Forwards Public Version of Revised Emergency Plan Implementing Procedures,Including Procedures EPIP SO1-VIII-1 Re Recognition & Classification of Emergencies & EPIP SO123-VIII-10 Re Emergency Coordinator Duties
ML13333B872
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 03/17/1983
From: Baskin K
Southern California Edison Co
To: Eisenhut D
Office of Nuclear Reactor Regulation
Shared Package
ML13333B871 List:
References
NUDOCS 8303300232
Download: ML13333B872 (1)


Text

Southern Ca/ifornia Edison Company P. 0. BOX 800 2244WALNUT GROVE AVENUE ROSEMEAD. CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING, (213) 572-1401 SAFETY, AND LICENSING March 17, 1983 Director, Office of Nuclear Reactor Regulation Attention:

Mr. Darrell G. Eisenhut, Director U. S. Nuclear Regulatory Commission Washington, D.C.

20555 Gentlemen:

Subject:

Docket Nos. 50-206, 50-361 and 50-362 San Onofre Nuclear Generating Station Units 1, 2 and 3 Provided as an enclosure are two copies of newly revised Emergency Planning procedures for San Onofre Nuclear.Generating Station, Units 2 and 3.

As you know Appendix E to 10 CFR 50 requires that changes to maintain the procedures up to date be provided to the NRC.

Enclosed for your information is the index of Emergency Procedures which shows the current status of each procedure.

If you have any questions regarding these procedures, please let me know.

Very truly yours, Enclosures cc:

R. H. Engelken, Regional Administrator Office of Inspection and Enforcement Region V f

303300232 830325 PDR ADOCK 05000206 F