APPENDIX A NOTICE OF VIOLATION Carolina Power and Light Company License No. DPR-23 H. B. Robinson Based on the NRC inspection September 8-11, 1980, certain of your activities were apparently not conducted in full compliance with NRC requirements as indi cated below. These items have been categorized as described in correspondence to you dated December 31, 1974.
A.
As required by Section 6.8.1 of the Technical Specifications "Written proce dures... shall be established, implemented, and maintained that meet...the requirements...of Section 5.1 and 5.3 by ANSI N18.7-1976 and Appendix A".
Contrary to the above, as of September 8, 1980, procedure for Pipe Stress Review and Analysis had no reference of acceptance criteria on dimensional tolerances for safety related supports.
This is an Infraction.
B. As required by Section 6.8.1 of the Technical Specifications "Written proce dures... shall be established, implemented, and maintained..."
and Special Procedure SP-205 paragraph 6.28 "Clearances shall be measured and recorded on all four sides of pipe and penetration and restraints..
Contrary to the above, field document, used to verify the as-built for safety-related system ISO-RC-4 did not have any records of inspection of clearances for the wall penetrations.
This is an Infraction.