301 Initial Exam Draft Administrative JPMs
ML13325A951
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 11/18/2013
From:
NRC/RGN-II
To:
Duke Energy Progress
References
50-400/13-301
Download: ML13325A951 (66)


Text

Appendix C Job Performance Measure Form ES-C-i Worksheet Facility: Shearon Harris Task No.: 01 5004H20i Task

Title:

Perform the Quadrant Power Tilt JPM No.: 2013 NRC Exam Ratio Surveillance Admin JPM RD A2 K/A

Reference:

G2.2.i2 RD 3.7 SRO 4.1 Alternate Path: No Examinee: NRC Examiner:

Facility Evaluator: Date:

Method of testing:

Simulated Performance: Actual Performance: X Classroom X Simulator Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.

. The plant is operating at 90% power when a rod in Control Bank A (P-b) dropped.

. The crew is performing AOP-OOi, MALFUNCTION OF ROD Initial Conditions: CONTROL AND INDICATION SYSTEM.

. There are NO deficiency tags on PR NIs.

. ERFIS points ANM9112U and ANM9113L have a BAD quality code. HNP IT has been notified and they are evaluating the ERFIS points.

The CRS has directed you to perform a manual QPTR LAW OST-1039, CALCULATION OF QPTR. The Power Range NIS indications are Initiating Cue: provided.

For the purposes of the examination, there will be no independent verification. Show values of your work.

2013 NRC Exam Admin JPM RD A2 Rev 2 1

Appendix C Job Performance Measure Form ES-C-i Worksheet Task Standard: Calculations within required band.

Correct Tech Spec actions are identified.

Required Materials: Calculator General

References:

OST-1 039, CALCULATION OF QPTR, Revision 16 Technical Specifications Handouts:

  • OST-1 039
  • Power Range NI Current and Voltage Set point Table
  • Technical Specifications Time Critical Task: No Validation Time: 10 minutes Critical Step Justification Must accurately determine the correct calculation based on collecting Step 11 and inputting either provided data or visual inspection data. The calculation will yield an unsatisfactory QPTR.

Step 14 Must identify that the QPTR upper is outside the band which will make this overall results unsatisfactory.

Step 15 Must unsatisfactory that the QPTR is greater than 1.02 (which is a Tech Spec limit).

Step 19 Must correctly identify through documentation that the QPTR limits are exceeded.

2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 3 of 15 Form ES-C-i PERFORMANCE INFORMATION Start Time:

Performance Step: I Obtain procedure.

Standard: Reviews procedure.

Evaluator Cue: Provide OST-1039.

Evaluator Note: A KEY is provided for your use on JPM prior to candidate pages.

Comment:

NOTE: The NI curve numbers provided in this JPM are Evaluator Note: numbers from the 2013 NRC Exam Frozen Procedures Curve Book folder.

Precaution and Limitation 4.0.1 has guidance if performing this Procedure Note: OST with one Power Range Channel inoperable.

Performance Step: 2 Completes Prerequisites section:

  • Verify instrumentation needed for the performance of this test is free of deficiencies that affect instrument indication.
  • Verify the most recent Curve F-X-8 is used in the performance of this procedure. (Reference 2.1.1 and 2.1.2)
  • OBTAIN CRS permission to perform this OST.

Standard:

  • Logs F-18-8 revision number: 6
  • Initials/signs all blocks Comment:

V Denotes Critical Steps 2013 NRC Exam Admin JPM RD A2 Rev. 2

Appendix C Page 4 of 15 Form ES-C-i PERFORMANCE INFORMATION Performance Step: 3

  • IF Quadrant Power Tilt Ratio Calculation Computer Program is used, THEN PERFORM the following:
  • MARK Step 7.0.2 N/A.
  • MARK Section 7.2 N/A.
  • PERFORM Section 7.1.
  • IF manual calculation of the Quadrant Power Tilt Ratio is used, THEN PERFORM the following:
  • MARK Section 7.1 N/A.
  • PERFORM Section 7.2.

Standard:

  • Marks Section 7.1 N/A
  • Proceeds to Section 7.2 Comment:

OST-1 039 Section 7.2 Note prior to step I Performance Step: 4 NOTE: The detector current meters on each power range channel drawer are designated as left-upper, right-lower.

Standard: Reads and circle slashes note Comment:

OST-I 039 Section 7.2, Step I Performance Step: 5 Prior to reading the value of detector current, VERIFY the meter range/rate switch is in the 400 iAISLOW position.

Standard: Prior to reading the value of detector current, VERIFIES the Meter Range/Rate switch is in the 400 pA/SLOW position.

Evaluator Note: This information is on the JPM Cue Sheet Comment:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 5 of 15 Form ES-C-i PERFORMANCE INFORMATION OST-1 039 Section 7.2, Step 2 Performance Step: 6 RECORD on Attachment 2, in column A, the upper and lower detector currents from all operable power range channels as read on the Nuclear Instrumentation Cabinet.

Standard: Transposes readings from PRNIS Readings Table onto Attachment 2.

Comment:

OST-1 039 Section 7.2, Step 3 q Performance Step: 7 RECORD on Attachment 2, in column B, the 100% power normalized current for each channel from Curie F-x-8.

Standard: Transposes TOP and BOTTOM 100% current values from the Curve Book provided.

Comment:

OST-1 039 Section 7.2, Note prior to Step 4 Performance Step: 8 NOTE: When recording all fractions and ratios, record to four decimal places, dropping the fifth and subsequent decimal places.

Standard: Reads and circle slashes note Comment:

OST-1 039 Section 7.2, Step 4 Performance Step: 9 Divide values in Column A by the respective normalized current in Column B and record the result in Column C as the Normalized Fraction.

Standard: Divides each Upper and Lower reading by the respective 100%

normalized current value and records in Column C.

Comment:

V Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 6 of 15 Form ES-C-i PERFORMANCE INFORMATION OST-1 039 Section 7.2, Step 5 Performance Step: 10 CALCULATE the average value for the upper and the lower Normalized Fractions as follows:

  • ADD the Normalized Fraction in each section of column C, recording the sum in the space provided.
  • DIVIDE the sum obtained in Step 7.2.5.a by the number of operable NI channels, recording the result in column D of Attachment 2.

Standard: Adds all Normalized Fractions for the same plane and records the sum in the space provided.

Divides by the sum by four and records result in Column D.

Comment:

OST-1 039 Section 7.2, Step 6 q Performance Step: 11 Using the formula and values from Attachment 2, CALCULATE the Upper and Lower Ratios.

Standard:

  • Divides the Maximum Normalized Fraction by the Average Normalized Fraction on each plane.
  • Determines the UPPER ratio is 1.02 The applicant may inform the CRS as soon as any Evaluator Note: calculation is> 1.02. If so, acknowledge and direct applicant to complete Attachment 2.

Comment:

OST-1 039 Section 7.2, Step 7 Performance Step: 12 PERFORM independent verification of all calculations made on Attachment 2.

Standard: Requests Independent Verifier.

Evaluator Cue: If necessary, repeat Initiating Cue: For the purpose of this examination, there will be no independent verification of your work.

Comment: Candidate may choose to check calculations.

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 7 of 15 Form ES-C-I PERFORMANCE INFORMATION OST-1 039 Section 7.2, Note prior to Step 8 Performance Step: 13 NOTE: The upper ratio or the lower ratio, whichever is greater, is the quadrant power tilt ratio (QPTR).

Standard: Reads and circle slashes note Comment:

OST-1 039 Section 7.2, Step 8 q Performance Step: 14 RECORD QPTR:

Standard: Records QPTR value as 1.0902 to 1.0912 (N43 UPPER)

Identifies Upper as outside the band Comment: Acceptable band is +1- 5% (rounded to .0005).

UPPER calculated band is 1.0902 to 1.0912 LOWER calculated band is 1.0665 to 1.0675 OST-1 039 Section 7.2, Step 9 q Performance Step: 15 CHECK QPTR is less than or equal to 1.02.

Standard: Identifies Upper QPTR as greater than 1.02 and QPTR is unacceptable Comment:

OST-1039 Section 7.2, Note prior to Step 10 Performance Step: 16 NOTE: ERFIS turn on codes used to obtain ERFIS QPTR values include QPTR and GD QPTR.

