MONTHYEARML24134A1562024-09-19019 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - FRN ML24102A2572024-04-25025 April 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - March 2024 ML23237B4412023-09-29029 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Federal Register Notice, Direct and Indirect License Transfer Issuance Order ML23124A0772023-05-17017 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (FRN) ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) ML22147A1252022-07-14014 July 2022 Federal Register Notice: Environmental Assessment and Finding of No Significant Impact Regarding License Amendment Request to Revise the Emergency Plan for Davis-Besse Nuclear Power Station, Unit No. 1 ML22147A1242022-07-14014 July 2022 Environmental Assessment and Finding of No Significant Impact Regarding License Amendment Request to Revise the Emergency Plan ML22034A9832022-02-15015 February 2022 FRN - Notice of Issuance of COVID-19 Exemptions Issued in January 2022 ML21123A0842021-05-19019 May 2021 FRN - Notice of Issuance of Multiple COVID-19 Exemptions Regarding Various Parts of 10 CFR Issued in April 2021 ML20335A0902020-12-21021 December 2020 Federal Register Notice - November 2020 COVID-19 Exemptions ML20119B0682020-05-0808 May 2020 Exemption ML20119B0702020-05-0808 May 2020 Federal Register Notice ML19303A0672019-12-0202 December 2019 Firstenergy Nuclear Operating Company - Federal Register Notice, Order Approving Direct and Indirect Transfer of Licenses and Draft Conforming Amendments for Beaver Valley Units 1 and 2, Davis-Besse Unit 1, and Perry Unit 1 ML19212A1372019-08-0606 August 2019 Federal Register Notice for Withdrawal of October 22, 2018, License Amendment Application ML19212A1352019-08-0606 August 2019 Federal Register Notice for Withdrawal of February 5, 2019, License Amendment Application for Post-Shutdown Emergency Plan ML19212A1362019-08-0606 August 2019 Federal Register Notice for Withdrawal of February 5, 2019, License Amendment Application for Permanently Defueled Technical Specifications ML19212A1392019-08-0606 August 2019 Withdrawal of Licensing Actions Associated with the Permanent Shut Down of the Plant (Epids L-2018-LLA-0287, L-2019-LLA-0011, L-2019-LLA-0012, L-2019-LLE-0011, and L-2019-LLQ-0000) ML19162A1332019-07-31031 July 2019 Federal Register Notice: Firstenergy Nuclear Operating Company Davis-Besse ISFSI - Environmental Assessment and Finding of No Significant Impact; Issuance ML19151A4742019-06-24024 June 2019 Letter to FENOC - Individual FRN Regarding Application for Order Consenting to Transfer of Licenses and Conforming Amendments. Notice of Consideration of Approval of Transfers and Conforming Amendments and Opportunity for Comments and a Hea ML19151A4932019-06-24024 June 2019 Individual FRN Regarding Application for Transfer of Licenses and Conforming Amendments. Notice of Consideration of Approval of Transfer of Facility Operating Licenses and Conforming Amendments, and Opportunity for Comments and a Hearing ML19067A0222019-06-0404 June 2019 FENOC - Exemption (EPID-L-2018-LLE-0016) ML19067A0232019-06-0404 June 2019 FENOC - Notice of Issuance of Exemption FRN (EPID-L-2018-LLE-0016) ML19133A0722019-05-16016 May 2019 FENOC Fleet - Beaver Valley 1 & Davis Besse 1 Withdrawal of an Amendment Request Administrative License Amendment Request to Reflect a Change in the Entity Providing a $400 Million Support Agreement (CAC Nos. MF9714 & MF9715, EPID L-2017-LL ML19133A0492019-05-16016 May 2019 FENOC Fleet FRN Notice Withdrawal of the Application ML19052A0412019-04-0404 April 2019 OEDO-18-00160 - Notice of Issuance of Final Director'S Decision in FRN ML19085A2172019-03-29029 March 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 04/09/2019 ML19056A5352019-02-28028 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/2019 NRC-2019-0065, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/20192019-02-28028 February 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 03/12/2019 NRC-2018-0192, Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment2018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment ML18130A8492018-09-0404 September 2018 Firstenergy Nuclear Operating Company (Fenoc); Firstenergy Nuclear Generation, LLC; Environmental Assessment ML18130A8852018-08-29029 August 2018 FENOC Fleet - Beaver Valley; Davis-Besse; Perry - Environment Assessment and Finding of No Significant Impact Related to Exemption Request for a Physical Barrier Requirement (CAC Nos. MG0010, MG0011, MG0012, and MG0013; EPID L-2018-LLE-0019 ML18220B3172018-08-27027 August 2018 OEDO-18-00160, Individual Fr Notice for Publication, 10 CFR 2206 Request-Action, FENOC Fleet 2.206 Petition ML18220B3142018-08-27027 August 2018 OEDO-18-00160 - Acknowledgement Letter 2.206 Petition for Citizen Complaint and Request for Enforcement Action Regarding Firstenergy Nuclear Facility Operations in Ohio and Pennsylvania NRC-2018-0174, OEDO-18-00160, Individual