Tennessee Valley Authority, P.O. Box 2000 Spring City, Tennessee 37381 January 10, 2014 ATTN : Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 10 CFR 50.54(q)(5) 10 CFR 50, Appendix E,Section V Watts Bar Nuclear Plant, Unit 1 and Unit 2 Facility Operating License No. NPF-90 NRC Docket No. 50-390, 50-391
Subject:
Emergency Plan Implementing Procedure Revision In accordance with the requirements of 10 CFR 50.54(q)(5) and 10 CFR Part 50, Appendix E, Section V, this submittal provides revisions to the Watts Bar Nuclear Plant (WBN) Emergency Plan Implementing Procedures (EPIPs). The attachment to this submittal provides a listing of each EPIP by title, the corresponding revision number and the date of effectiveness.
As noted on the attachment, the EPIP revisions have not been submitted within 30 days as specified by 10 CFR 50. The Tennessee Valley Authority (TVA) is investigating the cause of the internal processing error that led to the untimely submittal and has entered the condition into the corrective action program.
TVA has completed and retained analyses demonstrating that the changes do not reduce the effectiveness of the emergency plan and the plan, as changed, continues to meet the requirements in 10 CFR 50 appendix E and the planning standards of
§ 50.47(b).
In accordance with 10 CFR 50.4(b), copies of this submittal are being forwarded to the NRC Region IV Administrator and the resident inspector.
U.S. Nuclear Regulatory Commission January 10, 2014 Page 2 There are no commitments in this letter. Should you have questions regarding this submittal, please contact Thomas Detchemendy, Emergency Preparedness Manager at (423) 365-3232.
Respectfully,
~f~;
Timothy~. CleaJ Site Vice President Watts Bar Nuclear Plant
Attachment:
EPIP Revision List
Enclosure:
Revised Emergency Plan Implementing Procedures (EPIP) 1 through 8 and 10 through 17 cc (Enclosure):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Watts Bar Nuclear Plant Unit 1 NRC Senior Resident Inspector - Watts Bar Nuclear Plant Unit 2 NRR Project Manager - Watts Bar Nuclear Plant Unit 1
Attachment Emergency Plan Implementing Procedure (EPIP) Revision EPIP Revision Title Effective Date 1
040 Emergency Plan Classification Logic 11/26/2013 2
032 Notification of Unusual Event 11/26/2013 3
038 Alert 11/26/2013 4
036 Site Area Emergency 11/26/2013 5
042 General Emergency 11/26/2013 6
044 Activation and Operation of the 09/27/2013 Technical Support Center (TSC) 7 035 Activation and Operation of the 09/27/2013 Operations Support Center (OSC) 8 028 Personnel Accountability and 09/23/2013 Evacuation 10 026 Medical Emergency Response 09/23/2013 11 017 Security and Access Control 09/23/2013 12 032 Emergency Equipment and Supplies 09/23/2013 13 020 Initial Dose Assessment for 09/20/2013 Radiological Emergencies 14 023 Radiological Control Response 09/23/2013 15 016 Emergency Exposure Guidelines 09/23/2013 16 023 Termination of the Emergency and 09/27/2013 Recovery 17 003 Fire Emergency Procedure 09/23/2013