Standard: Reads and circle slashes note Comment:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 8 of 15 Form ES-C1 PERFORMANCE INFORMATION OST-1 039 Section 7.2, Step 10 Performance Step: 17 IF the ERFIS calculated QPTR value is available, THEN COMPARE OST-1 039 results to the ERFIS QPTR calculated output as a quality check.

Standard: Request status of ERFIS calculated QPTR value, and N/As step 7.2.10 when notified ERFIS QPTR is not available.

Evaluator Note: This information is on the JPM Cue Sheet Evaluator Cue:

Comment:

OST-1039 Section 7.2, Step 11 Performance Step: 18 IF any ERFIS QPTR quality codes do not have a good quality code or the higher of ANM91I2U orANM9I13L do not approximate the value for QPTR determined above, THEN CONTACT HNP IT to investigate.

Standard: Request if notification of the status of the ERFIS calculated QPTR value to HNP IT has been completed.

Evaluator Note: This information is on the JPM Cue Sheet Evaluator Cue:

Comment:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 9 of 15 Form ES-C-I PERFORMANCE INFORMATION OST-1 039 Section 7.3, Test Completion Step I 1 Performance Step: 19

  • IF this test was performed due to an inoperable QPTR alarm, THEN DOCUMENT completion of PMID 22125 RQ 01.
  • COMPLETE applicable sections of Attachment 3, Certifications and Reviews.
  • INFORM the CRS this test is completed.

Standard:

  • Check marks Periodic Surveillance or notes AOP-001 in Comments section
  • Plant Condition: 90% Power (may note dropped rod)
  • Model
  • Todays Date
  • Current Time
  • OST Completed By: Applicants name
  • Initials/Name
  • Indicate in General Comments Section and/or informs CRS that the limit is exceeded Evaluator Cue: Acknowledge any report.

Comment:

After the CRS has been notified:

Terminating Cue:

Evaluation on this JPM is complete.

STOP Time:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 10 of 15 Form ES-C-I PERFORMANCE INFORMATION KEY Record QPTR 1.0907 Acceptable band is +/-5% (rounded to 0005) 1.0902 to 1.0912 CHECK QPTR is less than or equal to 1 .02 (circle) YES A B C D UPPER UPPER AVERAGE UPPER 100% POWER NORMALIZED UPPER UPPER DETECTOR NORMALIZED FRACTION NORMALIZED DETECTOR CURRENT CURRENT (NOTE 1) FRACTION N-41 145.6 164.1 0.8872 N-42 162.5 187.6 0.8662 0.8840 N-43 199.8 207.2 0.9642 N-44 138.4 169.1 0.8184 SUM 3.5360 Maximum Upper Normalized Fraction 0.9642 Upper Ratio = = = 1.0907*

Average Upper Normalized Fraction 0.8840 Standard for this calculation is 1.0902 to 1.0912 A B C D LOWER LOWER AVERAGE LOWER 100% POWER NORMALIZED LOWER LOWER DETECTOR NORMALIZED FRACTION NORMALIZED DETECTOR CURRENT CURRENT (NOTE 1) FRACTION N-41 159.6 183.0 0.8721 N-42 172.1 200.4 0.8587 0.8729 N-43 209.3 224.7 0.9314 N-44 165.2 199.1 0.8297 SUM 3.4919 Maximum Lower Normalized Fraction 0.9314 Lower Ratio Average Lower Normalized Fraction = I .0670 0.8729 Standard for this calculation is 1.0665 to 1.0675

- Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 1 1 of 15 Form ES-C-i VERIFICATION OF COMPLETION Job Performance Measure No.: 2013 NRC Exam Admin JPM RO A2 Perform a Quadrant Power Tilt Ratio Surveillance Examinees Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:

Response

Result: SAT UNSAT Examiners Signature: Date:

2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET Name:

Date:

. The plant is operating at 90% power when a rod in Control Bank A (P-b) dropped.

. The crew is performing AOP-001, MALFUNCTION OF ROD Initial Conditions: CONTROL AND INDICATION SYSTEM.

. There are NO deficiency tags on PR NIs.

. ERFIS points ANM9112U and ANM91I3L have a BAD quality code. HNP IT has been notified and they are evaluating the ERFIS points.

The CRS has directed you to perform a manual QPTR lAW OST-1 039, CALCULATION OF QPTR. The Power Range NIS indications are Initiating Cue: provided.

For the purposes of the examination, there will be no independent verification. Show values of your work.

2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET

=i F proTanoN t. i 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET NVcLAM NSRUME4rATION PR0TECTON CHANNEL HE LPROTECTtON cHANNEL IV j 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET Current and Voltage Setpoints Table (100% Power, 0% Incore Axial Offset)

Top Current Bottom Current Channel # (jiA) (iA)

N41 164.1 183.0 N42 187.6 200.4 N43 207.2 224.7 N44 169.1 199.1 I Curve No. F-18-8 Rev. 6 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Job Performance Measure Form ES-C-i Worksheet Facility: Shearon Harris Task No.: i190i5H301 Task

Title:

Determine Active / Inactive Status JPM No.: 2013 NRC Admin Of Off Shift License Personnel JPM RO SRO Al-I K/A

Reference:

G2.1.i 3.8/4.2 Alternate Path: No Examinee: NRC Examiner:

Facility Evaluator: Date:

Method of testing:

Simulated-Performance: Actual Performance: X Classroom X Simulator Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.

The plant was at 100% power, when the OAC has a medical emergency and will not be able to work his next scheduled shift. The Operations Initi a I Conditions Resource Scheduler has contacted four off shift individuals to replace the QAC on the following day.

Initiatin g Cue You are to determine if each of the Licensed Operators is eligible to work the OAC position on the 0700- 1900 shift on September 13, 2013.

2013 NRC Admin Exam RO SRO Al-i Rev. 2 0 -

Appendix C Job Performance Measure Form ES-C-i Worksheet Task Standard: Determines the Training Department Rotation of Assignment and Work Control Operator license are Active and eligible to stand the 0700- 1900 shift on September 13, 2013 Required Materials: Calculator General

References:

OMM-001, rev 98 Handouts: JPM Cue Sheets Pages7 8 -

Time Critical Task: No Validation Time: 15 minutes Critical Task Justification Must determine the Active I Inactive status of Operator license correctly Step 2 or an ineligible Operator may stand watch Must determine the Active I Inactive status of Operator license correctly St ep 3 or an ineligible Operator may stand watch Ste 4 Must determine the Active I Inactive status of Operator license correctly or an ineligible Operator may stand watch Must determine the Active I Inactive status of Operator license correctly ep or an ineligible Operator may stand watch 2013 NRC Admin Exam RO SRO Al-i Rev. 2

Appendix C Page 3 of 9 Form ES-C-i PERFORMANCE INFORMATION Start Time:

Performance Step: I OBTAIN PROCEDURE Standard: Obtains OMM-OO1 and refers to Section 5.5 Maintenance of NRC Operator Licenses.

Comment:

V Performance Step: 2 Determine if the Active I Inactive status of FIN Team Operator license Standard: Candidate determines the license is Inactive and NOT ELIGIBLE because the operator did not work the required 5 twelve hour shifts in a license position during the previous quarter.

Comment:

V Performance Step: 3 Determine if the Active I inactive status of Train Department Rotation of Assignment Operator license Standard: Candidate determines the license is Active and ELIGIBLE because the license was reactivated in the previous quarter.

There is not a requirement to complete the normally required 5 twelve hour shifts in a license position during the quarter.

(i.e. could complete the reactivation during the last week of a quarter, thus the opportunity would not be available to work the 5 shifts)

Comment:

V - Denotes a Critical Step 2013 NRC Admin Exam RO SRO Al-i Rev. 2

Appendix C Page 4 of 9 Form ES-C-i PERFORMANCE INFORMATION V Performance Step: 4 Determine if the Active I Inactive status of Work Control Operator license Standard: Candidate determines the license is Active and ELIGIBLE because the operator worked the required 5 twelve hour shifts in a license position during the previous quarter.

