Southern California Edison Company P.
. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD. CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING, M
22 1982 (213) 572-1401 SAFETY, AND LICENSING m
Director, Office of Nuclear Reactor Regulation Attention:
D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Gentlemen:
Subject:
Docket No.P50-206 SEP Topic 111-6 Seismic Design Considerations 0
4 San Onofre Nuclear Generating Station Unit 1 By letter dated November 3, 1981, we indicated that the se C1 reevaluation of cable trays at San Onofre Unit 1 would be completed by March 1, 1982. As our evaluation program has proceeded since that time, this schedule has been affected by the analysis requirements and by access limitations during plant operation.
In light of these considerations, the schedule for these evaluations has been delayed as previously discussed with the NRC Staff.
We anticipate completion of the evaluation of cable trays in all normally accessible areas by April 12, 1982. For cable trays which are in areas where access was limited during normal operation, namely, the containment and switchgear rooms, we anticipate completion of the evaluation by May 1, 1982. In view of these schedules for completion of the evaluations, we currently anticipate submittal of a report discussing all of these evaluations by about May 15, 1982.
If you have any questions or wish to further discuss this matter, please let us know.
Very truly yours, 92033102L4 920322 PDR ADOCK 05000206 2