UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 15, 1998 Mr. J. S. Keenan, Vice President Carolina Power & Light Company H. B. Robinson Steam Electric Plant, Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550
SUBJECT:
QUALITY ASSURANCE PROGRAM DESCRIPTION REVISION. 15,.
H. B. ROBINSON, UNIT 2 (TAC NO. M99065)
Dear Mr. Keenan:
By letter dated June 2, 1997, Carolina Power and Light transmitted Revision 15 of their Quality Assurance Program Description. This revision reflected the relocation of selected portions of the H.B. Robinson Technical Specifications (TS) to the licensee's Updated Final Safety Analysis Report (UFSAR) which the licensee had proposed as part of the overall conversion to Improved Technical Specifications.
The staff completed its review of the licensee's Improved TS application by issuing License Amendment 176, with an accompanying Safety Evaluation (SE), on October 24, 1997. In the SE, the staff addressed the proposed relocation of the following TS items to the Quality Assurance (QA) Program description in the Updated Final Safety Analysis Report:
(1) TS Subsection 6.5. 1. 1, "Procedures, Tests, and Experiments, (2) TS Subsection 6.5.1.2, "Modifications, (3) TS Subsection 6.5.1.3, "Technical Specifications and License Changes, (4) TS Subsection 6.5.1.4, "Review of Technical Specification Violations, (5) TS Subsection 6.5.1.5, "Nuclear Safety Review Qualification, (6) TS Subsection 6.5.1.6, "Plant Nuclear Safety Committee, (7) TS Section 6.5.2, "Nuclear Assessment Section Independent Review Program, (8) TS Section 6.5.3, "Nuclear Assessment Section Assessment Program, (9).TS Section 6.5.4, "Outside Agency Inspection and Audit Program, and (10) TS Section 6.10, "Record Retention."
In the October 24, 1997 SE, the staff concluded that the proposed relocation of the above TS items from the TS to the QA Program Description satisfied the requirements of 10 CFR 50.36 and that the relocated items would be subjected to appropriate change controls (10 CFR 50.54(a)). On this basis, the staff approved the relocation of these items which supported, in part, the staff approval and issuance of Amendment 176.
9805270288 980515 PDR ADOCK 05000261 P
J. Keenan
-2 The SE did not directly address the compliance of the revised QA Program description with the requirements of 10 CFR 50, Appendix B. To be complete, based on the staff review of Revision 15 of the QA Program Description which contains the relocated items listed above, the staff concludes that Revision 15 to the QA Program Description in Chapter 17.3A of the UFSAR, continues to comply with the criteria of Appendix B to 10 CFR Part 50.
If you have any questions on this matter, please do not hesitate to contact me at (301) 415 1428.
Sincerely, (Original Signed By)
Joseph W. Shea, Project Manager Project Directorate 11-1 Division of Reactor Projects - 1/11 Office of Nuclear Reactor Regulation Docket No. 50-261 cc: See next page DISTRIBUTION:
&i KHeck LPlisco, RII PUBLIC PDII-1 Reading MShymlock, RiI OGC JZwolinski ACRS FILENAME - G:\\ROBINSON\\ROB99065.LTR OFFICE PM:P 1
LA:PDII-1 (A)PD:PDI1-1 HQMB/C NAME J
Dunni PTKuo SBlack DATE
- /q/98
/2/98 Y
98 J/198 COPY e5/No o
Yes/No OFFICIAL RECORD COPY
Mr. J. S. Keenan H. B. Robinson Steam Electric Carolina Power & Light Company Plant, Unit No. 2 cc:
Mr. William D. Johnson Mr. Mel Fry, Director Vice President and Senior Counsel N.C. Department of Environment Carolina Power & Light Company and Natural Resources Post Office Box 1551 Division of Radiation Protection Raleigh, North Carolina 27602 3825 Barrett Dr.
Raleigh, North Carolina 27609-7721 Ms. Karen E. Long Assistant Attorney General Mr. Robert P. Gruber State of North Carolina Executive Director Post Office Box 629 Public Staff - NCUC Raleigh, North Carolina 27602 Post Office Box 29520 Raleigh, North Carolina 27626-0520 U.S. Nuclear Regulatory Commission Resident Inspector's Office Mr. Max Batavia, Chief H. B. Robinson Steam Electric Plant South Carolina Department of Health 2112 Old Camden Road Bureau of Radiological Health Hartsville, South Carolina 29550 and Environmental Control.
2600 Bull Street Regional Administrator, Region II Columbia, South Carolina 29201 U.S. Nuclear Regulatory Commission Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Ms. D. B. Alexander Atlanta, Georgia 30303 Manager Performance Evaluation and Mr. J. W. Moyer Regulatory Affairs CPB 9 Plant General Manager Carolina Power & Light Company Carolina Power & Light Company Post Office Box 1551 H. B. Robinson Steam Electric Plant Raleigh, North Carolina 27602-1551 Unit No. 2 3581 West Entrance Road Hartsville, South Carolina 29550 Mr. Milton Shymlock U. S. Nuclear Regulatory Commission Public Service Commission Atlanta Federal Center State of South Carolina 61 Forsyth St., SW, Suite 23T85 Post Office Drawer 11649 Atlanta, Georgia 30303 Columbia, South Carolina 29211 Mr. T. M. Wilkerson Manager - Regulatory Affairs Mr. H. K. Chernoff Carolina Power & Light Company Supervisor, Licensing/Regulatory Programs H. B. Robinson Steam Electric Plant, Carolina Power & Light Company Unit No. 2 H. B. Robinson Steam Electric Plant, 3581 West Entrance Road Unit No. 2 Hartsville, South Carolina 29550-0790 3581 West Entrance Road Hartsville, South Carolina 29550