Southern California Edison Company P. 0. BOX 800 2244 WALNUTGROVEAVENUE
- ROSEMEAD, CALIFORNIA 91770 K. P. BASKIN TELEPHONE MANAGER OF NUCLEAR ENGINEERING.
September 28, 1982 (213) 572-1401 SAFETY, AND LICENSING Director, Office of Nuclear Reactor Regulation Attention: D. M. Crutchfield, Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C.
20555 Gentlemen:
Subject:
Docket 50-206 Safety Injection System Modifications San Onofre Nuclear Generating Station Unit 1 Our letter dated March 30, 1982 provided the schedule for replacement of the Safety Injection System Hydraulic Valves, and the status of a study of an alternative of modifying the Safety Injection System based on a dedicated SI system (new feedwater pumps) design. We indicated that replacement valves were ordered and could be installed during the first refueling outage following valve delivery in late 1984. We also indicated that as an alternative to replacing the hydraulic valves, we were continuing to perform preliminary engineering on a dedicated SI system to determine feasibility, cost and schedule. The purpose of this letter is to inform you that we have chosen to establish a dedicated SI system (new feedwater pumps) alternative and are cancelling our order for replacement valves.
An overview of the dedicated SI system was provided to representatives of the Regulatory Staff during a meeting on September 8, 1982. to this letter provides, more detailed information on the conceptual design of the dedicatedS&I-system alternative. In summary, this system relies on a set of new feedw ter pumps which would allow the current feedwater/SI pumps to become dedicated to the SI function, This design eliminates the need for extensive sequenci-ngiand interlocking of the eight hydraulic valves. A new power sour e wil1'be-incorporated to power the new feedwater pumps.
As indicated in the sched 6fE nclosure1 to this letter, these modifications are scheduled to be *inIp&ented during; the refueling outage for 6209300292 820928 PDR ADOCK 05000206 P
Mr. D. M. Crutchfield
-2 Cycle 10 which should occur in mid-1985.
It should be noted that this date is equivalent to the implementation date for the replacement valves project, now being terminated. It is our intention to adhere to this schedule. However, should other major projects be given higher priority during the integrated assessment, the schedule may require adjustment.
If you have any questions in this matter, please contact me.
Very truly yours, Enclosure
Enclosure SAFETY INJECTION SYSTEM MODIFICATIONS SAN ONOFRE NUCLEAR-GENERATING STATION, UNIT 1 SI PUMPS DEDICATION/NEW FEEDWATER PUMPS CONCEPTUAL DESIGN INFORMATION BACKGROUND Reference A describes an event at San Onofre Unit 1 which involved the failure of the Hydraulic Valves between the safety injection/feedwater pumps and the safety injection system headers.
This failure resulted in a modification of these valves and implementation of an interim SIS valve surveillance program.
In Reference 3, SCE committed to submit a schedule for replacement of the hydraulic valves and to study SIS design and performance to determine if major redesign is warranted. Reference C provided the status of the valve replacement project and a conceptual assessment of SIS redesign based on three alternatives.
Reference D provided a schedule for replacement of the valves, further results of our conceptual engineering of design alternatives, and our committment to further study the Dedicated SI Pumps alternative design to determine if redesign is warranted.
On September 8, 1982 at a meeting with members of the Regulatory Staff, our decision to proceed with SIS redesign based on a dedicated SIS pumps/new feedwater pumps concept was discussed. This enclosure presents the conceptual description of the system as presented at that.meeting. A description of any major refinements will be submitted if they become necessary during further preliminary and final engineering.
OBJECTIVE OF REDESIGN The objective of the SIS redesign is to minimize the reliance on extensive sequencing of the SIS hydraulic valves at San Onofre Unit 1. An alternative design is being engineered to have minimum impact on existing systems and components.
DEDICATED SIS/NEW FEEDWATER PUMPS SYSTEM DESCRIPTION General Description The feedwater pumps at San Onofre Unit 1 currently have dual functions.
They are used to supply feedwater to steam generators during normal operation and inject borated water to the reactor for emergency cooling when needed.
Figure 1 represents the schematic flow diagram of the as-built system for reference.
The switchover from the feedwater function to safety injection function relies on the alignment of the safety injection system valves (HV 851 A & 8, HV 852 A & B, HV 853 A & B, and HV 854 A & B) located upstream and downstream of the feedwater pumps.
Due to the failure of HV's 851 A & B in 1981, a conceptual study has been conducted with the objective of separating the feedwater and safety injection systems so that the safety injection function would not rely on the alignment of these valves.
The addition of new dedicated feedwater pumps has been selected as the best method of separating these systems.
-2 The new feedwater pump modification includes the addition of a pair of feedwater pumps with the associated piping, valves, power source, instrumentation and controls.
These modifications will leave the existing feedwater pumps, currently shared by the feedwater and safety injection systems to be exclusively available for the safety injection function.
- Thus, the feedwater system and safety injection system will be separated. The only modifications to the SIS will be capping off piping connections previously associated with the feedwater system, and modifying electrical and control circuits to reflect the system design.
