Southern California Edison Company P.

. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 M. 0. MEDFORD TELEPHONE MANAGER OF NUCLEAR ENGINEERING (818) 302-1749 AND LICENSING June 7, 1988 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Licensing Actions San Onofre Nuclear Generating Station Unit 1 In order to ensure a common understanding of pending licensing actions requested by SCE, a prioritized list of significant licensing actions for San Onofre Unit 1 has been prepared. This list is provided as an enclosure to this letter.

The enclosed list will be updated monthly in order to reflect changes in priorities and progress on the various issues. It is intended that this list be limited to approximately the ten most significant issues and not be all inclusive of either SCE or NRC ongoing activities.

If you have any questions or wish to discuss the enclosed list please call me.

Very truly yours, Enclosure cc: 3. B. Martin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3 8806160094 880607 PDR ADOCK 05000206 p

rn -. L Prioritized List of Significant San Onofre Unit 1 Licensing Actions May 1988 SCE Submittal Federal Register Approval Required Issue Dates Status Date Remarks

1. Environmental 5/27/88 None Required Review Prior to Qualification; Startup approval for startup
2. Partial Exemption 2/8/88 None Required NA1 from NRC fees
3. Nuclear 4/15/88 Noticed 5/11/88 9/1/88*

Instrumentation System Tech Specs (Am't. 150)

4. Spent Fuel 4/28/88 Notice Required ASAP prior to Responses to Transshipment 9/1/88 NRC questions License Amendment to be (Am't. 148) submitted 6/8/88
5. Administrative Tech 8/27/87 Notice Required NA Specs including QA Audits (Am't 145)
6. Control Rod 5/26/88 Notice Required 12/l/88**

Insertion Limits (Am't. 151)

7. Fire Protection 12/17/85 Notice Required NA Based on mtg.

Tech Specs 5/19/86 on 3/22/88 (Am'ts 120 & 136) revised Tech Spec to be submitted 6/24/88

8. Steam Generator 3/10/88 Notice Required 12/l/88**

Interim Tech Tube Plugging 3/22/88 Spec issued Criteria (F*) Tech 3/29/88 5/6/88 Spec --

long term (Am't 149)

  • Prior to Cycle 10 refueling outage
  • Prior to end of Cycle 10 refueling outage
1. NA indicates plant operation is not contingent on approval.

0941P