ML14176A813

From kanterella
Jump to navigation Jump to search
Insp Rept 50-261/89-26 on 891023-27.No Violations or Deviations Noted.Major Areas Inspected:Licensee Corrective Actions in Response to Previous Insp Findings Involving Environ Qualification of Electrical Equipment
ML14176A813
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 12/07/1989
From: Conlon T, Merriweather N
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML14176A812 List:
References
50-261-89-26, NUDOCS 8912210168
Download: ML14176A813 (11)


See also: IR 05000261/1989026

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

101 MARIETTA STREET,N.W.

ATLANTA, GEORGIA 30323

Report No.:

50-261/89-26

Licensee: Carolina Power and Light Company

P. 0. Box 1551

Raleigh, NC 27602

Docket No.:

50-261

License No.:

DPR-23

Facility Name: H. B. Robinson

Inspection Conducted:

October 23-27, 1989

Inspector:

.

e/

-

9

N. Merriweather

Date Singed

Approved

____

-

7

T. E.,Conion Chief

Date Signed

Plant Systems Section

Engineering Branch

Division of Reactor Safety

SUMMARY

Scope:

This routine announced inspection was conducted to review licensee's

corrective actions in response to previous inspection findings involving

environmental qualification (EQ)

of electrical equipment as discussed in NRC

Inspection Reports 50-261/87-10 and 87-19 and Notice of Violation and Proposed

Imposition of Civil Penalty issued June 16, 1988.

Results:

No specific strengths were noted in the licensee's corrective action program

for EQ problems identified in Report 50-261/87-10. The corrective actions were

considered timely but they were not always complete as evidenced by the

identification of similar problems in 1988.

The corrective action was also

limited in scope to those particular concerns identified in the report. As a,

result some significant EQ issues remained undisclosed until the EQ Program

assessment was performed in 1988. All except one of the previously identifies

violations is considered closed.

One violation remains open because the NRC

has concerns regarding the adequacy of the qualification documentation for the

conduit entrance seals installed as part of the corrective action. These seals

are submerged during a LOCA and have not been tested in a submerged condition.

For a further discussion on this problem see paragraph 2.d.

12

1D

F.UOC;IT:

2

The new items identified during this inspection are as follows:

Unresolved Item 50-261/89-26-01, the Victoreen High Range Radiation Monitor is

not installed in accordance with the qualified tested configuration.

The

configuration installed is similar to the one that failed during qualification

testing, paragraph 2.f.

Unresolved Item 50-261/89-26-02, the Licensee has not established qualification

for certain plant cables that become submerged during LOCA conditions,

paragraph 2.g.

Unresolved Item 50-261/89-26-03, the licensee has not established qualification

for a Raychem moisture seal installed on.containment penetration F01, paragraph

3.a.

Unresolved Item 50-261/89-26-04, the licensee will evaluate and determine dose

rates for Hydrogen Recombiner skid for EQ consideration, paragraph 3.b.

In the areas inspected, violations or deviations were not identified.

REPORT DETAILS

1. Persons Contacted

Licensee Employees

  • W. J. Flanagan, Manager, Modifications and Configuration Control
  • S. A Griggs, Technical Aide - Regulatory Compliance
  • E. M. Harris, Jr., Manager - Onsite Nuclear Safety
  • M. Heath, Engineering Supervisor, Modification Projects
  • J. D. Kloosterman, Director, Regulatory Compliance
  • R. E. Morgan, Plant General Manager
  • H. J. Young, Manager QA/QC

Other licensee employees contacted during this inspection included

engineers, security force members, and administrative personnel.

Other Organizations

L. Easter, Impell Engineer

J. C. Hamlen, Impell Engineer

F. Roy, EGS-EQ Engineer

NRC Resident Inspectors

L. Garner, Senior Resident Inspector

  • K. Jury, Resident Inspector
  • Attended exit interview

Acronyms and initialisms used throughout this report are described in

paragraph 5.

2. Action on Previous Inspection Findings (92701, 92702)

a. (Closed) Violation 50-261/87-10-01, Cable Identification and

Qualification (One Example of Violation A in the NOV)

NRC Inspection Report 50-261/87-10 identified several deficiencies

regarding the qualification of electrical cables at Robinson. The

report states in parts,... the licensee (1) did not know which type

of cable was used for specific EQ components, (2) did not believe

that procedural control of cable installation during plant construc

tion could be relied on to identify cables, (3) had not performed

plant walkdowns or modification package reviews to address the

possible use of other cable types, and (4) had not removed any cable

2

samples for analysis. The above problem was cited as a violation in

NRC Violation and Proposed Imposition of Civil Penalty dated June 16,

1988.