Fr Notice for Publication, 10 CFR 2206 Request-Action, FENOC Fleet 2.206 Petition2018-08-27027 August 2018 OEDO-18-00160, Individual Fr Notice for Publication, 10 CFR 2206 Request-Action, FENOC Fleet 2.206 Petition ML16336A0622017-01-0404 January 2017 Environmental Assessment and Finding of No Significant Impact Related to License Amendment Request to Revise Technical Specification 5.5.3, Radioactive Effluents Controls Program ML16250A3132016-09-0707 September 2016 EA-16-022 Davis Besse FRN Notice NRC-2016-0191, EA-16-022 Davis Besse FRN Notice2016-09-0707 September 2016 EA-16-022 Davis Besse FRN Notice ML16061A3012016-03-0202 March 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: March 15, 2016 ML15294A4112015-12-0808 December 2015 License Renewal FRN ML15070A4002015-04-29029 April 2015 FRN-Notice of Availability of the Final Plant-Specific Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Power Station, Unit 1 ML13018A2392015-04-0808 April 2015 G20110171 - Letter to Petitioner Saporito on Proposed Director'S Decision Regarding 2.206 Petition Dated: March 12, 2011 NRC-2014-0162, Federal Register Notice - Confirmatory Order Modifying License, Davis-Besse Nuclear Power Station, Unit 12014-06-30030 June 2014 Federal Register Notice - Confirmatory Order Modifying License, Davis-Besse Nuclear Power Station, Unit 1 ML14164A2102014-06-30030 June 2014 Federal Register Notice - Confirmatory Order Modifying License, Davis-Besse Nuclear Power Station, Unit 1 ML14050A0782014-02-24024 February 2014 Notice of Availability of Draft Plant-Specific Supplement 52 to Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Davis-Besse Nuclear Power Station, Unit 1 ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13228A3992013-08-12012 August 2013 Letter to Holders of Independent Spent Fuel Storage Installation (ISFSI) Licenses Re Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit - Rin 3150-AI64 (NRC-2009-0163) EA-02-109 ML13155A1132013-06-0404 June 2013 Federal Register Notice Published 6/4/2013, 78 Fr 33448-33449, Application for License to Export High-Enriched Uranium ML12237A1572012-08-28028 August 2012 Federal Register Notice Regarding the ACRS Plant License Renewal (Davis Besse)Subcommittee Meeting, September 19, 2012 ML1208002922012-03-20020 March 2012 Sunshine Federal Register Notice for Week of March 26, 2012 ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status 2024-09-19
[Table view] Category:Letter
MONTHYEARML24303A3282024-10-29029 October 2024 Information Request for the Cyber Security Baseline Inspection Identification to Perform Inspection ML24281A0662024-10-0404 October 2024 EN 57363 - MPR Associates, Inc. Report in Accordance with 10 CFR Part 21 on Incomplete Dedication of Contactors Supplied as Basic Components IR 05000346/20244032024-09-27027 September 2024 Security Baseline Inspection Report 05000346/2024403 ML24269A0552024-09-25025 September 2024 Submittal of the Updated Final Safety Analysis Report, Revision 35 05000346/LER-2021-001-01, Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground2024-09-19019 September 2024 Emergency Diesel Generator Speed Switch Failure Due to Direct Current System Ground ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter ML24260A2382024-09-16016 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24255A8032024-09-11011 September 2024 Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1602024-09-0505 September 2024 Information Request to Support Upcoming Material Control and Accounting Inspection at Davis-Besse Nuclear Power Station L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000346/20240052024-08-22022 August 2024 Updated Inspection Plan for Davis-Besse Nuclear Power Station (Report 05000346/2024005) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000346/20240022024-08-0101 August 2024 Integrated Inspection Report 05000346/2024002 IR 05000346/20244012024-07-30030 July 2024 Security Baseline Inspection Report 05000346/2024401 ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification L-24-032, Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report2024-07-15015 July 2024 Cycle 23 and Refueling Outage 23 Inservice Inspection Summary Report L-24-063, License Amendment Request to Remove the Table of Contents from the Technical Specifications2024-07-0808 July 2024 License Amendment Request to Remove the Table of Contents from the Technical Specifications L-24-024, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2024-06-19019 June 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-214, Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements2024-06-0505 June 2024 Submittal of Relief Request for Impractical American Society of Mechanical Engineers Boiler and Pressure Vessel Code Section XI Examination Requirements L-24-019, Unit No.1 - Report of Facility Changes, Tests, and Experiments2024-05-22022 May 2024 Unit No.1 - Report of Facility Changes, Tests, and Experiments ML24142A3532024-05-21021 