Comment:

V Performance Step: 5 Determine if the Active I Inactive status of Procedure Writers Group Operator license V Standard: Candidate determines the license is Inactive and NOT ELIGIBLE because a required license position was NOT reactivated in the previous quarter AND the individual did not work the required 5 twelve hour shifts in a license position during the quarter. (i.e. STA position is not an on shift position that is credited for a license operator watch)

Comment:

Performance Step: 6 Determines the licensed operators eligible to stand the 0700 -

1900 shift on September 13, 2013 Standard: Determines the Training Department Rotation of Assignment and Work Control Operator license are Active and eligible to stand the 0700- 1900 shift on September 13, 2013 Evaluator Cue: CRS acknowledges determination of eligible watch standers END OF JPM Comment:

Stop Time:

V - Denotes a Critical Step 2013 NRC Admin Exam RO SRO Al-I Rev. 2

Appendix C Page 5 of 9 Form ES-C-i PERFORMANCE INFORMATION KEY Four Reactor Operators have the following history:

  • All four are current in License Operator Requalification Training and have had a medical examination in the past 2 years.
  • None of the 4 have worked any shift since 06/30/13.
  • Active/Inactive status and time on shift since April 1, 2013 is as follows for each of the Reactor Operators:
  • FIN Team Operator License was active on April 1, 2013 4/02/13 worked 0700-1900 shift as OAC 4/03/13 -worked 0700-1900 shift as BOP 5/04/13 worked 0700-1 900 shift as CRS 6/14/13 worked 0700-1900 shift as STA 6/17/13 worked 1900-0700 shift as CRS
  • Training Department Rotation of Assignment Operator License was inactive on April 1, 2013 5/02/13 thru 5/06/13 worked 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> under the direction of the QAC and completed all requirements for reactivation.

5/10/13 worked 0700-1900 shift as BOP 5/12/13 worked 0700-1 900 shift as OAC 5/14/13 worked 1900-0700 shift as OAC 5/31/13 worked 1900-0700 shift as SOP

  • Work Control Operator License was active on April 1, 2013 4/23/13 worked 0700-1900 shift as OAC 4/25/1 3 worked 0700-1900 shift as BOP 5/05/13 worked 0700-1900 shift as QAC 5/14/13 worked 1900-0700 shift as BOP 6/17/13 worked 1900-0700 shift as OAC
  • Procedure Writers Group Operator License was active on April 1, 2013 4/12/13 thru 4/16/13 worked 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> under the direction of the STA and completed all requirements for reactivation.

4/14/13 worked 1900-0700 shift as STA 4/18/13 worked 0700-1900 shift as STA 5/12/13 worked 0700-1 900 shift as OAC 5/14/13 worked 1900-0700 shift as SOP 5/31/13 worked 1900-0700 shift as CRS To maintain active status, licensed individuals shall actively perform the functions of an operator or senior operator on a minimum of five 12-hour shifts per calendar quarter.

OR A minimum of 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> of shift functions under the direction of an operator or senior operator as appropriate and in the position to which the individual will be assigned. The 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> must have included a complete review of all required shift turnover procedures.

V - Denotes a Critical Step 2013 NRC Admin Exam RO SRO Al-i Rev. 2

Appendix C Page 6 of 9 Form ES-C-I PERFORMANCE INFORMATION KEY

1. FIN Team Operator ELIGIBLE CT ELIGIBLE
2. Training Department Rotation of Assignment Operator....IBLE NOT ELIGIBLE
3. Work Control Operator IBLE CT ELIGIBLE
4. Procedure Writers Group Operator ELIGIBLE IGIBLE V - Denotes a Critical Step 2013 NRC Admin Exam RO SRO Al-i Rev. 2

Appendix C Page 7 of 9 Form ES-C-i VERIFICATION OF COMPLETION Job Performance Measure No.: 2013 NRC JPM RO SRO Al-i Determine Active I Inactive Status Of Off Shift License Personnel OMM-00l Examinees Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:

Response

Result: SAT UNSAT Examiners Signature: Date:

2013 NRC Admin Exam RO SRO Al-i Rev. 2

Appendix C Page 8 of 9 Form ES-C-I JPM CUE SHEET Name:

Date:

The plant was at 100% power, when the OAC has a medical emergency Initial Conditions: and will not be able to work his next scheduled shift. The Operations Resource Scheduler has contacted four off shift individuals to replace the OAC on the following day.

Initiating Cue: You are to determine if each of the Licensed Operators is eligible to work the OAC position on the 0700- 1900 shift on September 13, 2013.

After making the determination of License Operator eligibility circle their status below:

1 FIN Team Operator ELIGIBLE I NOT ELIGIBLE

2. Training Department Rotation of Assignment Operator ELIGIBLE I NOT ELIGIBLE
3. Work Control Operator ELIGIBLE I NOT ELIGIBLE
4. Procedure Writers Group Operator ELIGIBLE I NOT ELIGIBLE 2013 NRC Admin Exam RO SRO Al-i Rev. 2

Appendix C Page 9 of 9 Form ES-C-I JPM CUE SHEET Four Reactor Operators have the following history:

  • All four are current in License Operator Requalification Training and have had a medical examination in the past 2 years.
  • None of the 4 have worked any shift since 06/30/13.
  • Active/Inactive status and time on shift since April 1, 2013 is as follows for each of the Reactor Operators:
  • FIN Team Operator License was active on April 1, 2013 4/02/13 worked 0700-1900 shift as OAC 4/03/13 worked 0700-1900 shift as BOP 5/04/13 worked 0700-1900 shift as CRS 6/14/13 -worked 0700-1900 shift as STA 6/17/13 worked 1900-0700 shift as CRS
  • Training Department Rotation of Assignment Operator License was inactive on April 1, 2013 5/02/13 thru 5/06/13 worked 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> under the direction of the OAC and completed all requirements for reactivation.

5/10/13 worked 0700-1900 shift as BOP 5/12/13 worked 0700-1 900 shift as OAC 5/14/13 worked 1900-0700 shift as OAC 5/31/13 worked 1900-0700 shift as BOP

  • Work Control Operator License was active on April 1, 2013 4/23/13 worked 0700-1900 shift as OAC 4/25/13 worked 0700-1900 shift as BOP 5/05/13 worked 0700-1900 shift as OAC 5/14/13 worked 1900-0700 shift as BOP 6/17/13 worked 1900-0700 shift as OAC
  • Procedure Writers Group Operator License was active on April 1, 2013 4/12/13 thru 4/16/13 worked 40 hours4.62963e-4 days <br />0.0111 hours <br />6.613757e-5 weeks <br />1.522e-5 months <br /> under the direction of the STA and completed all requirements for reactivation.

4/14/13 worked 1900-0700 shift as STA 4/18/13 worked 0700-1900 shift as STA 5/12/13 -worked 0700-1900 shift as OAC 5/14/13 worked 1900-0700 shift as BOP 5/31/13 worked 1900-0700 shift as CRS 2013 NRC Admin Exam RO SRO Al-I Rev. 2

Appendix C Job Performance Measure Form ES-C-I Worksheet Facility: HARRIS Task No.: 301179H601 Task

Title:

Determine Average RCS Boron JPM No.: 2013 NRC Admin Concentration JPM RD SRO A1-2 K/A

Reference:

004 A4.04 3.2 I 3.6 Alternate Path: No Examinee: NRC Examiner:

Facility Evaluator: Date:

Method of testing:

Simulated Performance: Actual Performance: X Classroom X Simulator Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.

Following a loss of offsite power, recovery actions are being taken in accordance with EOP-ECA-0. 1, Loss of All AC Power Recovery Without SI Required Plant conditions are as follows:

. PRZ pressure 2230psig

. RCS Hot Leg temperatures 555°F

. Core Exit thermocouples 560° F

  • PRZ Liquid space temperature 650°F Initial Conditions:
  • PRZ Steam space temperature 650°F
  • PRZ level 45 %
  • Charging and letdown are in service, with letdown flow at 45 gpm.

Chemistry has just taken RCS boron samples and reports the following results:

  • Loop B Hot Leg 930 ppm
  • Loop C Hot Leg 940 ppm
  • PRZ Liquid Space 961 ppm The CRS requires that you calculate the average RCS boron Initiating Cue: concentration for these conditions per EOP-ECA-0.l, Attachment I to TWO decimal places.