The licensee responded to the violation in a letter to NRC dated

September 1, 1988 in which the licensee admits the violation and

discusses what corrective actions were taken to resolve the concerns.

The licensee indicated that they performed a review of EQ cables

located inside containment.

The cable review included both field

walkdowns, modification package reviews, a review of the conduit and

cable list drawings,

and a review of original cable specification.

Included in the review was an inspection of each cable for physical

attributes such as cable diameter, color and configurations.

This

information was compared to information available in the conduit and

cable list and the original cable specifications with unknown PVC

cable being identified.

The unknown cable was replaced with

qualified cable.

The licensee has performed an additional

Engineering Evaluation (EEG 89-080) to identify all cable that is

required to be environmentally qualified. The review resulted in a

baseline EQ cable list which provided a computerized data base of all

EQ cables.

The

EE was approved the week of the inspection on

October 26, 1989.

However, the results of the review have already

been incorporated in the EQ Master list (TMM-019)

issued June 21,

1989. Appendix B to the Master List now identifies all EQ cables by

plant ID.

The list appeared to be all inclusive based on a random

sample of components.

The only concern identified is that there was

no method to go from the EQ Master List to the associated qualifica

tion documentation without assistance from licensee EQ staff.

The

index for the EQ Data Packages and reference files was not controlled

as part of the EQ Program. The inspector informed the licensee that

the list may not be considered acceptable without information

concerning manufacturer and model numbers.

In lieu of manufacturer

and model numbers the inspector also considered it to be acceptable

to include a reference to the appropriate EQDP. The licensee chose

the later as a reasonable solution to resolving concerns regarding

auditability of EQ files and the EQ Master list. The licensee agreed

to incorporate appropriate references to the EQDPs.

It appears that the reviews performed by the licensee are adequate to

verify that all EQ cables both inside and outside containment are

supported by test data.

The licensee is now in full compliance.

This item is closed.

b.

(Closed)

Violation 50-261/87-10-02,

Crouse -

Hinds Electrical

Penetrations (Example 1 of Violation B in the NOV),

(Closed) Unresolved Item 50-261/87-19-01, EQ of Penetration Splices

The violation occurred because the electrical connectors and

shrink-fit sleeve splices used on Crouse-Hinds penetrations 'were not

3

qualified by testing or analysis. The licensee admits the violation,

but argues that enforcement action is not warranted. The issue of

whether enforcement action is warranted is still being evaluated by

NRC and will not be discussed in this report.

This report will only

address the corrective actions taken by the licensee to resolve this

concern.

The licensee has conducted a review for all components identified on

the EQ Master list located inside containment to verify that all

unqualified penetration-to-pigtail and pigtail-to-field splices have

been replaced.

Back in 1987 the licensee had made attempts to

replace all questionable splices with qualified Raychem splices prior

to startup from the outage during which this concern was raised. The

implemented special procedure (SP) 775 installed qualified splices at

the penetration -to-pigtail connection and replaced Crouse-Hinds

connectors.

The licensee replaced instrumentation cable splices

considering that the violation only related to instrumentation

circuits because the

NRC had expressed a concern about loop

accuracies.

The repairs made on the pigtail-to-field cable splices were later

found to be unacceptable because they could allow moisture intrusion

from the open end of the cable jacket to the insulated butt splices,

and consequently, the possibility for a line-to-line leakage path was

created. This problem was discussed in NRC URI 50-261/87-19-01. The

licensee confirmed this failure mode by testing. Subsequently, they

implemented modification M928 to repair the splices made under SP775.

The plant was shutdown and the repairs were completed in 1987.

In October 1988 the licensee discovered that the HVH 1-4 containment

fan cooler penetration splices were not replaced with qualified

splices. The event was reported to NRC as LER 88-024.

It was later classified by NRC as an additional example of the

original violation. The licensee discovered some other EQ components

that were omitted from the Mod 928 repair and contained the SP 775/SP

759 pigtail-to-field cable splice that could allow moisture through

the cable jacket.

A final review of splices was conducted during the 1988 refueling

outage. This review verified that all EQ circuits could be tracked

through quality documentation to a qualified configuration.

