceptable ranges. Typically,

the acceptable range is the instrument span. Additionally,

the calorimetric will flag unacceptable deviations between

the redundant steam generator pressure channels input to

ERFIS or unacceptable deviations from the average feedwater

temperature by any feedwater temperature instrument.

However, no mechanism exists by which to detect deviations

such as that which developed in the loop 3 channel 2 steam

generation pressure instrument between different indicators.

The inspectors also determined that the licensee's

calibration program does not verify the signal from the

instrument loops to the ERFIS computer. Hence, portions of

the feedwater temperature and steam generator pressure

circuitry which feed the calorimetric program are not

verified in any licensee calibration program. The failure

to conduct a verification of the entire ERFIS signal path

for the steam generator pressure instruments was previously

identified during a Regulatory Guide (RG) 1.97 inspection

documented in NRC Inspection Report 90-08. The licensee did

conduct testing to verify the entire signal path during SP

1150,

Process Analog Indications Comparison To ERFIS Point

Indication For RG 1.97 Commitments on July 22, 1992.

However, this was not incorporated into a routine

verification of the entire ERFIS path. The inspectors were

advised that the licensee has implemented steps to verify

the ERFIS outputs during instrument loop calibrations until

complete verification of the ERFIS loop can be procedurally

implemented.

15

Calorimetric Program

The inspectors reviewed the calorimetric program. The

following items were observed.

The inspectors were advised by ERFIS personnel that input

data for the 12 ERFIS points used in the calorimetric

program are obtained from an instantaneous update when the

program is activated. This strategy makes the calorimetric

susceptible to errors as a result of normal variations in

plant parameters. No adjustment, compensation, or

administrative controls exist to correct for any error

introduced as the result of this methodology.

Thermal power is calculated in the calorimetric program

assuming a letdown flow of approximately 45 gpm. Though

this is'the normal letdown flow, the licensee does

occasionally conduct power operations with approximately 100

gpm of letdown flow. There is no adjustment made to the

calorimetric for this increased letdown. In fact, the

assumed letdown flow is not discussed in the calorimetric

procedure. Using licensee calculations of heat loss

associated with letdown flow, the inspectors determined that

this increased letdown could introduce almost a 3 megawatt

thermal error into the calorimetric.

The calorimetric program uses a value of component heat loss

obtained from testing performed in 1970. Discussions with

plant personnel indicates that portions of the original

asbestos containing lagging on some components in the CV

were replaced in the mid 1980's.

The impact in terms of

calorimetric performance of this lagging replacement was not

readily apparent from the information reviewed by the

inspectors. However, the inspectors reviewed a 1987

insulation contractor's trip report which stated that

following the insulation changeouts ".. the average

containment air temperature reportedly increased from about

1050 F to about 1200 F."

The inspectors did not

independently verify this statement. The inspectors

acknowledge that the component heat loss at 1.2 megawatts is

a small part of the thermal power. Nevertheless, the

inspectors concluded that relying on a heat loss calculation

performed 24 years ago, in the face of even partial

insulation changeout, may introduce errors into the

calorimetric.

It was not apparent from the inspector's review of the

calorimetric program that the overall accuracy of the

calorimetric has been identified by the licensee.

Instrument accuracies, errors introduced as a result of

(curve fits) used in the calorimetric and gradual

degradation of the component performance will affect the

16

accuracy of the alorimetric. This error has not been

translated into a strategy which monitors the accuracy of

the calorimetric and makes necessary changes or compensation

to plant operations so as not to violate licensed thermal

power limits.

Conclusion:

The inspectors acknowledge that the potential errors

introduced into the calorimetric as a result of the items

above, except for potential feed flow nozzle inaccuracies,

are probably small.

Additionally, conservatisms introduced

into the calorimetric as a result of steam quality and

feedwater enthalpy considerations may more than offset these

items. Nevertheless, the inspectors observed that control

of the calorimetric is weak. This weakness was reflected in

deficiencies observed in the calibration of instrumentation,

control of assumptions and initial conditions, and

assessment of errors contained in the calorimetric.

Overall, the inspectors concluded that the calorimetric

program does not contain controls commensurate with its

safety significance.

10 CFR 50, Appendix B, Criterion II, Quality Assurance

Program, requires that the quality assurance program provide

control over activities affecting quality of structures,

systems, and components, to an extent commensurate with

their importance to safety. Further, Criterion II requires

that these activities be accomplished with the use of

appropriate equipment and that all prerequisites have been

identified and satisfied. Further, the program is required

to take into account the need for special controls, test

equipment, and the need for verification of quality by

inspection or test.