May 2024 Station—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection L-24-072, Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 20232024-05-15015 May 2024 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report - 2023 L-24-111, Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-05-15015 May 2024 Response to Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations L-24-031, Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage2024-05-14014 May 2024 Unit No.1 - Steam Generator Tube Circumferential Crack Report - Spring 2024 Refueling Outage IR 05000346/20240012024-05-0303 May 2024 Integrated Inspection Report 05000346/2024001 L-24-069, Occupational Radiation Exposure Report for Year 20232024-04-30030 April 2024 Occupational Radiation Exposure Report for Year 2023 L-24-018, Submittal of Core Operating Limits Report, Cycle 24, Revision 02024-04-16016 April 2024 Submittal of Core Operating Limits Report, Cycle 24, Revision 0 ML24089A2582024-04-0101 April 2024 Request for Information for the NRC Quuadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000346/2024010 L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage ML24036A3472024-03-0707 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0076 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations ML24057A3362024-02-28028 February 2024 Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) IR 05000346/20230062024-02-28028 February 2024 Re-Issue Annual Assessment Letter for Davis-Besse Nuclear Power Station (Report 05000346/2023006) L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee IR 05000346/20243012024-02-0202 February 2024 NRC Initial License Examination Report 05000346/2024301 IR 05000346/20230042024-01-31031 January 2024 Integrated Inspection Report 05000346/2023004 ML23313A1352024-01-17017 January 2024 Authorization and Safety Evaluation for Alternative Request RP 5 for the Fifth 10 Year Interval Inservice Testing Program ML23353A1192023-12-19019 December 2023 Operator Licensing Examination Approval Davis Besse Nuclear Power Station, January 2024 L-23-260, Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station2023-12-0707 December 2023 Corrections to the 2022 Combined Annual Radiological Environmental Operating Report and Radioactive Effluent Release Report for the Davis-Besse Nuclear Power Station L-23-243, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23338A3172023-12-0606 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000346/2024001 IR 05000346/20234032023-11-0202 November 2023 Security Baseline Inspection Report 05000346/2023403 ML23293A0612023-11-0101 November 2023 Letter to the Honorable Marcy Kaptur, from Chair Hanson Responds to Letter Regarding Follow Up on Concerns Raised by Union Representatives During the June Visit to the Davis-Besse Nuclear Power Plant ML24045A0322023-10-26026 October 2023 L-23-221 Proposed Exam Submittal Cover Letter L-23-215, Changes to Emergency Plan2023-10-19019 October 2023 Changes to Emergency Plan ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments 2024-09-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 24, 2014 Mr. Raymond A Lieb, Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State Route 2 Oak Harbor, OH 43449-9760
SUBJECT:
NOTICE OF AVAILABILITY OF THE DRAFT PLANT-SPECIFIC SUPPLEMENT 52 TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS REGARDING DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1
Dear Mr. Lieb:
The U.S. Nuclear Regulatory Commission (NRC) staff has completed the draft plant-specific Supplement 52 to NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants (GElS)," regarding the renewal of operating license NPF-3 for an additional20 years of operation for Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse).
Enclosed is a copy of the draft supplement and the associated Federal Register Notice of Availability. This notice advises the public that the draft supplement is publicly available at the NRC Public Document Room or from the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The accession number for draft Supplement 52 to the GElS is ML14050A290. In addition, paper copies of the draft Supplement 52 are available to the public at the Ida Rupp Public Library, 310 Madison Street, Port Clinton, OH, 43452, and the Toledo-Lucas County Public Library, 325 North Michigan Street, Toledo, OH, 43452 As discussed in Chapter 9 of the draft supplement, the preliminary recommendation is that the adverse environmental impacts of license renewal for Davis-Besse are not great enough to deny the option of license renewal for energy-planning decisionmakers. This recommendation is based on: (1) the analysis and findings in the GElS; (2) the Environmental Report submitted by Ameren; (3) consultation with Federal, state, local, and tribal agencies; (4) the NRC staff's own independent review; and (5) the staff's consideration of public comments received during the seeping process.
