E-mail from J. Whited to D. Filchner Sending RAIs for 4RR ISI Relief Requests
ML13339A894
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 12/05/2013
From: Jeffrey Whited
Plant Licensing Branch 1
To: Filchner D
Susquehanna
Whited J
References
Download: ML13339A894 (1)


Text

Whited, Jeffrey From: Whited, Jeffrey Sent: Thursday, December 05, 2013 3:14 PM To: Filchner, Duane L (dlfilchner@pplweb.com)

Cc: Jennings, Jason (JJennings@pplweb.com)

Subject:

RE: DRAFT-RAIs to PPL REQUEST TO CHANGE TS SR 3.5.1.12 Attachments: DRAFT 4RR ISI RAIs.pdf Mr. Filchner, By letter dated August 30, 2013, (Agencywide Documents Access and Management System Accession No. ML13247A167) PPL Susquehanna, LLC (PPL, the licensee), submitted a set of Relief Requests from the American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI for the Fourth Ten-Year Inservice Inspection (ISI) Interval at Susquehanna Steam Electric Station (SSES) Units 1 and 2.

The NRC staff has reviewed the information submitted by the licensee, and based on this review, determined additional information is required to complete the assessment of the submitted information. Please find attached Draft Requests For Additional Information. They are being sent to you to ensure that the questions are understandable, the regulatory basis for the questions are clear, and to determine if the information was previously docketed. Please respond to me by Monday, December 16, 2013, and notify me if you desire to hold a teleconference to discuss the question. The NRC staff will request a response to the RAIs within 30 days of the formal NRC RAI transmittal letter.

Thank you, Jeffrey Whited Project ManagerBeaver Valley and Susquehanna Plant Licensing Branch I2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission (301)4154090 jeffrey.whited@nrc.gov 1