Requests That Full Operational Capability Date for Implementation of Emergency Operations Facility,Per TMI Action Item III.A.2,be Revised to 830101.Schedule Could Be Disrupted by Weather,Labor Conditions or Matl Delays
ML13317A868
Person / Time
Site: San Onofre  
Issue date: 02/11/1982
From: Baskin K
Southern California Edison Co
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737, TASK-3.A.2.2, TASK-TM NUDOCS 8202160326
Download: ML13317A868 (1)


Text

Southern California Edison Company P. 0. BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD. CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING, SAFETY, AND LICENSING February 11, 1982 Director, Office of Nuclear Reactor Regulation Attention:

Mr. Darrell G. Eisenhut, Director U. S. Nuclear Regulatory Commission Washington, D.C.

20555 Gentlemen:

Subject:

Docket Nos. 50-206, 50-361 and 50-362 San Onofre Nuclear Generating Station Units 1, 2 and 3 SCE's letter of February 2, 1981, indicated that the requirements of NUREG-0737, Item III.A.2 -

"Improving Licensee Emergency Preparedness - Long Term," would be satisfied consistent with the implementation schedule specified in NUREG-0737.

Subsequently the NRC's letter of February 18, 1981, provided further clarification of this item, along with proposed implementation dates, and requested a revised date and justification be proposed for any dates that could not be met. SCE's letter of July 1, 1981, stated that the Emergency Operating Facility for San Onofre, "is expected to be operational by October 1, 1982," on the basis of project status at that time.

A detailed review of current project schedules indicate that SCE is on schedule for compliance with the October 1, 1982 target date, however, there are no allowances in the schedule for potential adverse weather conditions, material delays or labor relations problems.

Should any of these unforeseen delays evolve, this target date will be in jeopardy.

Consequently, even though the San Onofre Emergency Operating Facility is currently under construction and will continue to be targeted for completion by October 1, 1982, we request that the "full operational capability" date be revised to January 1, 1983.

If there are any questions or comments regarding the above, please contact me.