IR 05000275/2013201

From kanterella
(Redirected from ML14009A294)
Jump to navigation Jump to search
IR 05000274-13-201 and 05000323-13-201, on 12/12/2013, Diablo Canyon Power Plant - NRC Security Inspection Report
ML14009A294
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 02/04/2014
From: Johnson C R
NRC/NSIR/DSO/DDSO/SPEB
To: Johnson R C
Pacific Gas & Electric Co
Cornelius, David 301-287-3623
References
IR-13-201
Download: ML14009A294 (3)


Text

February 4, 2014

Mr. Barry S. Allen, Site Vice President Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 3, Mail Station 104/6/601 Avila Beach, CA 93424

SUBJECT: DIABLO CANYON POWER PLANT - NRC SECURITY INSPECTION REPORT 05000275/2013201 AND 05000323/2013201

Dear Mr. Allen:

On December 12, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Diablo Canyon Power Plant. The inspection covered one or more of the key attributes of the security cornerstone of the NRC's Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed via telephone on December 30, 2013, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commission's rules and regulations and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel. One NRC-identified finding of very low security significance (i.e., Green as determined by the Physical Protection Significance Determination Process) was identified during this inspection. The deficiency was promptly corrected or compensated for, and the plant was in compliance with applicable physical protection and security requirements within the scope of this inspection before the inspectors left the site. This finding was determined to involve violations of NRC requirements. However, the NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy. If you contest the NCV in the enclosed report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Nuclear Security and Incident Response (NSIR); and the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Diablo Canyon Power Plant. One cross-cutting aspect was assigned to this finding, in the area of Human Performance, associated with Work Practices [(H.4(a). If you disagree with the cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Director, NSIR, and to the Branch Chief, Performance Evaluation Branch, NSIR. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However, the material enclosed herewith contains Safeguards Information as defined by 10 CFR 73.21 and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRC's ADAMS. If you choose to provide a response and Safeguards Information is necessary to provide an acceptable response, please provide the level of protection described in 10 CFR 73.21. Otherwise, if security-related information is necessary to provide an acceptable response, please mark your entire response "Security-Related Information - Withhold from Public Disclosure under 10 CFR 2.390" in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Sincerely,/RA/ Robert C. Johnson, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket Nos. 05000275, 05000323 License Nos. DPR-80, DPR-82 Nonpublic

Enclosure:

Inspection Report 05000275/2013201 and 05000323/2013201

w/Attachment:

Supplemental Information cc w/encl: M. Priebe, Manager, Security Director