Public meetings to discuss the findings of the draft SEIS will be held on Tuesday, March 25, 2014, at the Camp Perry Conference Center, 1000 Lawrence Road, Bldg. 600, Port Clinton, Ohio. 43453. The first session will convene at 2:00p.m. and will continue until4:00 p.m., as necessary. The second session will convene at 7:00p.m. and will continue until9:00 p.m., as necessary. An NRC meeting notice will be published to provide more details about those public meetings.
A separate Notice of Availability of the draft supplemental environmental impact statement will be placed in the Federal Register through the U.S. Environmental Protection Agency.
R. Lieb If you have any questions regarding this matter, please contact Elaine Keegan, Senior Project Manager for the environmental review of the Davis~ Besse license renewal application, by telephone at 301-415~8517 or by e~mail at Elaine.keegan@nrc.gov.
Sincerely, Brian 0. Wittick, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
As stated cc w/encl: Listserv
R. Lieb If you have any questions regarding this matter, please contact Elaine Keegan, Senior Project Manager for the environmental review of the Oavis-Besse license renewal application, by telephone at 301-415-8517 or by e-mail at Elaine.keegan@nrc.gov.
Sincerely, IRA!
Brian D. Wittick, Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-346
Enclosure:
As stated cc w/encl: Listserv DISTRIBUTION: See next page ADAMS Accession Nos. ML14050A523 (PKG)
ML14050A078 (LTR)
ML14050A521 (FRN)
OFFICE LA:DLR PM: RPB2:DLR BC:RPB2:DLR NAME YEdmonds EKeegan BWittick DATE 2/20/14 2/20/14 2/24/14 OFFICIAL RECORD
SUBJECT:
NOTICE OF AVAILABILITY OF THE DRAFT PLANT-SPECIFIC SUPPLEMENT 52 TO THE GENERIC ENVIRONMENTAL IMPACT STATEMENT FOR LICENSE RENEWAL OF NUCLEAR PLANTS REGARDING DAVIS-BESSE NUCLEAR POWER STATION, UNIT 1 DISTRIBUTION:
HARDCOPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRarb Resource RidsNrrDirRasb Resource RidsNrrDirRerb Resource RidsNrrDirRsrg Resource RidsNrrPMOavisBesse Resource EKeegan SCuadradoOeJesus BWittick YDiaz-Sanabria DWrona BHarris, OGC EBrown A Wang MMahoney DMclntyre, OPA VMitlyng,OPA TRiley,OCA EWilliamson, OGC RRihm, EDO JCameron, Rill
[7590-01 *PJ NUCLEAR REGULATORY COMMISSION
[Docket No. 50-346; NRC-2010-0298]
license Renewal Application for Davis-Besse Nuclear Power Station, Unit 1 AGENCY: Nuclear Regulatory Commission ACTION: Draft supplemental generic environmentaltmpact statement: issuance publtc meeting. and request for comment.
SUMMARY
- The US. Nuclear Regulatory Commission (NRC) is issuing for public comment a draft plant-specific Supplement 52 to the "Generic Environmental Impact Statement (GElS) for License Renewal of Nuclear Plants," NUREG-1437, regarding the renewal of operating license NPF-3 for an additional20 years of operation for Davis-Besse Nuclear Power Station, Unit 1 (Davis-Besse). Oavis-Besse is located in Ottawa County, Ohio. Possible alternatives to the proposed action (license renewal) include no action and reasonable alternative energy sources.
The NRC staff plans to hold two public meetings during the public comment period to present an overview of the draft plant-specific supplement to the GElS and to accept public comments on the document DATES: Submit comments by April21, 2014. Comments rece1ved afterth1s date will be considered, if it is practical to do so, but the NRC staff is able to ensure consideration only for comments received on or before this date.
ADDRESSES: You may submit comments by any of the following methods (unless this document describes a different method for submitting comments on a specific subject):
- Federal Rulemaking Web site: Go to http://www.requlations.gov and search for Docket ID NRC-201 0-0298. Address questions about NRC dockets to Carol Gallagher; telephone: 301*287-3422, e-mail. Carol Gallaqher@nrc.gov. For technical questions, contact the individual listed in the FOR FURTHER INFORMATION CONTACT section ofth1s document.
- Mail comments to: Cindy Bladey, Chief, Rules, Announcements, and Directives Branch, Office of Administration, Mail Stop: 3WFN-06-44M, U.S Nuclear Regulatory Commission, Washington. DC 20555-0001 For additional direction on accessing information and submitting comments, see "Accessing Information and Submitting Comments'* in the SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Ela1ne Keegan, Office of Nuclear Reactor RegUlation. US Nuclear Regulatory Commission. Washington, DC 20555-0001, telephone:
301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.
