Lists Valves That Will Be Partially Disassembled,Inspected & Manually Stroked as Part of Inservice Test Program. Reassembly Will Not Disturb Moving Internals
ML13324A876
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 05/30/1986
From: Medford M
Southern California Edison Co
To: Lear G
Office of Nuclear Reactor Regulation
References
NUDOCS 8606030246
Download: ML13324A876 (2)


Text

Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 M.O.MEDFORD TELEPHONE MANAGER, NUCLEAR LICENSING (818) 302-1749 May 30, 1986 Director, Office of Nuclear Reactor Regulation Attention: Mr. G. E. Lear, Director PWR Project Directorate No. 1 Division of PWR Licensing -A U. S. Nuclear Regulatory Commission Washington D.C.,

20555 Gentlemen:

Subject:

Docket No. 50-206 In-Service Testing of Check Valves San Onofre Nuclear Generating Station, Unit 1 This letter is in response to NRC questions regarding the In-Service Testing (IST) program for pumps and valves for the San Onofre Nuclear Generating Station, Unit 1. Specifically, the check valves listed below will be partially disassembled, inspected and manually stroked as part of the IST program. We have determined that the valve designs are adequate to permit partial valve disassembly and then reassembly without disturbing the moving internals.

Group 1 Check valves DWS-306, DWS-309, DWN-306 and DWN-309 (Diesel Generator Cooling Water System)

Group 2 Check valves SIS-003, SIS-004 and SIS-010 (Safety Injection System)

Group 3 Check valves SIS-303 and SIS-304 (Safety Injection System)

Group 4 Check valves FWS-438 and FWS-439 (Feedwater and Condensate System) 6606030246 660530 PDR ADOCVK 05o0206 0

PDR

Mr. G.

May 30, 1986 These inspections will be fully implemented at the next San Onofre Unit 1 refueling outage with at least one valve in Groups 1, 2 and 3 and both valves in Group 4 being disassembled and inspected at each refueling.

If you have any questions, please call me.

Very truly yours, cc:

R. Dudley, NRC/NRR San Onofre Unit 1 Project Manager F. R. Huey, NRC Senior Resident Inspector, Units 1, 2 and 3

3. B. Martin, NRC Region V, Regional Administrator D. Dilanni (NRC)