UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Mr. David A Heacock President and Chief Nuclear Officer Dominion Nuclear lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 June 10, 2014
SUBJECT:
MILLSTONE POWER STATION UNIT NO.3-CORRECTION LETTER TO LICENSE AMENDMENT NO. 259. (TAC NO. MF1731)
Dear Mr. Heacock:
On April 8. 2014, the Nuclear Regulatory Commission (NRC) issued Amendment No. 259 to Renewed Facility Operating License No. NPF-49 for Millstone Power Station, Unit No. 3 (Agencywide Documents Access and Management System Accession No. ML14073A055), in response to your application dated April 25, 2013, as supplemented by letters dated September 19, and December 11, 2013.
Amendment No. 259 revised the Technical Specification Section 6.8.4.f, "Containment Leakage Rate Testing Program", to change the peak calculated containment internal pressure for the design basis loss-of-coolant accident. However, the revised page for the Renewed Facility Operating License inadvertently changed the formatting on page 4 that resulted in an additional, unnumbered, page.
Enclosed please find corrected Renewed Facility Operating License page 4.
Please contact me at 301-415-14 76 if you have any questions.
Docket No. 50-423
Enclosure:
As stated cc w/encls: Distribution via Listserv Sincerely, Mohan C. Thadam, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (2)
Technical Specifications The Technical Specifications contained in Appendix A, revised through Amendment No. 259 and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto are hereby incorporated into the license. DNC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
(3)
DNC shall not take any action that would cause Dominion Resources, Inc. (DRI) or its parent companies to void, cancel, or diminish DNC's commitment to have sufficient funds available to fund an extended plant shutdown as represented in the application for approval of the transfer of the licenses for MPS Unit No. 3.
(4)
Immediately after the transfer of interests in MPS Unit No.3 to DNC, the amount in the decommissioning trust fund for MPS Unit No. 3 must, with respect to the interest in MPS Unit No. 3, that DNC would then hold, be at a level no less than the formula amount under 10 CFR 50.75.
(5)
The decommission trust agreement for MPS Unit No. 3 at the time the transfer of the unit to DNC is effected and thereafter is subject to the following:
(a)
The decommissioning trust agreement must be in a form acceptable to the NRC, (b)
With respect to the decommissioning trust fund, investments in the securities or other obligations of Dominion Resources, Inc. or its affiliates or subsidiaries, successors, or assigns are prohibited. Except for investments tied to market indexes or other non-nuclear-sector funds, investments in any entity owning one or more nuclear power plants are prohibited.
(c)
The decommissioning trust agreement for MPS Unit No. 3 must provide that no disbursements or payments from the trust, other than for ordinary administrative expenses, shall be made by the trustee until the trustee has first given the Director of the Office of Nuclear Reactor Regulation 30-days prior written notice of payment. The decommissioning trust agreement shall further contain a provision that no disbursements or payments from the trust shall be made if the trustee receives prior written notice of objection from the NRC.
(d)
The decommissioning trust agreement must provide that the agreement can not be amended in any material respect without 30 days prior written notification to the Director of the Office of Nuclear Reactor Regulation.
Renewed License No. NPF-49 Amendment No. 259
- ML14142A096 OFFICE LPL 1-1/PM LPL 1-1/PM NAME AChereskin MThadani DATE 5/21/2014 6/2/2014 Sincerely, IRA/
Mohan C. Thadani, Senior Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation LPLI-1 R/F RidsNrrDssStsb Resource RidsNrrDirsSCVB Resource RidsRgn1 MaiiCenter Resource RidsNrrDeEEEB Resource RidsNrrDoriDpr Resource RidsNrrPMMillstone Resource LPL 1-1/LA LPL 1-1/BC LPL 1-1/PM KGoldstein BBeasley MThadani 06/02/2014 6/10/2014 6/10/2014