Remits Fee for NRC Approval of Rev 1 to BN-TOP-1 for Use as Basis for Performance of Short Duration Type a Containment Leak Rate Test,Per 870804 Request
ML13330B244
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 08/24/1987
From: Medford M
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
NUDOCS 8708310003
Download: ML13330B244 (1)


Text

Southern California Edison Company P. 0.

BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD. CALIFORNIA 91770 M.O.MEDFORD TELEPHONE MANAGER OF NUCLEAR ENGINEERING (818) 302-1749 AND LICENSING August 24, 1987 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket Nos. 50-206, 50-361 and 50-362 San Onofre Nuclear Generating Station Units 1, 2, and 3 By letter dated June 9, 1987, SCE requested NRC approval of Bechtel Topical Report BN-TOP-1, Revision 1, for use at San Onofre Units 1, 2 and 3 as the basis for the performance of a short duration Type A containment leak rate test.

The NRC approved this report for use at San Onofre by letter dated July 2, 1987.

Following NRC approval, SCE was notified by letter dated August 4, 1987 that the required application fee of-$150.00 pursuant to 10 CFR 170 had not been submitted. Consequently, the purpose of this letter is to forward the application fee of $150.00, required by 10 CFR 170, to the NRC.

If you have any questions, please contact me.

Very truly yours, Enclosure cc: R. F. Dudley, NRR Project Manager, San Onofre Unit 1 H. Rood, NRR Senior Project Manager, San Onofre Units 2 and 3 J. B. Martin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3 R. M. Diggs, Facilities Program Coordinator, Licensee Fee Management Branch 6706310003 870824 PDR ADOCK 05o00206 P