Submittal of Developmental Revision H of the Technical Specification and Technical Specification Bases
ML13357A048
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 12/12/2013
From: Arent G
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML13357A047 List:
References
Download: ML13357A048 (3)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 December 12, 2013 10 CFR 50.36 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

Watts Bar Nuclear Plant Unit 2 - Submittal of Developmental Revision H of the Unit 2 Technical Specification and Technical Specification Bases

References:

1. TVA Letter to NRC dated September 26, 2013, "Watts Bar Nuclear Plant (WBN) Unit 2 - Submittal of Revised Section 4.3.1, "Criticality" Developmental Revision G of the Unit 2 Technical Specification (TS)"
2. TVA Letter to NRC dated June 13, 2013, "Watts Bar Nuclear Plant (WBN) Unit 2 - Submittal of Three Revised Specifications from Developmental Revision G of the Unit 2 Technical Specifications (TS)"
3. TVA Letter to NRC dated August 27, 2012, "Watts Bar Nuclear Plant (WBN) Unit 2 - Update to Technical Specification (TS) Table 3.3.3-1 and Technical Specification Bases (TSBs) 3.3.3" This letter provides a complete version of Developmental Revision H of the Watts Bar Nuclear Plant (WBN) Unit 2 Technical Specifications (TS) and Technical Specification Bases (TSB). Included in Developmental Revision H are changes that have been submitted by the referenced correspondence, changes to incorporate recently approved WBN Unit 1 Amendments and recently docketed WBN Unit 1 amendment requests. Three additional changes are included that have not been the subject of a prior submittal.

U.S. Nuclear Regulatory Commission Page 2 December 12, 2013 The enclosure provides a description of each of the changes, and of changes that have not been previously submitted the rationale for making the change. The changes support two unit operation or are necessary to provide consistency with the WBN Unit 1 TS. Attachment 1 to the enclosure provides the original WBN Unit 2 TS pages marked-up to show the changes. Attachment 2 to the enclosure provides the original WBN Unit 2 TS Bases pages marked-up to show the changes. Attachment 3 to the enclosure provides a complete copy of the WBN Unit 2 TS and TSB Developmental Revision H is provided on optical media.

There are no new commitments in this letter. If you have any questions, please contact me at (423) 365-2004.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 12t' day of December, 2013.

Respectfully, 4GoroZLrent Director, Watts Bar Licensing Nuclear Construction

Enclosure:

Synopsis of Revisions Included in Watts Bar Nuclear Plant Unit 2 Developmental Revision H of the Technical Specifications and Technical Specification Bases Attachments:

1.

TS Changes (Mark-Up) for WBN Unit 2

2.

TS Bases Changes (Mark-Up) for WBN Unit 2

3.

WBN Unit 2 TS and TSB Developmental Revision H

U.S. Nuclear Regulatory Commission Page 3 December 12, 2013 cc (Enclosure):

U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381