The

review also evaluated those components added to the EQ Master list

due to either a change in the environmental zone or the EQ list

re-evaluation program.

The results of the above reviews are

discussed in EE 89-044. The above items and the associated LER 88-024

are now considered closed.

4

C. (closed)

Violation 50-261/87-10-03, Limitorque Valve Operators

(Examples 2 of Violation A and Example 2 of -Violation B of the NOV

dated June 16, 1988)

Two examples of Violations were identified, failure to -provide

qualification documentation for- EQ valves (V-744A and B) and failure

to install EQ valves (V-866A and B) in accordance with the tested

configuration. The licensee responded to the violations in a letter

dated September 1, 1988. The licensee indicated that the qualifica

tion file for valves V-744A and B was updated with supplemental

information evaluating the operability of the valves during small and

large break LOCAs. The unqualified grease in the geared limit switch

housing and the internal wiring were also replaced. - Subsequently,

thevalves were replaced with Limitorque SB-3 actuators that do not

have motor brakes.

The brakes on the old actuators had not been

demonstrated to be qualified.

(See Inspection Report 87-10).

The

deficiencies identified on valves V-866A and B involved unqualified

tape splices, unqualified limit switch gear housing grease, lack of

T-drains and grease reliefs, and unidentified jumper wires.

All

these deficiencies were corrected by work request prior to startup

from the outage when they were discovered.

The licensee is now in

full compliance.

Both examples of violations are now considered

closed.

CI.

(Open) Violation 50-261/87-10-04, Cable Entrance Seals For Solenoid

Valves and Transmitters (Violation C in the NOV Dated 16 June 88)

The violation involved a failure to install conduit seals on ASCO

Solenoid valves and Rosemont 1153A transmitters.

Since the EQ

inspection the licensee installed conduit seals on all EQ equipment

identified on MOD 924-5 which included the Reactor Vessel Head Vent

Solenoid valves (RC-567 thru 572) reported on LER 88-20.

The

Regulatory Guide 1.97 items required to be EQ qualified have also

been verified by the licensee to have documentation showing that

seals have been installed.

A list of all components requiring

conduit seals is now incorporated as Appendix B to the EQ Master list

(TMM-019).

Additionally,

the Maintenance Management Procedure

MMM-025 was annotated to identify which components require conduit

seals. The seal design utilized to provide a moisture proof barrier

was provided by Patel Engineers. However, subsequent review of the

file (EQDP 21.0) and associated test reports raises several concerns

regarding the adequacy of the testing conducted on the seals and how

the test anomalies were .evaluated.

Review of both test reports

revealed that several specimens failed post LOCA pressure tests

of 100 psig of nitrogen gas.

Some failures occurred at less than

10 psig.

The failures were attributed to design problems and

technicians not following procedures.

The intent of the second test

was to verify the acceptability of the design changes and qualify

the grommets as a reusable seal.

The failures in the second test

were attributed to technician handling. The NRC concerns with both

tests are as follows:

(1) Test durations of ten and four days respectively versus 30 days

required operating time period.

(2) Questionable thermal pre-aging as a result of using an appearant

high activation energy value of 2.29 ev versus industry used

values of 1.00 ev for similar material.

(3) Test specimens were not tested submereged.

(4) Lack of use range data for cable diameters versus hole diameters

in rubber grommet.

In a letter from CP&L dated November 14, 1989, the licensee provided

additional information regarding the determination of the activation

energy and reduced time LOCA testing on Patel seals. In this letter

the licensee indicated that the activation energy for EPDM was

determined by thermogravimetric analysis (TGA) on the actual grommet

material in accordance with ASTM E698-79. The licensee believes that

this method of determining the activation energy is acceptable.

The

letter further discusses how the results of a ten day LOCA test were

extrapolated using the Arrhenius formula (assuming aging at 250 0 F

for nine days) to qualify the seals for more than the required 30

days.

All this information is currently being evaluated by NRC for

acceptability.

In addition to the above, the licensee provided a letter dated

November 17,

1989, which provides the alternative plan and schedule

for long term resolution of the environmental qualification of Patel

Conduit Seals.

This letter was submitted in accordance with a

commitment

made with NRC during a telephone conversation on

November 13, 1989. In this letter the licensee has committed to have

all actions completed prior to start-up from the 1990 refueling

outage. This item remains open.

Subsequent to the inspection the licensee reported a potential

deficiency with the wire use range of Patel conduit seals.

