MONTHYEARIR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) ML23283A0222023-10-0909 October 2023 Follow Up to Fermi Unit 2 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval ML23276B4542023-10-0505 October 2023 Cyber Security Inspection Report 05000341/2023402 ML23243A8852023-09-18018 September 2023 Issuance of Amendment No. 225 Regarding Revision of Technical Specifications 3.7.2, Emergency Equipment Cooling Water, Emergency Equipment Service Water and System and Ultimate Heat Sink (Exigent Circumstances) ML23248A2242023-09-0707 September 2023 Regulatory Audit in Support of Review of License Amendment Request for a Risk-Informed Approach for Addressing the Effects of Debris on ECCS Strainer Performance ML23223A2242023-08-29029 August 2023 Individual Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for Hearing (Exigent Circumstances) ML23237B4332023-08-25025 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI IR 05000341/20230052023-08-24024 August 2023 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2023005) ML23229A0122023-08-17017 August 2023 Issuance of Amendment No. 224 to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 (Emergency Circumstances) IR 05000341/20233012023-08-16016 August 2023 NRC Initial License Examination Report 05000341/2023301 ML23227A2212023-08-15015 August 2023 Emergency Application to Revise Technical Specifications to Adopt TSTF 568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 ML23219A1792023-08-0707 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Fermi Power Plant, Unit 2 ML23216A1872023-08-0404 August 2023 Submittal of Relief Request RR-A25 for Extended License Period IR 05000341/20230022023-08-0404 August 2023 Integrated Inspection Report 05000341/2023002 ML23206A1272023-07-26026 July 2023 NOED for Fermi Power Plant, Unit Two Technical Specification 3.7.2, Emergency Equipment Cooling Water Emergency Equipment Service Water System and Ultimate Heat Sink IR 05000341/20230012023-06-28028 June 2023 Integrated Inspection Report 05000341/2023001 2024-08-14
[Table view] |
Text
June 11, 2014 Mr. James T. Conner Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 280 OBA 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
DETERMINATION OF ACCEPTABILITY AND SUFFICIENCY FOR DOCKETING, PROPOSED REVIEW SCHEDULE, AND OPPORTUNITY FOR A HEARING REGARDING THE APPLICATION FROM DTE ELECTRIC COMPANY, FOR RENEWAL OF THE OPERATING LICENSE FOR FERMI 2
Dear Mr. Conner:
By letter dated April 24, 2014, as amended by letter dated June 5, 2014, the U.S. Nuclear Regulatory Commission (NRC) received the DTE Electric Company (DTE) application for renewal of operating license number NPF-43 for Fermi 2. Notice of receipt of this application was published in the Federal Register on May 12, 2014 (79 FR 27003). The purpose of this letter is to provide the results of the NRC staff's acceptance review of the license renewal application (LRA) for Fermi 2. The acceptance review determines whether the application contains sufficient information to allow the NRC staff to proceed with the safety and environmental review.
The NRC staff has reviewed your application following the guidance in NUREG-1800, Revision 2, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants, and NUREG-1555, Supplement 1, Revision 1, Standard Review Plans for Environmental Reviews for Nuclear Power Plants. The NRC staff has determined that the application is complete and acceptable for docketing, in accordance with Title 10 of the Code of Federal Regulations (CFR) Sections 2.101, 54.19, 54.21, 54.22, 54.23, 51.45, and 51.53(c).
However, the staffs determination does not preclude requests for additional information (RAIs) as the review proceeds.
This letter also forwards the NRC staffs safety and environmental review schedule for the Fermi 2 application (Enclosure 1). The NRC staff will follow established review procedures and the enclosed schedule to complete the reviews required by 10 CFR Parts 51 and 54. The schedule of work activities and milestones for performing the LRA review for Fermi 2 reflects a 25-month review schedule. Milestones for hearing activities are not included in the enclosed schedule because these activities are determined by the Commission or the Atomic Safety and Licensing Board Panel.
