Southern California Edison Company P. O BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 F. R. NANDY TELEPHONE MANAGER OF NUCLEAR LICENSING January 25, 1989 (818) 302-1896 U. S. Nuclear Regulatory Commission Attention:
Document Control Desk Washington, D.C. 20555 Gentlemen:
Subject:
Docket Nos. 50-206, 50-361 and 50-362 Response to Generic Letter 88-14, "Instrument Air" San Onofre Nuclear Generating Station Units 1, 2 and 3 NRC Generic Letter:88-14, "Instrument Air System Problems Affecting Safety-Related Equipment" issued August 8, 1988, requested licensees to perform a variety of verification activities on plant air systems. This generic letter also requested a response by February 4, 1989. The purpose of this letter is to inform the NRC that our response to Generic Letter 88-14 will be delayed until March 17, 1989. This delay is due to the unavailability of resources which were required to support the ongoing refueling activities.
If you have any questions, please contact me.
Very truly ou cc: 3. B. Martin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3 8902080359 890125 PDR ADOCK 05000206 PNU