The

licensee identified 69 seals, including equipment in both trains of

instruments required to mitigate the consequence of a LOCA which

could be affected if equipment was flooded.

Proposed correctiv.

action includes inspection of all 69 conduit seals for proper use

range.

On those with improper use range,

the grommets will be

replaced. On ASCO solenoid valves the licensee plans on drilling a

drain hole in the conduit.

6

e.

(closed) Violation 50-261/87-10-05,

Raychem Splices (Example 3 of

Violation B in the NOV Dated 16 June 88)

A violation occurred because the licensee's EQ files at the time of

the inspection did not address the discrepancies between installed

versus tested Raychem splices.

The licensee at the time of the

inspection was conducting walkdown inspections to address the

concerns identified in IN 86-53,

"Improper Installation of Heat

Shrinkable Tubing".

The licensee completed the inspection (SP-754)

using the results of several LOCA type test reports.

The splices

found not to meet the acceptance criteria were replaced by SP 759.

In addition, the EQDP was revised to reference

the Wyle Report

(17859028) that allows a 1 inch seallength.

Based on the above,

this item is considered closed.

f. (closed) Violation 50-261/87-10-06, Instrument Accuracy (Violation D

in the NOV dated June 16, 1988)

A violation was identified during the subject inspection because CP&L

files did not adequately address instrument accuracy requirements,

particularly as it related to specified accuracies versus accuracies

obtained during the design basis accident conditions.

The licensee

responded to the violation in a letter dated September 1, 1988.

In

this letter the licensee indicated that the corrective action taken

was to begin developing loop accuracy calculations based on actual

cable.test data and to incorporate these calculations into the files.

The inspector examined five completed calculations (89-07, 89-12,89-013, 89-014 and 89-015) for EQ instruments located inside

containment.

The calculations established limits for the cabling

loss IR values to maintain assumed system accuracies.

The methods

used for calculating the loop errors considered contributions from

all components and splices in the loop.

The calculations did not

identify any components as being unqualified. Calculation No.89-014

is the loop error analysis for the worst case Victoreen (R-328) High

Range Radiation Monitors. A concern exists whether the detector and

cable assembly are installed in a qualified configuration.

This

review did not address the acceptability of the assumptions made in

this analysis.

The. qualified tested configuration used a sealed

conduit arrangement from the detector to the test chamber penetration.

However, the detectors at Robinson use Raychem Shrink tubing on the

stainless steel outer shell connector. This configuration is one of

the configurations that was tested and failed due to moisture

entering the splice area via the cable jacket. The acceptability of

the installed Victoreen detectors and assumptions made in the analysis

will be identified as Unresolved Item 50-261/89-26-01, Victoreen High

Range Radiation Monitor is not installed in accordance with the tested

configuration.

4

7

All the calculations identified above assumed the worst case IR

values for cables obtained during LOCA testing in a steam environ

ment.

Recently the licensee discovered that several EQ cables and

components become submerged. However the licensee takes the position

that the worst case IR values during LOCA testing will encompass the

IR values during submerged conditions.

The licensee indicated that

they also considered post LOCA water immersion hi-pot tests that

were conducted at ambient temperatures for 5 minutes and IPCEA

standard water immersion testing. The NRC staff does not agree with

the licensee's position that qualification for submergence can be

done by analysis and still meet the intent of NUREG 0588, paragraph

2.2(5) which requires equipment that is submerged to be demonstrated

by tests.

The testing discussed above does not fully envelope H.B.

Robinson containment accident conditions.

This item is unresolved

and will be identified as Unresolved Item 50-261/89-26-02, Cable

Submergence Qualification Data.

The above unresolved items may result in the loop error calculations

being revised at a later date.

However, the licensee's design

program will ensure that appropriate information is used in

reanalyzing the loop errors.

Not withstanding resolution of the

above unresolved items, this violation is considered closed.

g. (Closed)

Violation 50-261/87-10-07,

Taped Cable Splices (Examples

No. 4 of Violation B in the NOV dated June 16, 1988

A violation resulted because the licensee did not have adequate

documentation in the file to support a similarity analysis on how

Scotch 88 tape was chemically similar to Scotch 33 and 17 and did not

have a correlation between the tested configuration and the way the

tape was installed.

The licensee responded to the violation in a letter dated

September 1, 1988.

In this letter the licensee indicated that the

splices had been removed during the 1986 outage.

This item is

considered closed.