2013 NRC Exam Admin JPM RO SROA1-2 Rev 2

Appendix C Job Performance Measure Form ES-C-i Worksheet Task Standard: Average RCS boron calculation determined to be 937.4 + 0.5 ppm.

Required Materials:

  • Calculator
  • Curve Book General

References:

  • EOP-ECA-0. 1 Loss of All AC Power Recovery Without SI Required, Rev. 0
  • Curve D-X40, Pressurizer Volume Handouts:
  • EOP-ECA-0.1, Loss of All AC Power Recovery Without SI Required, Rev. 0 Attachment 1
  • Curve Book (preferred) or at a minimum Curve D-X-40 Time Critical Task: No Validation Time: 15 minutes 2013 NRC Exam Admin JPM RO SRO A1-2 Rev. 2

Appendix C Page 3 of 9 Form ES-C-i PERFORMANCE INFORMATION Start Time:

Performance Step: I Locate ECA-O. 1 Attachment 1, and Curve Book (Attachment 1 provided with handout)

Standard: Obtains ECA-O.i, Attachment 1, and Curve Book Comment:

ECA.-O1, Att. 1, Step 1 Performance Step: 2 Record PRZ level at the time of PRZ sample Standard:

Records PRZ level as 45%

Comment:

ECA-O.1, Att. 1, Step 2 V Performance Step: 3 Determine PRZ volume (VpRz) based on PRZ level and curve D-X-40 Standard:

  • References curve D-X-40
  • Determines intersection of 653°F PRZ LIQUID SPACE TEMP LINE and 45% on INDICATED PRESSURIZER LEVEL axis (X) to correspond to 2900 +/- 100 gallons on VOLUME axis (Y)

Comment:

V Denotes a Critical Step 2013 NRC Exam Admin JPM RO SRO Ai-2 Rev.2

Appendix C Page 4 of 9 Form ES-C-i PERFORMANCE INFORMATION ECA-0.1, Att. 1, Step 3 V Performance Step: 4 Determine CVCS volume (Vccs) based on letdown status:

  • If letdown in service 2136 gal ÷ 2 = 1068 gal
  • If letdown isolated 0 Standard: Determines letdown volume of 1068 gallons due to letdown being in service Comment:

ECA-0.1, Aft. 1, Step 4 Performance Step: 5 Record RCS loop B boron concentration C2 Standard: Records RCS loop B boron concentration as 930 ppm Comment:

ECA-0.1, Att. 1, Step 5 Performance Step: 6 Record RCS loop C boron concentration C3 Standard: Records RCS loop C boron concentration as 940 ppm Comment:

ECA-0.1,Att. 1, Step 6 Performance Step: 7 Record PRZ liquid space boron concentration CPRZ Standard: Records PRZ liquid space boron concentration as 961 ppm Comment:

V - Denotes a Critical Step 2013 NRC Exam Admin JPM RO SRO A1-2 Rev.2

Appendix C Page 5 of 9 Form ES-C-I PERFORMANCE INFORMATION ECA-0.1 Att. 1, Step 7 Performance Step: 6 Calculate average RCS boron concentration (CAvG) using the following formula (formula on Att. 1, Step 7)

Standard: Calculates average RCS boron concentration to be 937.42 +/- 0.5 ppm. (Range 936.92 937.92 ppm)

Evaluator Note: NOTE: ALLOWED TOLERANCE BORDERS TOLERANCE FOR ALLOWED ERROR IN READING CURVE D-X-40, BUT WILL NOT BE MET IF APPLICANT FAILS TO ACCOUNT FOR CVCS LETDOWN OR OTHER SIMILAR ERRORS.

Comment:

Evaluator Cue: When boration calculation completed END OF JPM Stop Time:

Terminating Cue: Calculation of average boration concentration completed.

V Denotes a Critical Step 2013 NRC Exam Admin JPM RO SRO A1-2 Rev.2

Appendix C Page 6 of 9 Form ES-C-i PERFORMANCE INFORMATION KEY OF ALL PLC POWER RECOVERY WITHOUT SI REQUIRED LOSS Attachment 1 Shoot 1 o 1 CALCULITlON FOR AVERAGE RCS BORON CONCENTRATION

1. Record PRZ level at the time o PRZ sample: 45  %
2. Determine PRZ volume (\/PRZ

) based on PRZ level and curve D-X-40: 2900 +/- 100 GAL

3. Determine CVCS volume (Vcvcs) based on letdown status: 1068 GAL
  • ((letdown inservice=2136 GAL÷2= 1O8 GAL
  • If letdown isolated = 0 GAL
4. Record RCS loop B boron concentration C2: 30 PPM 5 Record RCS loop C boron concentration 03: 940 PPM
6. Record PRZ liquid space boron concentration CPRz: PPM
7. Calculate average RCS boron concentration (Cav ) using the Following formula:

[(930 + 940) x (31218 ÷ 1068)] + [961 x (2900 + 3700)]

[(C2 4- C3)x(31218 + Vcvcs)] FCpz x (VFIZ 37O0)}

Cavg= = 937 42 PPM (VFsP.z+ 2 x (Vcvcs) 4 66135)

(2900 + 2 x (1068) + 66135)

NOTE 1: RCS Volume not including PRZ, Upper Head, Surge Line or CVCS = 62,435 GAL.

(Value halved in calculation ro ocount for averaginG the boron concentration for Loops B and C 31 ,218 GAL.)

NOTE 2: RCS Volume not including PRZor CVCS = 66i35 GAL NOTE 3: Combined Upper Head and Surge Line Volume = 3700 GAL.

(Upper Head Volume 33r35 GAL and Surge Line Volume = 335 GAL.)

NOTE 4: CVCS Volume = 2138 GAL (Value halved in Step 3 to account for averaging the boron concentration for RCS loop B and C = 1068 GAL)

NOTE 5: The boron concentraicn ot te Upper Head and Surge Line is assumed to be that of the PRZ since these volumes a so stagnate when RCPs are lost. CVCS boron conceniration ts assumed to be that of the RCS EOP-ECA-0. 1 I Rev. 0 Page 49 of 54 V Denotes a Critical Step 2013 NRC Exam Admin JPM RO SRO A1-2 Rev.2

Appendix C te 7 of 9 Form ES-C-I PERFORMANCE INFORMATION KEY PRESSURIZER VOLUME (LT.-459, LT-460, AND LT-461) 10000-.

95O0 --.- .-.------

PRZLQUIDSPACETEMP 90 _i -.----

85O0 1___653DF -

8000f----- - ,-


n-.--

750O- 550DEGF - --

7000 - -. . -

6OO: I 500DEGF _._:_*_._

6000 -.

0 350 DEG F - -. - -

i 5000_ -- - - - ---

( 45QQ: .-..-....-..

70 D EG F 40O0 ._.

÷ 350 2

L 1 900 00 0 -

-z- - .. -----

3000 4 ,-.-.-.---

2500-- -...-.-..-

1 CRT NO -

REV,, NO.

2000 -

OXCINATOR DE aZZf2_

TE /f/-97

-- SHIF OPDRATIONS DATE 1000 - -

0.0 5.0 10.0 15.0 20.0 25.0 30.0 35.0 40.0 45.0 50.0 55.0 60.0 65.0 70.0 75.0 80.0 85.0 90.0 95.0 100.0 INDICA TED PRESSURIZER LEVEL (%)

/ Denotes a Critical Step 2013 NRC Exam Admin JPM RO SRO A1-2 Rev.2

Appendix C Page 8 of 9 Form ES-C-I VERIFICATION OF COMPLETION Job Performance Measure No.: 2013 NRC Exam Admin JPM RO SRO A1-2 Determine Average RCS Boron Concentration Examinees Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:

Response

Result: SAT UNSAT Examiners Signature: Date:

2013 NRC Exam Admin JPM RO SROA1-2 Rev. 2

Appendix C Page 9 of 9 Form ES-C-i JPM CUE SHEET Following a loss of offsite power, recovery actions are being taken in accordance with EOP-ECA-0.1, Loss of All AC Power Recovery Without SI Required Plant conditions are as follows:

. PRZ pressure 2230 psig

  • RCS Hot Leg temperatures 555° F

. Core Exit thermocouples 560°F

. PRZ Liquid space temperature 650°F Initial Conditions:

  • PRZ Steam space temperature 650°F
  • PRZ level 45 %
  • Charging and letdown are in service, with letdown flow at 45 gpm.

