Notification of 820520 Meeting W/Util in Bethesda,Md to Discuss Seismic Design Adequacy
ML13333B693
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 05/11/1982
From: Paulson W
Office of Nuclear Reactor Regulation
To: Crutchfield D
Office of Nuclear Reactor Regulation
Shared Package
ML13333B694 List:
References
TASK-03-06, TASK-3-6, TASK-RR NUDOCS 8205140168
Download: ML13333B693 (3)


Text

May 11, 1982 Docket No. 50-206 RE Cf VIEDK 2MAY 123 1982o.

MEMORANDUM FOR:

Dennis M. Crutchfield, Chief usUmanamarm Operating Reactors Branch #5, DL 1ma FROM:

Walter A. Paulson, Project Manager Operating Reactors Branch #5, DL

SUBJECT:

FORTHCOMING MEETING WITH SOUTNERN CALIFORNIA EDISON COMPANY -

SAN ONOFRE UNIT NO. 1 Date & Time:

Thursday May 20, 1982 1:00 PM Location:

Room P-118 Phillips Building 7920 Norfolk Avenue Bethesda, Maryland

Purpose:

To discuss San Onofre Unit No. 1 seismic design adequacy (see attached agenda).

Participants:

SCE K. Baskin, et al.

NRC W. Paulson, D. Crutchfield, W. Russell, G. Lainas, R. Purple, D. Eisenhut, E. Case, H. Denton, J. Knight, F. Schauer, R. Vollmer, S. Burns, R. Hoefling and L. Chandler Original signed by Walter A. Paulson, Project Manager Operating Reactors Branch #5 Division of Licensing DL' 0

  1. 5 OFFICE SURNAME.

NRC DATF E

.0 O FFICIA L R E C O R D C..P Y NRC FORM 318 (10-80) NRCM 0240 OFFICIAL RE CO RD CO PY USGPO: 1981-335-960

MEETING AGENDA SAN ONOFRE UNIT 1 SEISMIC DESIGN ADEQUACY

1.

Confirmation and demonstration by the licensee that the original plant design and construction met the licensing basis described in the FSAR.

2. Seismic capacity of the Reactor Coolant Pressure Boundry (RCPB) and systems and equipment necessary for safe shutdown (hot shutdown).

a.. Implication of lack of system availability following a postulated SSE (0.5g Housner) based upon the licensee's reanalysis (0.67g Housner) and the licensee's structural integrity criteria (April 30, 1982 submittal),

b. Non-conservatisms in the licensee's structural integrity criteria which when considered would identify additional system or component availability concerns,
c. Identification of potentially serious deficiencies in the methods of reanalysis of RCPB branch lines which when considered could identify additional system availability concerns.
3.

Implication of Item 2 above for accident mitigation systems.

4. Discussion of licensee's proposed program for corrective actions to be implemented prior to startup.

CVk R E UNITEDSTATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 May 11, 1982 Docket No. 50-206 MEMORANDUM FOR:

Dennis M. Crutchfield, Chief Operating Reactors Branch #5, DL FROM:

Walter A. Paulson, Project Manager Operating Reactors Branch #5, DL

SUBJECT:

FORTHCOMING MEETING WITH SOUTHERN CALIFORNIA EDISON COMPANY -

SAN ONOFRE UNIT NO. 1 Date & Time:

Thursday May 20, 1982 1:00 PM Location:

Room P-118 Phillips Building 7920 Norfolk Avenue Bethesda, Maryland

Purpose:

To discuss San Onofre Unit No. 1 seismic design adequacy (see attached agenda).

Participants:

SCE K. Baskin, et al.

NRC W. Paulson, D. Crutchfield, W. Russell, G. Lainas, R. Purple, D. Eisenhut, E. Case, H. Denton, J. Knight, F. Schauer, R. Vollmer, S. Burns, R. Hoefling and L. Chandler Walter A..Paulson, Project Manager Operating Reactors Branch #5 Division of Licensing