3. Licensee Event Reports (LERs)

a. LER 88-22, Corrected Containment Flood Level Results in Submergence

of Additional Components

Followup on the above LER revealed that the licensee has completed

all corrective actions to resolve the concern.

The licensee

performed an evaluation of the components that were submerged and

concluded that they were acceptable. However, they made repairs to

penetration FO1 to protect the Kapton insulation from interacting

with Chemical spray during a. design basis event.

The systems

associated with penetration F01 were the neutron detector NE-51,

channel I core Exit Thermocouples and the Reactor Vessel Level

8

Indication System.

Repairs made to penetration FO1 consisted of

installing a Raychem shrink seal to the stainless steel feed through

to achieve a sealed arrangement over the penetration and pigtail

cables.

The repair was implenented by (PCN 88-189/00) Mod M-977,

Rev. 0. The inspector questioned the qualification of this

configuration as a qualified seal.

The licensee provided copies of

Raychem test reports for NEIS seal kits that were tested under LOCA

conditions. However, the only configuration considered qualified by

Raychem is for use outside containment in HELB environments.

Additionally,

the seal has not been tested under submerged

conditions.

The NRC inspector did not consider the seal to be

qualified; however,

the licensee believes the EQDP is adequate to

demonstrate that this configuration is acceptable. Pending review of

the licensee's additional information this item will be tracked as

Unresolved Item 50-261/89-26-03, Review Qualification for Raychem

Penetration Seal.

As stated earlier in other parts of this report

the NRC still has questions that have not been resolved regarding

the qualification of cables and conduit seals for submergence.

b. LER 88-28, Inadequate Post Accident Containment Hydrogen Reduction/

Venting System

The licensee reported that the Hydrogen Recombiner system or Post

Accident Containment Venting system could not be operated because

several locked closed manual valves in the Reactor Auxiliary Building

Pipe Alley would be inaccessible due to high radiation levels in the

area during Post LOCA conditions. The licensee corrected the problem

by relocating the manual valves to an area that is accessible during

LOCA conditions.

The inspector was satisfied that relocating the

valves would resolve the above concern.

However, review of the EQ

master list revealed that the Hydrogen Recombiner is not considered

EQ.

This is based on the fact that the Recombiner skid will be

installed in the Fuel Handling building which will not see the direct

effects of a LOCA inside containment. However, it is considered that

the recombiner internals will see some radiation dose due to the

LOCA. It is this dose that the licensee was asked to quantify to

confirm that the recombiners need not be qualified. The licensee did

not know the dose rates anticipated, however, they contacted Duke

Power, the supplier of the Recombiner skid package, to determine what

radiation levels the Recombiner could operate in. The issue will be

tracked as Unresolved Item 50-261/89-26-04,

Dose Rate for Hydrogen

Recombiner.

4. Exit Interview

The inspection scope and results were summarized on October 27, 1989, with

those persons indicated in paragraph 1.

The inspectors described the

areas inspected and discussed in detail the inspection results listed

below.

Proprietary information is not contained in this report.

Dissenting comments were not received from the licensee. resltllite

9

Four New Unresolved Items were identified as follows:

(Open) Unresolved Item 50-261/89-26-01,

Victoreen High

Range

Radiation Monitor is not Installed in Accordance with the Tested

Configuration, paragraph 2.f

O

(Open) Unresolved Item 50-261/89-26-02, Cable Submergence Qualifica

tion Data, paragraph 2.g

o

(Open)

Unresolved Item 50-261/89-20-03,

Review Qualification for

Raychem Penetration Seal, Paragraph 3.9

(Open)

Unresolved Item 50-261/89-26-04,

Dose Rate for Hydrogen

Recombiner, paragraph 3.b

(Open) Violation 50-261/87-10-04, Remains open pending evaluation of

Patel conduit seal test data.

5. Acronyms and Initialisms

CPL

Carolina Power and Light Company

EE

Engineering Evaluation

EPDM

-Ethylene

Proplene Diene Monomers

EQ

Environmental Qualification

EQDP

Equipment Qualification Data Package

HELB

High Energy Line Break

ID

Identification

IN

Information Notice

IPCEA

Insulated Power Cable Engineers Association

LER

Licensee Event Report

LOCA

Loss of Coolant Accident

MOD

Modification

NESI

Nuclear Environmental Interface Kit

NOV

Notice of Violation

NRC

Nuclear Regulatory Commission

PCN

Plant Change Notice

SP

Special Procedure

URI

Unresolved Item

0III