Chemistry has just taken RCS boron samples and reports the following results:

  • Loop B Hot Leg 930 ppm
  • Loop C Hot Leg 940 ppm
  • PRZ Liquid Space 961 ppm The CRS requires that you calculate the average RCS boron Initiating Cue: concentration for these conditions per EOP-ECA-0.i, Attachment 1 to TWO decimal places.

2013 NRC Exam Admin JPM RO SRO A1-2 Rev. 2

Appendix C Job Performance Measure Form ES-C-i Worksheet Facility: ShearonHarris Task No.: 015004H201 Task

Title:

Perform the Quadrant Power Tilt JPM No.: 2013 NRC Exam Ratio Surveillance Admin JPM SRO A2 K/A

Reference:

G2.2.12 RO 3.7 SRO 4.1 Alternate Path: No Examinee: NRC Examiner:

Facility Evaluator: Date:

Method of testing:

Simulated Performance: Actual Performance: X Classroom X Simulator Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.

. The plant is operating at 90% power when a rod in Control Bank A (P-b) dropped.

. The crew is performing AOP-00i, MALFUNCTION OF ROD Initial Conditions: CONTROL AND INDICATION SYSTEM.

. There are NO deficiency tags on PR NIs.

. ERFIS points ANM91 12U and ANM91 13L have a BAD quality code. HNP IT. has been notified and they are evaluating the ERFIS points.

The CRS has directed you to perform a manual QPTR lAW OST-i 039, CALCULATION OF QPTR, AND evaluate the actions, if any, of the applicable Technical Specification. The Power Range NIS indications Initiating Cue: are provided.

For the purposes of the examination, there will be no independent verification. Show values of your work.

2013 NRC Exam Admin JPM SRO A2 Rev 2

Appendix C Job Performance Measure Form ES-C-i Worksheet Task Standard: Calculations within required band.

Correct Tech Spec actions are identified.

Required Materials: Calculator General

References:

OST-1039, CALCULATION OF QPTR, Revision 16 Technical Specifications Handouts:

  • OST-1 039
  • Power Range NI Current and Voltage Set point Table
  • Technical Specifications Time Critical Task: No Validation Time: 15 minutes Critical Step Justification Must accurately determine the correct calculation based on collecting Step 11 and inputting either provided data or visual inspection data. The calculation will yield an unsatisfactory QPTR.

Ste p 14 Must identify that the QPTR upper is outside the band which will make this overall results unsatisfactory.

Step 15 Must unsatisfactory that the QPTR is greater than 1.02 (which is a Tech Spec limit).

Must correctly identify through documentation that the QPTR limits are Step 19 exceeded.

Must accurately identify associated Technical Specifications with a Step 20 QPTR that has exceeded the limits specified in HNP Technical Specifications.

2013 NRC Exam Admin JPM SRO A2 Rev. 2

Appendix C Page 3 of 17 Form ES-C-i PERFORMANCE INFORMATION Start Time:

Performance Step: I Obtain procedure.

Standard: Reviews procedure.

Evaluator Cue: Provide OST-1 039.

Evaluator Note: A KEY is provided for your use on JPM prior to candidate pages.

Comment:

NOTE: The NI curve numbers provided in this JPM are Evaluator Note: numbers from the 2013 NRC Exam Frozen Procedures Curve Book folder.

Precaution and Limitation 4.0.1 has guidance if performing this Procedure Note: OST with one Power Range Channel inoperable.

Performance Step: 2 Completes Prerequisites section:

  • Verify instrumentation needed for the performance of this test is free of deficiencies that affect instrument indication.
  • Verify the most recent Curve F-X-8 is used in the performance of this procedure. (Reference 2.1.1 and 2.1.2)
  • OBTAIN CRS permission to perform this OST.

Standard:

  • Logs F-18-8 revision number: 6
  • Initials/signs all blocks Comment:

- Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 4 of 17 Form ES-C-i PERFORMANCE INFORMATION Performance Step: 3

  • IF Quadrant Power Tilt Ratio Calculation Computer Program is used, THEN PERFORM the following:
  • MARK Step 7.0.2 N/A.
  • MARK Section 7.2 N/A.
  • PERFORM Section 7.1.
  • IF manual calculation of the Quadrant Power Tilt Ratio is used, THEN PERFORM the following:
  • MARK Section 7.1 N/A.
  • PERFORM Section 7.2.

Standard:

  • Marks Section 7.1 N/A
  • Proceeds to Section 7.2 Comment:

OST-1 039 Section 7.2 Note prior to step I Performance Step: 4 NOTE: The detector current meters on each power range channel drawer are designated as leftupper, right-lower.

Standard: Reads and circle slashes note Comment:

OST-I 039 Section 7.2, Step I Performance Step: 5 Prior to reading the value of detector current, VERIFY the meter range/rate switch is in the 400 LAJS LOW position.

Standard: Prior to reading the value of detector current, VERIFIES the Meter Range/Rate switch is in the 400 pNSLOW position.

Evaluator Note: This information is on the JPM Cue Sheet Comment:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 5 of 17 Form ES-C-I PERFORMANCE INFORMATION OST-1 039 Section 7.2, Step 2 Performance Step: 6 RECORD on Attachment 2, in column A, the upper and lower detector currents from all operable power range channels as read on the Nuclear Instrumentation Cabinet.

Standard: Transposes readings from PRNIS Readings Table onto Attachment 2.

Comment:

OST-1 039 Section 7.2, Step 3 J Performance Step: 7 RECORD on Attachment 2, in column B, the 100% power normalized current for each channel from Curve F-x-8.

Standard: Transposes TOP and BOTTOM 100% current values from the Curve Book provided.

Comment:

OST-1 039 Section 7.2, Note prior to Step 4 Performance Step: 8 NOTE: When recording all fractions and ratios, record to four decimal places, dropping the fifth and subsequent decimal places.

Standard: Reads and circle slashes note Comment:

OST-1 039 Section 7.2, Step 4 Performance Step: 9 Divide values in Column A by the respective normalized current in Column B and record the result in Column C as the Normalized Fraction.

Standard: Divides each Upper and Lower reading by the respective 100%

normalized current value and records in Column C.

Comment:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 6 of 17 Form ES-C-i PERFORMANCE INFORMATION OST-1 039 Section 7.2, Step 5 Performance Step: 10 CALCULATE the average value for the upper and the lower Normalized Fractions as follows:

. ADD the Normalized Fraction in each section of column C, recording the sum in the space provided.

. DIVIDE the sum obtained in Step 7.2.5.a by the number of operable NI channels, recording the result in column D of Attachment 2.

Standard: Adds all Normalized Fractions for the same plane and records the sum in the space provided.

Divides by the sum by four and records result in Column D.

Comment:

OST-1 039 Section 7.2, Step 6 J Performance Step: 11 Using the formula and values from Attachment 2, CALCULATE the Upper and Lower Ratios.

Standard:

  • Divides the Maximum Normalized Fraction by the Average Normalized Fraction on each plane.
  • Determines the UPPER ratio is 1.02 The applicant may inform the CRS as soon as any Evaluator Note: calculation is> 1.02. If so, acknowledge and direct applicant to complete Attachment 2.

Comment:

OST-1 039 Section 7.2, Step 7 Performance Step: 12 PERFORM independent verification of all calculations made on Attachment 2.

Standard: Requests Independent Verifier.

Evaluator Cue: If necessary, repeat Initiating Cue: For the purpose of this examination, there will be no independent verification of your work.

Comment: Candidate may choose to check calculations.

V Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 7 of 17 Form ES-C-i PERFORMANCE INFORMATION OST-1 039 Section 7.2, Note prior to Step 8 Performance Step: 13 NOTE: The upper ratio or the lower ratio, whichever is greater, is the quadrant power tilt ratio (QPTR).

Standard: Reads and circle slashes note Comment:

OST-1 039 Section 7.2, Step 8

-J Performance Step: 14 RECORD QPTR:

Standard: Records QPTR value as 1.0902 to 1.0912 (N43 UPPER)

Identifies Upper as outside the band Comment: Acceptable band is +1- 5% (rounded to .0005).