Figure 2 shows the proposed modifications to the existing piping and the new feedwater pump arrangement. Additional piping, isolation valves (HV-852 and HV-854 valves may be salvaged for this purpose), and check valves for the new feedwater pumps will be required. The low pressure and the high pressure heater bypass connections, located upstream and downstream of the existing feedwater pumps, and the flow elements (FE13 and 14) for both east and west feedwater trains will be left intact.
The feedwater recirculation lines will be rerouted to the.new pumps.
For the west feedwater train, the manual auxiliary feedwater flow path connection will be relocated.
A new power source will be provided to feed the new feedwater pumps.
As-built instrumentation and controls common to both the safety injection and feedwater systems will be dedicated to the safety injection system operation.
All instrumentation and controls used exclusively for the as-built feedwater system will be utilized in the new feedwater trains.
Implementation of this modification will eliminate the need for valve sequencing between the feedwater and safety injection systems. Replacement valves will no longer be required and are being cancelled. Once the systems are separated, there will not be continuous pressure from the feedwater system on the hydraulic valves (HV853 A&B and HV851 A&B).
This will eliminate the high pressure on the valve seats which contributed to the earlier problems.
In addition, by isolating the two systems the valves will no longer require sequencing and interlocks to prevent condensate from being supplied to the SIS. The requirement for maintaining the remaining SIS valves normally closed will be further evaluated as engineering progresses.
Feedwater Pumps A.
New Feedwater Pump Configuration Two new feedwater pumps, one for each train, with performance characteristics of the existing feedwater pumps are required. Major pump manufacturers have preliminarily indicated that pumps meeting specified hydraulic requirements can be delivered with a lead time between 10 and 15 months.
-3 B. New Pump Locations Various possible locations on the east and west side of the plant were evaluated primarily based on physical feasibilities, comparison of turbine cycle efficiency, and degree of physical modification required. Some locations were eliminated due to lack-of space or the necessity of extensive physical modifications.
However, studies conducted to date indicate that there are locations on both sides of the turbine building that could meet the requirements for locating the new pumps.
Power Supply A non-safety related power supply dedicated to the new feedwater pumps motors will be required for this design.
A new 30 MVA, 230 kV-4.36 kV, 3 0 transformer, similar to the existing spare "C" transformer, with a provision for installation of FA/FA cooling, will be installed.
The new transformer is presently planned to be installed near the fence at the south side of the plant with the switchgear room located nearby.
Control and Logic Modification The control logic for the following components will require revision to implement the proposed design.
- a.
SI discharge valves HV-851 A & B, b
SI suction valves HV-853 A & B,
- c.
FW discharge valves HV-852 A & B,
- d.
FW suction valves HV-854 A & B,
- e. Feedwater pump recirculation valves CV875 A & B,
- f. Feedwater pump recirculation valves CV36 and CV37,
- g. Condensate and feedwater pumps' start/stop controls.
SCHEDULE Figure 3 represents a conceptual schedule for performing engineering, procurement and construction to modify the Safety Injection System by adding two new feedwater pumps.
FRM. COND. PUMPS 70 STEAM GENERAToRS pwsT V
cy 7.5A 36 CONTAINAfNT 852A dTHELL S/S V
SPUMPS eO. opC S/S CO& D LEG FRM. CONO. PUMPS 70 57M GEWEAroRS 1s st s/s am-i 8548 LOQP B
1---
r S/
COLO L EG oAo C O L D O L
- FEtbWATE,
/i///'
4.38 AS S//LTS YT 4f
- lr
/S/
r91~//A~/
TO 77/F EX/37/A TO/tPFHPATE
- - a PIN HIJ/A
/4
/2 F
3"EPIPS
-N--
-3 (FOR WESTr1/MPOCA/LY) sea SA 7 Y A / E C O A F 14
_1 _A)
TO IPC,5 I
I 5/5 RECl/A7/O 3" "1 70 PEFI /// W -
57-ORAGE TANK1 T--T r-/2" XS 4r-7 FEEFE WA 7ER,6 0 A6P (F02A WEW$7P P A
)---
SEA WArZ AV I
WA 11ON 4
/II
/xEP 5Nre J02fSEALITERPR/RA-SEA/ TPRR SEAZ WAE____-
RI ONES7
&/
FRM O/.FRATER//
'19 8 2 I1 9 8 3 1 9 8 4 N1 9 8 5 1 9 8 6 J FMAM J J AS 0 N D J FMAM J J AS 0 NDJ FMAM J J AS D J FMAM J J A S 0 ND J FMAM J C Y CLE 8 C Y CLE 9
-C Y CLE 10 EVENTS Seismic Upgrade-
-Normal Operation -
Refueing -Normal Operation Refueling I
& Integrated Assess-SEP Modifications rent Feed Pumps OUTAGES SIS VALVES (now being cancelled)
Valve Delivery NEW FEEDWATER PUMPS Theoretical Turrent Implementation Schedule INTEGRATED SCHEDULE Figure 3