Notifies That Evaluation of Postulated Water Hammers Will Be Completed by 801030 Due to Delay in Receipt of Info from Westinghouse
ML13330A129
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 10/02/1980
From: Baskin K
Southern California Edison Co
To: Crutchfield D
Office of Nuclear Reactor Regulation
References
REF-GTECI-A-01, REF-GTECI-PI, TASK-05-13, TASK-5-13, TASK-A-01, TASK-A-1, TASK-OR, TASK-RR NUDOCS 8010070462
Download: ML13330A129 (1)


Text

Southern California Edison Company P. 0. BOX 800 2244WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING, (213) 572.1401 SAFETY, AND LICENSING October 2, 1980 Director of Nuclear Reactor Regulation Attention: D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Steam Generator Water Hammer San Onofre Nuclear Generating Station Unit 1 By letter dated April 11, 1980, we indicated that an evaluation of postulated water hammers at San Onofre Unit I would be completed by September 30, 1980. Due to a delay in receipt of this information from Westinghouse, the evaluation will not be available until October 30, 1980.

If you have any questions regarding this matter, please let me know.

Very truly yours, 8010070 2