UPPER calculated band is 1.0902 to 1.0912 LOWER calculated band is 1.0665 to 1.0675 OST-1 039 Section 7.2, Step 9 J Performance Step: 15 CHECK QPTR is less than or equal to 1.02.

Standard: Identifies Upper QPTR as greater than 1.02 and QPTR is unacceptable Comment:

OST-1 039 Section 7.2, Note prior to Step 10 Performance Step: 16 NOTE: ERFIS turn on codes used to obtain ERFIS QPTR values include QPTR and GD QPTR.

Standard: Reads and circle slashes note Comment:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 8 of 17 Form ES-C1 PERFORMANCE INFORMATION OST-1 039 Section 7.2, Step 10 Performance Step: 17 IF the ERFIS calculated QPTR value is available, THEN COMPARE OST-1 039 results to the ERFIS QPTR calculated output as a quality check.

Standard: Request status of ERFIS calculated QPTR value, and N/As step 7.2.10 when notified ERFIS QPTR is not available.

Evaluator Note: This information is on the JPM Cue Sheet Evaluator Cue:

Comment:

OST-1 039 Section 7.2, Step 11 Performance Step: 18 IF any ERFIS QPTR quality codes do not have a good quality code or the higher of ANM91 1 2U or ANM91 1 3L do not approximate the value for QPTR determined above, THEN CONTACT HNP IT to investigate.

Standard: Request if notification of the status of the ERFIS calculated QPTR value to HNP IT has been completed.

Evaluator Note: This information is on the JPM Cue Sheet 1

Evaluator Cue:

Comment:

V Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 9 of 17 Form ES-C-I PERFORMANCE INFORMATION OST-1 039 Section 7.3, Test Completion Step I J Performance Step: 19

  • IF this test was performed due to an inoperable QPTR alarm, THEN DOCUMENT completion of PMID 22125 RQ 01.
  • COMPLETE applicable sections of Attachment 3, Certifications and Reviews.
  • IN FORM the CRS this test is completed.

Standard:

  • Check marks Periodic Surveillance or notes AOP-001 in Comments section
  • Plant Condition: 90% Power (may note dropped rod)
  • Model
  • Todays Date
  • Current Time
  • OST Completed By: Applicants name
  • Initials/Name
  • Indicate in General Comments Section and/or informs CRS that the limit is exceeded Evaluator Cue: Acknowledge any report.

Comment:

q Performance Step: 20 Identify the Technical Specification LCOs that would be in effect.

Standard: Identifies that Technical Specification 3.2.4, Quadrant Power Tilt Ratio has been exceeded

  • Identifies the following ACTION statements to be implemented and the required time limitation (see page 12) o 3.2.4.b.1 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> o 3.2.4.b.2 30 minutes, reduce thermal power to < 73%
  • (9% x 3% 27% 100% 27% = 73%)

o 3.2.4.b.3 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />

[ Evaluator Note:

Technical Specification 3.2.4.b.4 is not required to be identified since no direction is provided in the cue for raising thermal power.

Comment:

- Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 10 of 17 Form ES-C-i PERFORMANCE INFORMATION After the CRS has been notified:

Terminating Cue:

Evaluation on this JPM is complete.

STOP Time:

V Denotes Critical Steps

- 2013 NRC Exam Admin JPM RD A2 Rev. 2

Appendix C Page 11 of 17 Form ES-C-i PERFORMANCE INFORMATION KEY Record QPTR = 1.0907 Acceptable band is +/-5% (rounded to .0005) 1.0902 to 1.0912 CHECK QPTR is less than or equal to 1.02 (circle) YES A B C D UPPER UPPER AVERAGE UPPER 100% POWER NORMALIZED UPPER UPPER DETECTOR NORMALIZED FRACTION NORMALIZED DETECTOR CURRENT CURRENT (NOTE 1) FRACTION N-41 145.6 164.1 0.8872 N-42 162.5 187.6 0.8662 0.8840 N-43 199.8 207.2 0.9642 N-44 138.4 169.1 0.8184 SUM 3.5360 Maximum Upper Normalized Fraction 0.9642 Upper Ratio = = = 1.0907*

Average Upper Normalized Fraction 0.8840 Standard for this calculation is 1.0902 to 1.0912 A B C D LOWER LOWER AVERAGE LOWER 100% POWER NORMALIZED LOWER LOWER DETECTOR NORMALIZED FRACTION NORMALIZED DETECTOR CURRENT CURRENT (NOTE 1) FRACTION N-41 159.6 183.0 0.8721 N-42 172.1 200.4 0.8587 0.8729 N-43 209.3 224.7 0.9314 N-44 165.2 199.1 0.8297 SUM 3.4919 Maximum Lower Normalized Fraction 0.9314 Lower Ratio =

= 1 .0670**

Average Lower Normalized Fraction 0.8729 Standard for this calculation is 1.0665 to 1.0675 V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 12 of 17 Form ES-C-i PERFORMANCE INFORMATION KEY

\4E GIST 3UI LIMVTS 1UI CONOtTO4 FDR opRKrTGN

_ION (Cortriue)

Wits tfe QUADRANT POWER TILT RATIO did to 1 09 du* to saIignsent f .fth.r a shutdcin or cortr1 ro4

1. C41ulati[ the QUADP,AiiT PCWR flIJ RATtO it lUSt CflC& per hour untir etther a) Thi 1IADRANT PWER TILT RATIO Is rdued to wfthni ts Uiit or b) ThE4AL PGER fi ce t4 less thr 5 of RAT!E TNR?4AL PER 2 Redu. ThERKAL PWR at least 3 from RATt: VERL PR for cti % of Indicated QUADRANT PGE3 TILT ATID in excess of LCO, wittfri 30 nuta
a. Verify tat te QUADRANT POWER TZURATIC ts 1tIn tt 1lit itMri Z hour aftur xt*dn the 1jit or riduci ThER4AL PWE t 1,.:s than SZ of RATO ThERKAL POWER within the nxt 2 hcur iiid redu+/-e tfla Power Rarn. eitrn Fit xHi1i Trip S.tolnts to 1*s than or equal to S of RATED ThEIA POd!R witMn.thane4hcu.ri;&rd
4. td.tify ard or the cauie of the ut fifeit cori4ftcn pHor to incrwtrg ThERMAL PR, sunquent P(MR CPERATION iove & ol Rtt!E ThER)AL PER say rctad prvid ttat the QUAERMT PCWER TILT RAT!C f veilfle4 uith{rt Its 1lit t leut OflC* hOUT fr 12 OU1 Ø? WItiI v*r1f1* acatab1e at or crietar RAT ThERMAL PWEL
c. With the QUAANT POWER flU RNTtD detaratne4 to exceed 1.9 due to cauas othar than the 1saTIreit of either a shut4owr or contrcl rod Z. Ca1ci1it. thi QUADRANT POWER TILT RrtO at 1*ast n* er hew with either:

a) Th. QWCRANT POWER TILT RATIO fi rtdced to WitMfi Its H.eit or b) ThERMAL POWER Is r*1tcd to l.ss ttN. 5 af RATED ThEMAL P(WER.

EARK HARRIS - t1MI 1 3/4 Z12 V Denotes Critical Steps 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 13 of 17 Form ES-C-I VERIFICATION OF COMPLETION Job Performance Measure No.: 2013 NRC Exam Admin JPM RD A2 Perform a Quadrant Power Tilt Ratio Surveillance Examinees Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:

Response

Result: SAT UNSAT Examiners Signature: Date:

2013 NRC Exam Admin JPM RD A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET Name:

Date:

. The plant is operating at 90% power when a rod in Control Bank A (P-la) dropped.

. The crew is performing AOP-OOi, MALFUNCTION OF ROD Initial Conditions: CONTROL AND INDICATION SYSTEM.

. There are NO deficiency tags on PR NIs.

. ERFIS points ANM9112U and ANM9I13L have a BAD quality code. HNP IT has been notified and they are evaluating the ERFIS points.

The CRS has directed you to perform a manual QPTR lAW OST-l 039, CALCULATION OF QPTR, AND evaluate the actions, if any, of the applicable Technical Specification. The Power Range NIS indications Initiating Cue: are provided.