SUPPLEMENTARY INFORMATION:
I. Accessing Information and Submitting Comments.
A. Accessing Information Please refer to Docket 10 NRC~201 0-0298 when contacting the NRC about the availability of information regarding this document. You may access publicly-available information related to this document by any of the following methods.
- Federal Rulemaking Web site: Go to htto /iV'Nvw_reaulations aov and search for Docket ID NRC-2010-0298
- NRC's Agencywide Documents Access and Management System (ADAMS):
You may access publicly available documents online in the NRC Library at http://www.nrc.gov/reading-rm/adams.html To begin the search, select "ADAMS Public Documents" and then select "Begin Web-based ADAMS Search." For problems with ADAMS, please contact the NRC's Public Document Room reference staff at 1-800-397-4209. 301-415-4737. or by e-mail to pdr.resource@nrc.gov. The ADAMS accession number for each document referenced in this document (if that document is available in ADAMS) is provided the first time that a document is referenced. The draft plant-specific Supplement 52 to the GElS, is available in ADAMS under Accession No ML14050A290.
- NRC's PDR: You may examine and purchase copies of public documents at the NRC's PDR, Room 01-F21, One White Flint North. 11555 Rockville Pike, Rockville, Maryland 20852 In addition, paper copies of the draft plant specific Supplement 52 are available to the public at the Ida Rupp Public Library, 310 Madison Street, Port Clinton, OH 43452, and the Toledo-Lucas County Public Library, 325 North Michigan Street, Toledo, OH, 43452.
8_ Submitting Comments Please include Docket 10 NRC-2010-0298 in the subject line of your comment submission, in order to ensure that the NRC is able to make your comment submission available to the public in this docket.
The NRC cautions you not to include identifymg or contact information that you do not want to be publicly disclosed in your comment submission_ The NRC will post all comment submissions at htto'//www.regulations.aov as well as enter the comment submissions into ADAMS The NRC does not routinely edit comment submissions to remove identifying or contact Information If you are requesting or aggregating comments from other persons for submission to the NRC, then you should inform those persons not to include identifying or contact information that they do not want to be publicly disclosed in their comment submission_ Your request should state that the NRC does not routinely edit comment submissions to remove such information before making the comment submissions available to the public or entering the comment submissions into ADAMS II. Discussion.
The NRC is issuing for public comment a draft plant-specific Supplement 52 to the GElS, regarding the renewal of operat1ng license NPF-3 for an additional 20 years of operation for Oavis-Besse_ Supplement 52 to the GElS includes the preliminary analysis that evaluaies the environmental impacts of the proposed action and alternatives to the proposed a::::tion. The NRC's preliminary recommendation is that the adverse environmental impacts of license
renewal for Davis-Besse are not great enough to deny the option of license renewal for energy planning decisionmakers.
Ill. Public Meetings.
The NRC staff will hold public meetings prior to the close of the public comment period to present an overview of the draft plant-specific supplement to the GElS and to accept public comment on the document. Two meettngs will be held at the Camp Perry Conference Center, 1000 Lawrence Road. Bldg 600, Port Clinton, Ohio 43453 on Tuesday, March 25. 2014_ The first session will convene at 2:00p.m. and will continue until 4:00p.m , as necessary. The second session will convene at 7 00 p.m and will continue until g-oo p.m as necessary. The meetings will be transcribed and will include: (1) a presentation of the contents of the draft plant-specific supplement to the GElS, and (2) the opportunity for interested government agencies. organizations, and individuals to provide comments on the draft report. Additionally, the NRC staff will host informal discussions one hour prior to the start of each session at the
- same location. No comments on the draft supplement to the GElS will be accepted during the informal discussions. To be considered, comments must be provided either at the transcribed public meeting or in writing. Persons may pre-register to attend or present oral comments at the meeting by contacting Elaine Keegan, the NRC Environmental Project Manager. at 1-800-368-5642 extension 8517. or by e-mail at Elaine.KeeaaniWnrc.aov no later than Wednesday, March 19. 2014. Members of the public may also reg1ster to provide oral comments within 15 minutes of the start of each session Individual oral comments may be lim1ted by the time available. depending on the number of persons who register. If special equipment or accommodations are needed to attend or present Information at the public meeting, the need
should be brought to Ms. Keegan's attention no later than Monday, March 10, 2014, to provide the NRC staff adequate notice to determine whether the request can be accommodated.
Dated at Rockville, Maryland, this 24th day of February, 2014.
For the Nuclear Regulatory Commission.
(/~ c. c:..."-"'-:-' * --
Brian D Wittick. Chief Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation