Text
REGULATOROINFORMATION DISTRIBUTION *TEM (RIDS)
ACCESSION NBR:8510100083 DOCDATE: 85/10/07 NOTARIZED: YES DOCKET #
FACIL:50-206 San Onofre Nuclear Station, Unit 1, Southern Californ 05000206 AUTHNAME AUTHOR AFFILIATION
- MEDFORDM, Southern California Edison Co.
RECIP.NAME RECIPIENT AFFILIATION Office of Nuclear Reactor Regulation, Director
SUBJECT:
Withdraws request as part of Proposed Change 149 to License DPR-13,removing Valves CV-948 & 949 from Tech Spec Table 3.6.2-1, "Remote Manual (RM) or Automatic Contanment Isolation Valve Summary." Revised table encl, DISTRIBUTION CODE: A001D COPIES RECEIVED:LTR.
ENCL SIZE: --- --
TITLE: OR Submittal: General Distribution NOTES:NRR/DL/SEP Icy, 05000206 OL:03/27/67 RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL NRR 0885 BC 01 7
7 INTERNAL: ACRS 09 6
6 ADM/LFMB 1
0 ELD/HDS2 1
0 NRR/DE/MTEB 1
1 NRR/DL DIR 1
1 NRR/DL/ORAB 1
0 NRR/DL/TSRG 1
1 METB 1
1 NRR/DSI/RAB 1
1 FI 04 1
1 RGN5 1
1 EXTERNAL: 24X 1
1 EG&G BRUSKES 1
1 LPDR 03 1
1 NRC POR 02 1
1 NSIC 05 1
1 NOTES:
1 1
TOTAL NUMBER OF COPIES REQUIRED:
LTTR 29 ENCL 26
Southern California Edison Company C
P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD. CALIFORNIA 91770 M. 0. MEDFORD TELEPHONE MANAGER, NUCLEAR LICENSING (818) 302-1749 October 7, 1985 Director, Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Gentlemen:
Subject:
Docket No. 50-206 Revision to Amendment Application No. 130 San Onofre Nuclear Generating Station Unit 1
Reference:
May 9, 1985 letter from K. P. Baskin, SCE, to H. R. Denton, NRC The referenced letter provided Proposed Change No. 149 (submitted by Amendment Application No. 130) which requests to revise Technical Specification 3.6.2, "Containment Isolation Valves" and associated Table 3.6.2-1, "Power Operated or Automatic Containment Isolation Valve Summary."
As part of the requested revisions, two containment isolation valves currently listed in Table 3.6.2 were to be removed.
These valves, CV-948 and 949, provide containment isolation for the Pressurizer Relief Tank Gas Sample penetration. However, this penetration was removed from service by installation of a pipe cap inside containment to provide containment integrity, and a second cap outside of containment. Therefore, CV-948 and 949 no longer provide a containment isolation function and were to be removed from Table 3.6.2-1.
Subsequent to submittal of Proposed Change No. 149, it has been determined that the Pressurizer Relief Tank Gas Sample penetration should be returned to service. The work necessary to return this line to service will be conducted during the upcoming refueling outage. It is therefore our desire to withdraw our request as part of Proposed Change No. 149 to remove these valves from Table 3.6.2-1.
A revision to Table 3.6.2-1 is provided as an enclosure.
If you have any questions or desire additional information, please let me know.
Very truly yours, 510 1O00O83 O2 6
'2 D0206 PDR At)0CK
.pD P
MJT:5100F cc:
- 3. 0. Ward, California Department of Health Services 0 p
- 3. A. Zwetzig, USNRC Region V
TABLE 3.6.2-1 REMOTE MANUAL (RM) OR AUTOMATIC CONTAINMENT ISOLATION VALVE
SUMMARY
DESCRIPTION INSIDE SPHERE OUTSIDE SPHERE
- 1. Sphere Sump Discharge CV-102 CV-103
- 2. RCS Dr Tk Discharge CV-104 CV-105
- 3. RCS Dr Tk Vent CV-106 CV-107
- 5. ORMS 1211/1212 Sphere CV-147 SV-1212-9 Sample Supply
- 6. ORMS 1211/1212 Sphere CV-146 SV-1212-8 Sample Return
- 7. A Stm. Gen. Stm. Sample SV-119
- 8. B Stm. Gen. Stm. Sample SV-120
- 9. C Stm. Gen. Stm. Sample SV-121
- 10. A Stm. Gen. Blowdown Sample SV-123
- 11.
B Stm. Gen. Blowdown Sample SV-122
- 12. C Stm. Gen. Blowdown Sample SV-124
- 13.
Service Water to Sphere CV-537 CV-115
- 14. Service Air to Sphere Check Valve SV-125
- 15.
SI Loop C Vent SV-702B SV-702A
- 16.
SI Loop B Vent SV-7020 SV-702C
- 17.
H2 Calibration Gas SV-3004 SV-2004
- 18.
RC Loop Sample (CV-955, CV-956, CV-957 CV-962) RM SV-3302
- 19.
Pressurizer Sample (CV-951, CV-953) RM CV-992
- 20.
Sphere Purge Air Supply*
POV-9
- 21.
Sphere Purge Air Outlet*
POV-10
- 22.
Sphere Equalizing/Vent CV-116 CV-10 Inst. Air Vent CV-40
- 23.
Primary Makeup to PRT CV-533 CV-534
- 24.
Cont. Cooling Out CV-515 RM
- 25.
Cont. Cooling In CV-516 RM
- 26.
N2 Supply to PORV Check Valve CV-532 RM
- 27.
- 28.
Seal Water Return CV-527 RM CV-528 RM
- 29.
RC Loop Sample Return Check Valve SV-3303
- 30.
PRT Gas Sample CV-948 RM CV-949 Manual valves CVS-301 and CVS-313 of the Sphere Purge Air Supply and Air Outlet lines, respectively, shall be locked closed during MODES 1, 2, 3, and 4.