For the purposes of the examination, there will be no independent verification. Show values of your work.

2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET

\NUCtEAR1NSTRUMENTATON>J. NUCLEAg NSTRUMENTATON PROltCrlOr4 CHANNEL I PROTECT ION CHANNEL 1 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET NUCLEAR tNsRuMA1IoN: NUcLEAR NSTRUMENTATON PROTECTION CHANNEt. flX POTECT1ON OHANNEL V 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET Current and Voltage Setpoints Table (100% Power, 0% lncore Axial Offset)

Top Current Bottom Current Channe # (ptA) (A)

N41 164.1 183.0 N42 187.6 200.4 N43 207.2 224.7 N44 169.1 199.1 Curve No. F-lB-S Rev. 6 2013 NRC Exam Admin JPM RO A2 Rev. 2

Appendix C Page 1 of 1 1 Form ES-C-i Worksheet Facility: Shearon Harris Task No.:

Task

Title:

Using survey maps determine stay JPM No.: 2013 NRC Exam Admin times JPM RO SRO A-3 K/A

Reference:

G.2.3.4 RO 3.2 SRO 3.7 Alternate Path: No Examinee: NRC Examiner:

Facility Evaluator: Date:

Method of testing:

Simulated Performance: Actual Performance: X Classroom X Simulator Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.

Initial Conditions: Two individuals are tasked to hang a clearance on 1CS-38, Letdown PCV Isol Vlv. The clearance includes the following valves:

  • 1 CS-39, Outlet lsol Vlv to LTDN PCV Drain Vlv
  • 1CS-40, Outlet Isol to LTDN PCV Drain Isol Vlv
  • 1CS-43, Outlet Isol Vlv to LTDN PCV Initiating Cue: Two Operators are being assigned to hang a clearance and perform work in a radiological area. Operator 1 has an accumulated annual Whole Body dose of 1750 mrem (Duke Energy Progress). Operator 2 has an accumulated annual Whole Body dose of 700 mrem (Duke Energy Progress) and worked at Nine Mile Point earlier this year where he has accumulated 2550 mrem.

The clearance and work activity is for 1CS-38, Letdown PCV lsol Vlv. The ALARA group has determined that additional shielding is not warranted for this work.

Using the supplied survey map, determine the maximum allowable individual stay times for each Operator that would prevent exceeding the Progress Energy Annual Administrative dose limit while performing these activities.

Do not consider dose received during transit. The calculated dose should be ONLY what they would receive while working at the valves for the clearance.

Complete the information below and return to the evaluator when complete.

I 2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

(

)

Appendix C Page 2 of 1 1 Form ES-C-i Worksheet Task Standard: Calculation of stay times based on survey maps, two hours for Operator 1, six hours for Operator 2.

Required Materials: Survey map A45 RAB 236 LETDOWN & LETDOWN REHEAT HX &VG Map 21 SFD-5-S-1 304 General

References:

DOS-NGGC-0004, Administrative Dose Limits Section 9.3, Duke Energy Progress Annual Administrative Dose Limits (Rev. 12)

LIMIT 2 REM Duke Energy Progress dose not to exceed 4 REM total dose if Non-Duke Energy Progress dose for the current year has been determined.

Time Critical Task: No Validation Time: 10 minutes Critical Task Justification Step I Must determine dose rates in order to calculate stay time Step 2 Must determine available dose to determine stay time.

IF incorrect calculation of stay time is made the individuals could exceed Ste p 3 their dose limits.

2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

Appendix C Page 3 of 1 1 Form ES-C-I PERFORMANCE INFORMATION START TIME:

Evaluator Note: The order of performance does not matter IF THE APPLICANT ASKS FOR IT: Provide a copy of DOS NGGC-0004, Rev. 12 v Performance Step: I Using Radiological Survey Record Map A45 and RAB 236 LETDOWN & LETDOWN REHEAT HX &VG Map 21, determines dose rates in the area where the clearance will be applied Standard: Identifies that General Area Dose Rates are 125 mrem/hr Comment:

v Performance Step: 2 Determine the remaining dose for the year for each individual Standard: Operator 1: 250 mrem 2000 mrem 1750 mrem

- = 250 mrem Operator 2: 750 mrem 4000 mrem 700 mrem (PE)

- - 2550 mrem (NMP) = 750 mrem Comment:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

Appendix C Page 4 of 1 1 Form ES-C-i PERFORMANCE INFORMATION V Performance Step: 3 Determine stay time for each operator (based on 1st Operator

. reaching 2 Rem and the 2nd Operator reaching 4 Rem for the year)

Standard: Operator 1: 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> 250 mrem ÷ 125 mrem/hr = 2 hrs Operator 2: 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> 750 mrem ÷ 125 mrem/hr = 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> Comment:

Terminating Cue: After the stay time has been calculated, this JPM is complete.

END OF JPM STOP TIME:

V - Denotes Critical Steps 2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

Appendix C Page 5 of 1 1 Form ES-C-i VERIFICATION OF COMPLETION Job Performance Measure No.: 2013 NRC Exam Admin JPM RO SRO A-3 Using survey maps determine stay times. (DOS-NGGC-0004 Rev. 12)

DOS-NGGC-0004, Administrative Dose Limits, Section 9.3, Duke Energy Progress Annual Administrative Dose Limits.

LIMIT 2 REM Progress Energy dose not to exceed 4 REM total dose if Non-Duke Energy Progress dose for the current year has been determined.

Examinees Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:

Response

Result: SAT UNSAT Examiners Signature: Date:

2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET Name:

Date:

Initial Conditions: Two individuals are tasked to hang a clearance on 1CS-38, Letdown PCV Isol Vlv. The clearance includes the following valves:

. 1CS-35, Inlet lsol Vlv to LTDN PCV

. 1CS-36, Inlet lsol Vlv to LTDN PCV Drain Vlv

. 1CS-37, Inlet Isol to LTDN PCV Drain Vlv

. 1CS-38, Letdown PCV lsol Vlv.

. 1CS-39, Outlet lsol Vlv to LTDN PCV Drain Vlv

. 1CS-40, Outlet Isol to LTDN PCV Drain Isol Vlv

. 1CS-43, Outlet Isol Vlv to LTDN PCV Initiating Cue: Two Operators are being assigned to hang a clearance and perform work in a radiological area. Operator 1 has an accumulated annual Whole Body dose of 1750 mrem (Duke Energy Progress). Operator 2 has an accumulated annual Whole Body dose of 700 mrem (Duke Energy Progress) and worked at Nine Mile Point earlier this year where he has accumulated 2550 mrem.

The clearance and work activity is for 1CS-38, Letdown PCV lsol Vlv. The ALARA group has determined that additional shielding is not warranted for this work.

Using the supplied survey map, determine the maximum allowable individual stay times for each Operator that would prevent exceeding the Duke Energy Progress Annual Administrative dose limit while performing these activities.

Do not consider dose received during transit. The calculated dose should be ONLY what they would receive while working at the valves for the clearance.

Complete the information below and return to the evaluator when complete.

Record the maximum allowable stay time calculations below to the nearest hour and minute.

