Requests NRC Approval of Rev 1 to Bechtel Rept BN-TOP-1, Testing Criteria for Integrated Leakage Rate Testing of Primary Containment Structures for Nuclear Power Plants, for Use as Basis for Short Duration Type a Test
ML13330B220
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 06/09/1987
From: Medford M
SOUTHERN CALIFORNIA EDISON CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
TAC-65544, TAC-65545, TAC-65546, NUDOCS 8706160543
Download: ML13330B220 (2)


Text

Southern California Edison Company P. 0.

BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 M.O.MEDFORD June 9, 1987 TELEPHONE MANAGER OF NUCLEAR ENGINEERING (818) 302-1749 AND LICENSING U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket Nos. 50-206, 50-361 and 50-362 San Onofre Nuclear Generating Station Units 1, 2 and 3

References:

1. AEC to Bechtel Corporation letter dated January 15, 1973
2. NRC to TVA letter dated January 7, 1983 The purpose of this letter is to request NRC approval of Bechtel Topical Report BN-TOP-1, Rev. 1, 1972 (Enclosure I) for use at San Onofre Units 1, 2 and 3 as the basis for the performance of a short duration Type A containment leak rate test. Appendix 3 to 10 CFR 50 endorses ANSI N45.4 (Enclosure II) as the NRC acceptable test criteria for the performance of Type A containment leak rate testing. This ANSI standard states:

"If it can be demonstrated to the satisfaction of those responsible for the acceptance of the containment structure that the leakage rate can be accurately determined during a shorter test period, the agreed-upon shorter period may be used."

(ANSI N45.4-1972, Section 7.6)

The Atomic Energy Commission approved Bechtel Topical BN-TOP-1, Rev. 1 for referencing in Safety Analysis Reports (Reference 1) and the NRC subsequently approved this report for use as the Type A test acceptance criteria for Tennessee Valley Authority's Sequoyah Nuclear Plant (Reference 2).

SCE intends to use BN-TOP-1, Rev. I as the basis for a short duration Type A test during the upcoming San Onofre Unit 2 refueling outage scheduled to begin in August 1987. SCE requests specific NRC approval of BN-TOP-1, Rev. 1 for use at San Onofre Units 1, 2 and 3 prior to the start of the Unit 2 outage.

If you have any questions, please contact me.

Very truly yours, 8706160543 870609 T(

PDR ADOCK 05000206 P

PDRL Enclosures cc: R. F. Dudley, NRR Project Manager, San Onofre Unit 1 H. Rood, NRR Senior Project Manager, San Onofre Units 2 and 3 J. B. Martin, Regional Administrator, NRC Region V F. R. Huey, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3

ENCLOSURE I