On November 28, 1994, the inspectors determined that

inadequate controls were applied to the licensee's

calorimetric program. Deficiencies identified included use

of uncalibrated instrumentation, failure to control the

plant condition prerequisites under which the calorimetric

program results were valid, failure to specify a method or

timing for acquiring manually input data, lack of

verification of automatically input data, and inconsistent

controls on the instruments used in the calorimetric. This

is identified as a violation, VIO 94-27-07: Failure To

Adequately Control Calorimetric.

The inspectors attempted to independently assess the

accuracy of the calorimetric using diverse indicators or the

results of tests other than OST-010. However, the

inspectors observed that most of the readily available

information could be impacted by errors common to the

17

calorimetric. Given this limitation, the inspectors

reviewed historical plant performance data which indicated

that the current electrical output at an indicated power of

100 percent is consistent with that for similar conditions

during the last three cycles.

Based on the information obtained during the inspection, except as

noted above, the maintenance program was adequately implemented.

5.

ENGINEERING

a.

Onsite Engineering (37551)

RTGB Design Control

At approximately 3:00 p.m, on the afternoon of October 31, 1994,

the inspectors were monitoring I & C work associated with the

calibration of instrumentation on the RTGB, when they detected a

piece of 1/2" electrical conduit attached by plastic tie wraps to

two horizontal structural supports inside the panel.

The piece of

conduit had itself been used as a structural member to which

bundles of wiring had been secured. The inspectors discussed

their observations with the shift supervisor who in turn, notified

the engineering department.

At 3:22 p.m. that afternoon, the shift supervisor initiated an

operability determination on the RTGB due to the possible loss of

associated controls and indications during a seismic event. The

Licensee detected four other examples of unanalyzed wiring support

material in the RTGB including a 6 foot length of one inch steel

piping. An assortment of hardware had been used to secure these

supports to the framework of the RTGB including 1/4" cable ties,

3/16" cable ties and metal clamps. The licensee's investigation

failed to determine how or when the unanalyzed supports had been

installed in the RTGB.

The licensee performed Operability Determination 94-01 which

indicated that installation was acceptable, in that, the tie wraps

provide sufficient structural support to resist the loadings which

would occur during a design basis seismic event. The licensee's

current plans are to replace the tie wrap supports with

appropriately designed fasteners. This work is to be performed in

compliance with the licensee's process for the modification of

safety-related equipment.

10 CFR 50, Appendix B, Criterion III, Design Control requires in

part, that design changes, including field changes, undergo the

same review and meet the same standards as those applied to the

original design. This review includes, but is not limited to the

verification or checking the adequacy of the design.

18

The RTGB was modified with no review or verification of the

adequacy of the design.

This NRC identified violation is not being cited because criteria

specified in Section VII.B of the NRC Enforcement Policy were

satisfied. This issue will be tracked as a non-cited violation,

NCV 94-27-08; Unreviewed RTGB Modification.

Calibration Of Rod Insertion Limits

During post-calibration review, the inspectors noted that the

control bank D end of life rod insertion limits specified on curve

1.98, "Rod Insertion Limits," were incorrect. At 100 percent

power, the curve specifies a control bank D insertion limit of

164 steps.

However, the fuel vendor analysis for cycle 16

specifies 165 steps for this limit.

The inspectors noted that the

safety significance of this observation was minimal since alarms

are provided prior to reaching this level of rod insertion.

Further, the licensee routinely operates with the rods withdrawn

well in excess of this limit.

The inspectors concluded that this

error represented a lack of attention to detail on the part of the

engineering technical support personnel.

Based on the information obtained during the inspection, except as noted

above, the engineering program was adequately implemented.

6.

PLANT SUPPORT

a.

Plant Support Activities (71750)

Annual Exercise (82301)

In Section 5.6.1.2.2, Exercises, of their RCP, the licensee

committed to perform an off-hours exercise between midnight and

06:00 A.M. once every six years. This off-year annual exercise

which started on November 15, 1994, at 2:30 A.M. satisfied that

commitment.

This was the first exercise in which the licensee used the "Team"

concept in staffing the ERO. A "Team" would be analogous to a

"Crew" in staffing the control room. The "Team" concept appeared

to work well.

The exercise scenario consisted of: a fire lasting greater than

ten minutes resulting in a NOUE; a loss of annunciators resulting

in an SAE; a radiation spill; and the declaration of a General

Emergency due to multiple spent fuel assemblies being damaged when

a spent fuel cask dropped into the spent fuel pool.

Security commenced their security search procedure for

incorporating the TSC and EOF into the protected area at the NOUE

declaration. The security search took 51 minutes to complete.

19

The licensee activated the TSC and EOF when the search was

complete and after the Alert Emergency declaration.

The Control Room crew exhibited good communication skills.

The

crew was alert and actively pursued resolution to plant problems

and potential plant problems that were scenario driven. From the

control room, emergency event classifications were correct,

activation procedures were followed, and offsite notifications

were timely and complete. The SEC in the control room exhibited

good command and control.

