Informs of Planned Insp Program for Plant During post-operational & Decommissioning Phases
ML13319B058
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 11/24/1993
From: Reese J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Scarano R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
NUDOCS 9312160012
Download: ML13319B058 (4)


Text

s RE~,

0 UNITED STATES NUCLEAR REGULATORY COMMISSION REGION V 1450 MARIA LANE WALNUT CREEK, CALIFORNIA 94596-5368 November 24, 1993 MEMORANDUM FOR:

Ross A. Scarano, Director Division of Radiation Safety & Safeguards FROM:

James H. Reese, Chief Facilities Radiological Protection Branch

SUBJECT:

PLANNED INSPECTION PROGRAM FOR SAN ONOFRE NUCLEAR PLANT UNIT-1 DURING THE POST-OPERATIONAL AND DECOMMISSIONING PHASES POST OPERATIONS HISTORY On November 30, 1992, SONGS Unit-1 permanently shutdown, and reactor defueling was completed on March 9, 1993. SCE submitted a preliminary decommissioning plan on December 1, 1992, and Permanently Defueled Technical Specification amendment on May 12, 1993.

Based on discussions with NRR-HQ, the SONGS Unit-1 PDTS may be out in December 1993.

POST OPERATIONS INSPECTION PLAN In accordance with NRC Inspection Manual Chapter 2561 the following inspection procedures will be utilized during the post-operational phase of SONGS Unit-1 in FY-94:

61726 Surveillance Observations 62703 Maintenance Observations 71707 Operational Safety Verification 81018 Security Plan & Implementing Procedures 81700 Physical Security Program for Power Reactors 83750 Occupational Exposure 84750 Radwaste Systems, Water Chemistry,and REMP 86700 Spent Fuel Pool Activities 86750 Solid Radwaste Management & Transportation 92701 Followup 9312160012 931124 PDR ADOCK 05000206 G

PDR

The inspection program will use a total of 75 hours8.680556e-4 days <br />0.0208 hours <br />1.240079e-4 weeks <br />2.85375e-5 months <br /> (55 hrs. for Project Engineering & Radiological Controls, and 20 hrs. for Security) in FY-94 at SONGS-1. Presently, the licensee intends to keep Unit-i in a SAFESTOR until year 2013, but begin some decommissioning activities in 2004.

Jn.eese, C ief a lities Radiological Protection Branch cc: J. Reese R. Pate D. Schuster F. Wenslawski bcc: M. Smith Central File

cc: J. Reese R. Pate D. Schuster F. Wenslawski bcc: M. Smith Central File EST COPY REQUE57'p PY (n

EQ UEST COPY S ND TO PDR NO rOYE

/NO, E'/NO

/NO L

JRee RPate 1 Vfg93 11 1.19 3 11/-019 3 NTO DCS 1.9S NO

FORD 1 REGULAWY INFORMATION DISTRIBUTIWSYSTEM (RIDS)

ACCESSION NBR:9312160012 DOC.DATE: 93/11/24 NOTARIZED: NO DOCKET #

FACIL:50-206 San Onofre Nuclear Station, Unit 1, Southern Californ 05000206 AUTH.NAME AUTHOR AFFILIATION REESE,J.H.

Region 5 (Post 820201)

RECIP.NAME RECIPIENT AFFILIATION SCARANOR.A.

Region 5 (Post 820201)

SUBJECT:

Informs of planned insp program for plant during B

post-operational & decommissioning phases.

DISTRIBUTION CODE: IEO1D COPIES RECEIVED:LTR / ENCL 0 SIZE:

TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response D

NOTES:License Exp date in accordance with 10CFR2,2.109 05000206 RECIPIENT COPIES RECIPIENT COPIES F

ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL ONDB PD 1

BROWN,S 1

0 INTERNAL: ACRS 2

AEOD/DEIB I

R AEOD/DSP/ROAB 1

AEOD/DSP/TPAB 1

AEOD/TTC 1

DEDRO 1

NRR/DORS/OEAB 1

NRR/DRCH/HHFB 1

NRR/DRIL/RPEB 1

NRR/DRSS/PEPB 1

NRR/PMAS/ILPB1 1

NRR/PMAS/ILPB2 1

NUDOCS-ABSTRACT 1

OE DIR 1

1 OGC/HDS3 1

1 R

FIL 02 1

RES/HFB 1

1 RGNB FILE 01 1

D EXTERNAL: EG&G/BRYCEoJ.H.

1 NRC PDR 1

NSIC 1

C M

N NOTE TO ALL 'RIDS" RECIPIENTS:

PLEA SE HELP 'S TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK.

ROOM P-37 (EXT. 504-2065) TO ELIMINATE YOUR NA.ME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 24 ENCL