Operator 1: Operator 2:

2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

C]

ci)

Cc) 0 C,)

0 0::

f2

-,)

z C 0

S

-D C)

LU S

i S x

0 UJ U- C-)

z C) r-4 l 0

t -1 P r *3 fl . fl C]

z F C)

LU LU 999 C,)

LU r 0 I- CO as as ,-1 st sri 0 C-C- I C c Co 02 00 CC 00 CC 00 00 D

C-)

0 > -s i. - rs -s Co cc, Co o - Co Co Co Co Co Co Co Co

-)

h i- r -  ?-

z0 I

0 0 .0 CO ID CI Cs 0 Ci V C- fl 3 C- CO C, I4 *-4 II I-I

-- -S  ? CO CO CO CO C Ci CO fl CO 00 .

l,(,,fl 0000 LCOrlvo3 r- - C ID C-I Cfl fl 50 C-- 00 Ci 00 00 CC) 00 00 (0 (1) CC) (C) (C) (0 CC) (C) (C) (C) ., s C) C) U C) U U U U U U U U U U U . , ,S ,

s- s- 5 -4 .-4 s4

-4 c,., In - > -> - >

CO Os C) C-I Ci iC Cs 0 C- 00 Ci 0 19 (0 t fi C) C CO C (0 Cr, C 1 1 t ID CO IC) I Cs 0 I CO 0, 0 C) IC)

C 11 St Cs SC fl fl C C C Cs C fl 3, 1) 0 0 SC) 3 0 II

0) 0 0 C C I C-. C
__, cI - N - N o - N -
;i Os. N -, N 0i N N Co Co Co s. N Cc, O- ,, N Co N 0-. 0-, o,,

C) Ci C) C C C C-I CC) 6 00 Cc i CC)

(0 C-I St fl CS 00 Cc CC) st C C-- C 0 C) CC) 1 C Cs

,. (1 C-) C-I C) C-) (9 (0 CC) (0 (0 CC, C15 IC) CC) it CO C C-) Iii S S C Cs C Ci C fl Ci Ci Ci C, 0 0 0 C U CC) ( CC) 00 CC) CC) 1/) CC) 00 (0 (1) (0 00 5/) (0 CC) 5/) (0 I) CC) 5/) 1/) (0 (0 (0 5/) CC) (0 (0 .0 CC) CC) CC) CC) (I) CC)

C)C)UUUUC)UUQU UUUUUUUUUUUUUUUUUUUUQUUUUQ C Ifi 0) C-- C-) IC) C 0 C-- CC C ID

  • Si* S Cl C, st C SD C-- C) Ci 0 C-I fl CO CO (9(9 C) (9) C-) C-I CC) *t 3 C C-) CC (0 CC) (0CC)

Appendix C Form ES-C-I JPMCUESHEET RAB 236 LETDOWN & LETDOWN REHEAT MAP 21 HEAT EXCHANGERS/VALVE GALLERY 0

W*illi

\4)

V 8 1EH 24

,st Th 4 >

LE1DOVN fIX LI PHOTOGRAPHS V <

LVr; 1I! V EJRVEYS I AREA RAD MONITOR IARMI iI 2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET Map A45 RADIOLOGICAL SURVEY RECORD i-get 0tI link I BldgEIev: RAE 236 Arca LedownHX&VG Date:09/13/13 Ii 0735 RWP# Survey #0992-013 j

c0uponeDt: NJA Work  : Cleaiance and work on 1 CS-S S 1

scriprio

. Surveyor: A Tech Siature: by: B-. Bossrnann No entry required into letdown HX ro, no se1dnadd for job Lociion tt::.

3 6K floor (by dran) 4 lOOK locr 5 1.K floor (n.dr V21ar)

. 6 4K s <tic lCS-:35 AV/

Ii doQ N fl

/\12C 125 //

Th J1 10

/

10

-/______

Ji

% p 100 1nstnrnezt Serial NoJUTC RA Radiation Area BetaDeae Rare AirActiWty oi 341 t8 HRA IiAa r LRRA Locked adation Area R Reinfhour No__DAC_% . uC1cc K070 4w VI IRA V Hih1atiOn Area XXXX Bouedrny ARA Artw RadiationArea 0 S earLocation %ty uCitee / \ I CA Cenl.aminanonArea L A.r Saziple Locanon No.DAC-1000 rtctd A vty uCfcc QA Recerd 2013 NRC Exam Admin JPM RO SRO A3 Rev. 2

0 cy) 0 Cl) 0 0

E 2

(U uJ C-)

z C) 0 (N

I w

w (I) w D

C) 0

a) 0 Ci) 0 C

E

-D Cl) w 2 (5

2 x 0 w Li 0 z

0 I

w uJ I

Ci) w D

0 0

1F

Appendix C Job Performance Measure Form ES-C-I Worksheet Facility: Shearon-Harris Task No.: 345001 H602 Task

Title:

Classify an EAL JPM No.: 2013 NRC Exam Admin JPM SRO A4 K/A

Reference:

G2.4.41 R02.9SR04.6 Alternate Path: No Examinee: NRC Examiner:

Facility Evaluator: Date:

Method of testing: This JPM can be performed in any setting with the required references available.

Simulated Performance: Actual Performance: x Classroom X Simulator Plant READ TO THE EXAMINEE I will explain the initial conditions, which steps to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this Job Performance Measure will be satisfied.

You are the Site Emergency Coordinator.

Given the following plant conditions:

  • The plant is in Mode 1
  • A-SA Safety train is in service
  • AOP-016 is being performed due to a 12 gpm leak in C SG The following occurs at 1115:
  • Offsite Power is lost
  • Safety Injection actuates due to a steam leak inside Initial Conditions: containment
  • Containment pressure stabilizes at 3.6 psig At 1120:
  • BOP reports 1BD-20, Stm Gen B Bldn lsol. and 1BD-30 SA, Stm Gen B Bldn Isol failed to close automatically or manually
  • Sanford Substation Maintenance reports that their truck brakes failed and it has crashed into Breaker 52-13 damaging the breaker and the connecting transmission lines The time is now 1125:

For the above plant conditions, classify the event.

Initiating Cue: Evaluate the EAL Matrix and determine the highest classification required for these plant conditions. This is a time critical JPM.

2013 NRC Exam Admin JPM SRO A4 Rev. 2

Appendix C Job Performance Measure Form ES-C-i Worksheet Task Standard: Classify the highest EAL as an ALERT Required Materials: None General

References:

PEP-I 10 EAL Matrix PEP-i 10 EP-EAL (allowed reference)

Handouts:

  • Attached Initial Conditions
  • PEP-lb
  • PEP-lb EAL Matrix
  • EP-EAL Time Critical Task: YES 15 minutes for classification.

Validation Time: 15 minutes CRITICAL TASK JUSTIFICATION Classification of the event is critical for determining State and County Step I notifications, public information notices, site information notices, and event reportability to the Nuc[ear Regulatory Commission.

2013 NRC Exam Admin JPM SRO A4 Rev. 2

Appendix C Page 3 of 5 Form ES-C-i PERFORMANCE INFORMATION Evaluator Cue: Start Time for this portion of JPM begins when the individual has been briefed.

START TIME:

Performance Step: I Identify EAL Classification for events in progress.

Standard : The correct EAL is: Alert HA16 Vehicle crash resulting in EITHER:

Visible damage (Note 4) to any Table H-i structure containing systems or components required for safe shutdown of the plant OR Control Room indication of degraded performance of systems required for the safe shutdown of the plant (Table H-i)

Comments:

STOP TIME:

Terminating Cue: EAL classification(s) completed and provided to evaluator.

V - Denotes Critical Steps 2013 NRC Exam Admin JPM SRO A4 Rev. 2

Appendix C Page 4 of 5 Form ES-C-I VERIFICATION OF COMPLETION Job Performance Measure No.: 2013 NRC Exam Admin JPM SRO A4 Classify an Event Examinees Name:

Date Performed:

Facility Evaluator:

Number of Attempts:

Time to Complete:

Question Documentation:

Question:

Response

Result: SAT UNSAT Examiners Signature: Date:

2013 NRC Exam Admin JPM SRO A4 Rev. 2

Appendix C Form ES-C-i JPM CUE SHEET Name:

Date:

You are the Site Emergency Coordinator.

Given the following plant conditions:

. The plant is in Mode 1

. A-SA Safety train is in service

. AOP-016 is being performed due to a 12 gpm leak in CSG The following occurs at 1 1 15:

  • Offsite Power is lost

. Reactor trips on undervoltage for all 3 RCPs

. Safety Injection actuates due to a steam leak inside Initial Conditions: containment

. Containment pressure stabilizes at 3.6 psig At 1120:

. BOP reports 1BD-20, Stm Gen B Bldn Isol. and 1BD-30 SA, Stm Gen B Bldn Isol failed to close automatically or manually

  • Sanford Substation Maintenance reports that their truck brakes failed and it has crashed into Breaker 52-13 damaging the breaker and the connecting transmission lines The time is now 1125:

For the above plant conditions, classify the event.

Evaluate the EAL Matrix and determine the classification(s) required for these plant conditions.

Initiating Cue:

This is a time critical JPM.

EAL Classification:

EAL:

2013 NRC Exam Admin JPM SRO A4 Rev. 2