The SECs used procedures when

transferring SEC responsibilities from the Control Room to the

TSC. The transfer was clear and concise.

The TSC was activated in a timely manner, approximately 44 minutes

after the Alert Emergency declaration. In the TSC, briefings were

held on the hour and half hour. The SEC exhibited good command

and control.

The TSC staff communicated effectively among

themselves and with the OSC. Once activated, event declarations

were made from the TSC.

Event classifications were correct and

procedures were followed.

The OSC prioritized missions. In forming a team, work missions

were planned, radiation levels and plume exposure were considered.

Once teams were formed, they were briefed on their mission, plant

conditions, and radiation levels. Once deployed, teams were

tracked and debriefed when missions were complete.

The EOF was activated in a timely manner, approximately 45 minutes

after the Alert Emergency declaration. The EOF held their own

briefings in addition to monitoring TSC briefings. The EOF staff

functioned satisfactorily together as a team. Dose assessment

personnel identified radiation levels increasing before the rest

of the EOF staff was aware that the spent fuel cask had dropped

into the spent fuel pool.

The dose assessment individual

immediately applied the data pertaining to increasing radiation

levels to the appropriate general emergency EALs and PARs.

Overall communications among ERFs were satisfactory.

Once activated, the EOF had responsibility for offsite

notifications. During the exercise, a total of nine initial and

follow-up offsite notifications were transmitted offsite. The

inspector reviewed the nine notifications for timeliness and

message content. The inspector concluded that all of the

notifications were timely. The inspector determined that although

adequate, several notifications should have contained additional

pertinent information. Examples are:

Offsite facilities were not informed when the fire was

extinguished or when the annunciators alarm were back in

service.

20

In Notification message number 8, offsite agencies were not

informed as to why the basis for the offsite dose release

changed from an elevated release to one at ground level.

This caused confusion with offsite agencies.

The inspectors noted that the licensee's press releases raised

more question than they provided answers.

The inspectors observed the licensee's evaluator critique of the

exercise. The inspectors noted that the critique was thorough and

objective.

In IR 94-11, an EW was identified for delayed initial offsite

notifications. Based on the inspector's review of the nine

notifications for timeliness, the inspector considers EW 94-11-01:

Delayed Initial Notification, closed.

While touring the EOF/TSC mechanical equipment area, the resident

inspectors noted several uncapped cable penetrations in an outer

wall.

Additionally, the resident inspectors noted that the iodine

channel of the R-38 radiation monitor was being carried in a

source check log as out of service. While reviewing the EOF/TSC

drawing, the inspectors also noted that the building may have been

modified from the original design. The inspectors were concerned

that each of these items may degrade the capability of the

buildings ventilation system to perform its design function.

These items were identified to the licensee. Pending further

review by the inspectors, this concern is identified as an

Unresolved Item, URI 94-27-09: Impact Of Potential System

Deficiencies On EOF/TSC Ventilation System Design.

The inspectors observation of the exercise concluded the exercise

was fully successful.

No exercises weaknesses, violations or

deviations were identified.

b.

Site Visit By Boise Interagency Fire Center Representative

The NRC maintains a contract with the Boise Interagency Fire

Center in Boise, Idaho, for providing emergency communications

assistance. One of the terms of the contract is that the Boise

personnel visit each site every five years. The purpose of the

site visits is to collect information for preplanning which will

give responding Boise Personnel advanced information about what

emergency communications equipment would be required. The NRC

contract with Boise requires that from the time of initial

notification, Boise has twelve hours to respond to a site and be

operational.

Boise schedules the site visits around times when major national

or international emergencies such as hurricanes and forest fires

are not anticipated.

21

A Boise representative visited the Robinson facility on

November 30, 1994.

The actual visit lasted approximately an hour

during which the Boise representative met the resident inspector

and the Emergency Response Coordinator, and was provided copies of

the 10 and 50 mile EPZ maps, the EOF and TSC layout, and FSAR

sections 2.1 and 2.2 (Geography and Demography).

c.

Followup -

Plant Support (92904)

Closed EW 50-261/94-11-01: Delayed initial notification

IFI 93-15-01, 261/93-15-01: Review Licensee Evaluation Of TI

2515/112 Weakness

In Inspection Report 93-15, the inspectors documented a review of

the licensee's program for identifying, evaluating, and

documenting changes in population distributions, or industrial,

military, or transportation hazards on or near the site that may

have occurred since the plant was originally licensed. As a

constituent of this inspection, the licensee's program for

updating the FSAR was also reviewed.

The FSAR is required to be updated annually, pursuant to

CFR 50.71(e).

