Forwards Updated Prioritized List of Significant Licensing Actions for Facility
ML14114A299
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/21/1988
From: Medford M
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NUDOCS 8809260171
Download: ML14114A299 (2)


Text

u Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 M. 0. MEDFORD TELEPHONE MANAGER OF NUCLEAR ENGINEERING (818) 302-1749 AND LICENSING September 21, 1988 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Licensing Actions San Onofre Nuclear Generating Station Unit 1 By letter dated August 3, 1988, a prioritized list of significant licensing actions for San Onofre Unit 1 was provided to the NRC. The purpose of this letter is to provide an update of the list.

The enclosure provides the updated list with the revised priorities and changes. All changes are indicated by change bars.

If you have any questions regarding this matter, please let me know.

Very truly yours, Enclosure cc: 3. B. Martin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3 Jf "P a60171 Al

Prioritized List of Significant San Onofre Unit 1 Licensing Actions September 1988 SCE Federal Approval Submittal Register Required1 Issue Dates Status Date -_Remarks

1. Core Related 8/31/87 Noticed 10/28/88 Approval Tech Specs 7/8/88 required for (Am't. 143) operation beyond October 19
2. Spent Fuel 4/28/88 Noticed 11/12/88 Approval of Transshipment 6/10/88 6/20/88 deletion of License Amendment Tech Spec 4.13 (Am't. 148) required for operation beyond 11/12/88
3. Nuclear 4/15/88 Noticed 11/27/88*

Instrumentation 5/11/88 System Tech Specs (Am't. 150)

4. Control Rod 5/26/88 Noticed 2/24/89**

Insertion Limits 7/28/88 (Am't. 151)

5. Fire Protection 12/17/85 Notice NA Based on mtg.

Tech Specs 5/19/86 Required of 3/22/88 (Am'ts 120 & 136) proposed Tech Spec to be revised.

Submittal scheduled for 9/16/88

6. Steam Generator 3/10/88 Noticed 2/24/89**

Interim Tech Tube Plugging 3/22/88 5/16/88 Spec issued Criteria (F*) Tech 3/29/88 5/6/88 Spec --

long term (Am't 149)

  • Prior to Cycle 10 refueling outage
    • Prior to end of Cycle 10 refueling outage
1. NA indicates plant operation is not contingent on approval.

0941P/3