The NRC staff noted that a triennial fire protection inspection is scheduled during the third quarter of 2014. The NRC staff understands that a large number of your license renewal team members will be providing assistance to this inspection and that you will not be able to support the Aging Management Program audits until September 15, 2014, due to resources availability.
J. T. Conner We would like to emphasize that the review of your LRA will be very detailed and thorough, and the NRC staff will make every effort to meet the scheduled milestones. Thus, your responses to the staff's RAIs, if needed, must be complete and provided in a timely manner. We request that you inform the NRC staff as early as possible should potential delays arise in your support of the schedule.
Finally, we have also enclosed a copy of the notice related to your application that is being sent to the Office of the Federal Register for publication (Enclosure 2). This notice announces the opportunity to request a hearing and to file a petition for leave to intervene.
If you have any questions on this matter, please contact Ms. Daneira Meléndez-Colón, Project Manager, for the safety review of Fermi 2 LRA, by telephone at 301-415-3301 or via e-mail at Daneira.Melendez-Colon@nrc.gov. If you have any questions related to the environmental review of the Fermi 2 LRA, please contact Ms. Leslie Perkins at 301-415-2375 or by e-mail at Leslie.Perkins@nrc.gov.
Sincerely,
/RA/
John W. Lubinski, Director Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosures:
- 1. Review Schedule
- 2. Federal Register Notice cc w/encls: See next page
ML14150A416 (Letter), ML14150A340 (Federal Register Notice),
ML14157A168 (Package) *concurred via email OFFICE LA:DLR* PM:RPB1:DLR BC:RPB1:DLR PM:RPB2:DLR NAME YEdmonds DMelendez-Colon YDiaz-Sanabria LPerkins DATE 6/3/14 6/4/14 6/4/14 6/5/14 OFFICE BC:RPB2:DLR OGC D:DLR NAME BWittick CKanatas JLubinski DATE 6/5/14 6/9/14 6/11/14 FERMI 2 LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Milestone Scheduled Actual Receive license renewal application (LRA) 04/30/2014 04/30/2014 Publish Federal Register Notice (FRN) - LRA availability 05/2014 05/12/2014 Publish FRN - acceptance/rejection and opportunity for hearing 06/2014 Publish FRN - environmental scoping meeting 06/2014 Public Meeting - License Renewal Overview and Environmental Scoping 07/24/2014 Meeting Audit - Scoping and Screening Methodology 08/04/2014 Deadline for filing hearing requests and petitions for intervention 08/2014 Environmental scoping period ends 08/2014 Audit - Environmental 09/08/2014 Audit - Aging Management Programs (Week 1) 09/15/2014 Audit - Aging Management Programs (Week 2) 09/29/2014 Regional Inspection - IP 71002, License Renewal Procedure 03/2015 Issue draft supplemental environmental impact statement (SEIS) 06/2015 U.S. Environmental Protection Agency FRN Published - draft SEIS available 06/2015 for comments Public Meeting - draft SEIS meeting 07/2015 End of draft SEIS comment period 08/2015 Issue safety evaluation report (SER) with open items 09/2015 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 11/2015 Issue final SEIS 02/2016 U.S. Environmental Protection Agency FRN Published - final SEIS available 02/2016 Issue final SER 02/2016 ACRS Full Committee meeting 04/2016 Decision - Director, NRR 05/2016 Commission decision, if hearing granted TBD ENCLOSURE 1
SUBJECT:
RECEIPT AND AVAILABILITY OF THE LICENSE RENEWAL APPLICATION FOR FERMI 2 NUCLEAR POWER PLANT DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRsrg Resource RidsNrrPMFermi2 Resource D. Melendez-Colon Y. Diaz-Sanabria L. Perkins B. Wittick M. Kunowski, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII H. Logaras, RIII C. Kanatas, OGC D. Roth, OGC A. Stone, RIII S. Sheldon, RIII