The inspector reviewed Robinson Administrative

Procedure AP-021, Development, Review, and Approval of Changes To

The Safety Analysis Report, as well as, higher tier procedures

such as NED-3.2 and NGGM 304-01, which describe the licensee's

program intended to ensure that updates to the FSAR are

accomplished. The inspectors noted that the guidance provided in

those procedures dealt almost exclusively with the mechanism of

processing the paperwork associated with an FSAR update, but did

not embody the more universal instruction such as how, when, or

why, an update is to be originated. This was not a formal

documented program in place to facilitate the routine update of

the FSAR.

The licensee indicated that they would evaluate their existing

program for updating the FSAR. This item was identified IFI

261/93-15-01:

Review Licensee Evaluation of TI 2515/.112

Weakness.

The licensee has since modified Administrative Procedure AP-021,

Development, Review and Approval of Changes To the Updated Final

Safety Analysis Report to require that a review of the UFSAR is

performed within six month of the last refueling outage and

annually, and to assure that identified changes result in a

revision. This IFI is closed.

Based on the information obtained during the inspection, except as noted

above, the plant support program was adequately implemented.

22

7.

EXIT INTERVIEW

Preliminary exit findings regarding the EP drill inspection effort were

communicated to the licensee on December 16, 1994, upon completion of

inspection activities by the Regional Inspector.

Preliminary exit findings were communicated to the licensee regarding

Project Engineer open item followup inspection efforts on November 18,

1994.

The inspectors met with licensee representatives (denoted in

paragraph 1) at the conclusion of the inspection on December 6, 1994.

During this meeting, the inspectors summarized the scope and findings of

the inspection as they are detailed in this report. The licensee

representatives acknowledged the inspector's comments and did not

identify as proprietary any of the materials provided to or reviewed by

the inspectors during this inspection. No dissenting comments from the

licensee were received

Item Number

Status

Description/Reference Paragraph

VIO 94-27-01

OPEN

Operator Procedure Non-Compliance Results

In Control Room Ventilation Inoperable

(paragraph 3)

NCV 94-27-02

OPEN

Inadequate FT-613 Calibration Procedure

(paragraph 4)

URI 94-27-03

OPEN

WCCU Oil Procurement Practices (paragraph

4)

NCV 94-27-04

OPEN

Failure To Provide Procedure For Safety

Related Maintenance (paragraph 4)

NCV 94-27-05

OPEN

Inadequate Testing Of Control Room

Ventilation Dampers (paragraph 4)

URI 94-27-06

OPEN

Resolution of Feedwater Nozzle Performance

and Impact On Calorimetric (paragraph 4)

VIO 94-27-07

OPEN

Failure To Adequately Control Calorimetric

(Paragraph 4)

NCV 94-27-08

OPEN

Unreviewed RTGB Modification (Paragraph 5)

URI 94-27-09

OPEN

Impact Of Potential System Deficiencies on

EOF/TSC Ventilation System Design

(Paragraph 6)

URI 94-23-05

CLOSED

Control Room Exhaust Dampers (paragraph 4)

23

EW 94-11-01

CLOSED

Delayed Initial Notification (paragraph 6)

IFI 93-15-01

CLOSED

Review of Licensee Evaluation of TI

2515/112 Weakness (paragraph 6)

ACRONYMS AND INITIALISMS

CFR

Code of Federal Regulation

CV

Containment Vessel

CRVS

Control Room Vandalization System

DPI

Digital Position Indicator

EAL

Emergency Action Level

EOF

Emergency Operations Facility

EPZ

Emergency Planning Zone

ERF

Emergency Response Facility

EST

Engineering Surveillance Test

ERFIS

Emergency Response Facility Information System

EW

Exercise Weakness

FCV

Flow Control Valve

FSAR

Final Safety Analysis Report

FT

Flow Transmitter

gpm

Gallons Per Minute

HEPA

High Effective Particulate Absolute

HVE

Heating Ventilation Exhaust

I&C

Instrumentation & Control

LCO

Limiting Condition For Operation

Ma

Milliamp

NAD

Nuclear Assessment Department

NED

Nuclear Energy Division

NGGM

Nuclear Generation Group Manual

NOUE

Notice of Unusual Event

OSC

Operations Surveillance Center

OST

Operations Surveillance Test

PAR

Protective Action Recommendation

PI

Pressure Indicator

PIC

Process Instrument Calibration

PM

Preventative Maintenance

psig

Pounds per square inch-gauge

RCP

Reactor Coolant Pump

RTD

Resistance Thermal Device

RTGB

Reactor Turbine Gauge Board

SAE

Site Area Emergency

SEC

Site Emergency Coordinator

SP

Special Procedure

STA

Shift Technical Advisor

TSC

Technical Support Center

UFSAR

Updated Final Safety Analysis Report

URI

Unresolved Item

VIO

Violation